Sp 70.133 30.2012 load-bearing and enclosing structures. Bearing and enclosing structures. Requirements for surface quality and appearance of monolithic concrete and reinforced concrete structures


"This set of rules has been developed in order to improve the quality of construction and installation works, the durability and reliability of buildings and structures, as well as the level of safety of people at the construction site, the safety of material assets in accordance with the Federal Law dated , increasing the level of harmonization of regulatory requirements with European and international regulatory documents, the use of uniform methods for determining performance characteristics and evaluation methods.
This set of rules applies to the production and acceptance of work performed during the construction and reconstruction of enterprises, buildings and structures in all sectors of the national economy:
in the construction of monolithic concrete and reinforced concrete structures from heavy, extra heavy, on porous aggregates, heat-resistant and alkali-resistant concrete, in the production of shotcrete and;
in the manufacture of prefabricated concrete and reinforced concrete structures in the conditions of a construction site;
during the installation of prefabricated reinforced concrete, steel, wooden structures and structures made of light efficient materials;
when welding assembly joints of building steel and reinforced concrete structures, reinforcement joints and embedded products of monolithic reinforced concrete structures;
in the production of works on the construction of stone and reinforced masonry structures from ceramic and silicate bricks, ceramic, silicate, natural and concrete stones, brick and ceramic panels and blocks, concrete blocks.
The requirements of this set of rules should be taken into account when designing the structures of buildings and structures.
When erecting special structures - roads, bridges, pipes, steel tanks and gas tanks, tunnels, subways, airfields, hydraulic engineering reclamation and other structures, as well as when erecting buildings and structures on permafrost and subsidence soils, undermined territories and in seismic areas, additional be guided by the requirements of the relevant regulatory documents.

Foreword
About the set of rules
Introduction
1 area of ​​use
2. Regulatory references
3. General requirements
4. Installation of steel structures
4.1. General provisions
4.2. Preparation of structures for installation
4.3. pre-assembly
4.4. Installation, alignment and fastening
4.5. Bolted field connections without controlled tension
4.6. Mounting connections on bolts, including high-strength, with controlled tension
4.7. Special field connections
4.8. Field welded joints
4.9. Structural prestressing
4.10. Testing of structures and structures
4.11. Additional rules for the installation of structures of one-story buildings
4.12. Requirements for acceptance control
4.13. Additional rules for the installation of structures of multi-storey buildings
4.14. Ensuring the stability of the main structural elements during installation
4.16. Installation of structures of structural coatings
4.15. Installation of built-in structures
4.17. Mounting structures of suspended cable-stayed roofs
4.18. Installation of membrane coating structures
4.19. Additional rules for the installation of structures of conveyor galleries
4.20. Additional rules for the installation of structures of antenna communication structures and chimney towers
4.21. Dismantling and installation of facility structures during the reconstruction of existing production facilities
4.22. Installation and dismantling of structures using helicopters
5. Concrete work
5.1. Materials for heavy and fine-grained concrete
5.2. Concrete mixtures
5.3. Substrate preparation and concrete placement
5.4. Curing and care of concrete
5.5. Quality control of concrete in structures
5.6. Concrete on porous aggregates
5.7. Acid and alkali resistant concretes
5.8. Prestressing concretes
5.9. Heat-resistant concrete
5.10. Concrete especially heavy and for radiation protection
5.11. Production of concrete works at negative temperatures
5.12. Concrete work at air temperatures above 25 °C
5.13. Special concreting methods
5.14. Cutting expansion joints, technological grooves, openings, holes and surface treatment of monolithic structures
5.15. Seam cementation. Shotcrete and sprayed concrete works
5.16. Reinforcing works
5.17. Formwork
5.18. Acceptance of concrete and reinforced concrete structures or parts of structures
6. Installation of prefabricated reinforced concrete and concrete structures
6.1. General instructions
6.2. Construction of bases and foundations
6.3. Installation of columns and frames
6.4. Installation of crossbars, beams, trusses, floor slabs and coatings
6.5. Installing wall panels
6.6. Installation of ventilation units, volumetric units of elevator shafts and sanitary cabins
6.7. Construction of buildings by lifting floors
6.8. Welding and anti-corrosion coating of embedded and connecting products
6.9. Sealing joints and seams
6.10. Water, air and vapor permeability, heat and sound insulation of joints of external walls and mounting units adjoining window and door blocks to wall openings
7. Installation of light enclosing structures
7.1. General requirements for the installation of lightweight building envelopes
7.2. Enclosing structures made of chrysotile cement sheets, extrusion panels and slabs
7.3. Installation of metal enclosing roof structures of sheet assembly and sandwich panels
7.4. Hinged ventilated facades
7.5. Sheathed frame partitions
7.6. Walls made of sandwich panels and sheet assembly
8. Installation of wooden structures
8.1. General provisions for the acceptance and installation of wooden structures
8.2. Installation of wooden columns and racks
8.3. Installation of glued wooden beams
8.4. Installation of wooden prefabricated trusses
8.5. Installation of glued wooden arches and frames
8.6. Installation of ribbed domes made of laminated wood
8.7. Installation of wall panels and floor slabs
9. Stone structures
9.1. General provisions for the construction of stone structures
9.2. Masonry from ceramic and silicate bricks, from ceramic, concrete, silicate and natural stones of the correct form
9.3. Masonry of multilayer lightweight exterior walls. Load-bearing exterior walls
9.4. Non-bearing (hinged) multilayer walls
9.5. Requirements for structures and materials of the front layer of multilayer walls
9.6. Wall masonry made of large-format ceramic hollow stones
9.7. Wall masonry made of large silicate blocks
9.8. Wall cladding during masonry construction
9.9. Features of masonry arches and vaults
9.10. Masonry from rubble stone and rubble concrete
9.11. Additional requirements for the performance of work in seismic regions
9.12. Construction of stone structures in winter conditions
9.13. Masonry with antifreeze additives
9.14. Laying on solutions without antifreeze additives, followed by hardening of structures by heating
9.15. Freezing masonry
9.16. Quality control of works
9.17. Strengthening of stone structures of reconstructed and damaged buildings
9.18. Acceptance of stone structures
10. Welding of field joints of building structures
10.1. General provisions
10.2. Assembly and welding of field joints of steel structures
10.3. Assembly and welding of field joints of reinforced concrete structures
10.4. Quality control of welded joints in steel structures 10.5. Quality control of welded joints
during the installation of reinforced concrete structures
Annex A
(mandatory)

Annex B
(mandatory)
Calculation of the stability of structural elements
Annex L
(recommended)
Scope of cements in construction
Annex M
(mandatory)
Materials for concrete and solutions
Annex H
(recommended)
Scope of additives in concrete (GOST 24211)
Appendix P
(recommended)
Selection of the most economical method of curing concrete during winter concreting of monolithic structures
Annex P
(recommended)
Recommended grades of powder and bond of diamond tools for processing concrete and reinforced concrete
Appendix C
(mandatory)
Loads and data for the calculation of the formwork of monolithic concrete and reinforced concrete structures (GOST R 52085)
Appendix T
(reference)
Binders for masonry mortars and their compositions
Appendix Y
(reference)
Antifreeze and plasticizing additives in solutions, conditions for their use and expected strength of the solution
Annex F
(mandatory)
N
Annex X
(recommended)
Requirements for surface quality and appearance of monolithic concrete and reinforced concrete structures bibliography

Bearing and enclosing structures
updated version of SNiP 3.03.01-87 - current status

Requirements for surface quality and appearance of monolithic concrete and reinforced concrete structures

To assess the quality of the surface of monolithic concrete and reinforced concrete structures, four classes are used, determined by the maximum tolerances for straightness and local irregularities given in Table X.1. The classes apply to floors, walls, columns, foundations and other structures with straight surfaces. The main purpose of concrete surfaces is given in Table X.2. The concrete surface class of monolithic structures and the quality of concrete surfaces with special requirements for appearance should be specified in the project documentation. In unspecified cases, the surface class is accepted as A6 or A7 (depending on the purpose).

Table X.1. Annex X. SP 70.13330.2012

Concrete surface classes

Concrete surface class

Straightness tolerances for measured distances, mm

local irregularities (0.1 m)

Note. Straightness tolerances are applied subject to the tolerances for the thickness of the protective layer and for the dimensions of the sections (thicknesses) of the elements.

Table X.2. Annex X. SP 70.13330.2012

The main purpose of concrete surfaces of monolithic structures

Concrete surface class

The main purpose of structural surfaces

The front surface of walls, columns and the lower surface of floors with increased requirements for appearance. Surface for improved painting without putty

The front surface of the walls, columns and the lower surface of the ceilings, prepared for finishing (pasting with wallpaper, cladding)

The front surface of walls, columns, the lower surface of ceilings without special requirements for surface quality. Unfinished or plain painted surface

Minimum requirements for the quality of the concrete surface. Plastered and concealed surfaces

The project documentation should specify additional requirements for concrete surfaces that are constantly exposed to moving water or other aggressive influences.

Requirements for curved curved surfaces should be specified in the design documentation separately.

On concrete surfaces are not allowed:

  • areas of uncompacted concrete;
  • grease stains and rust stains (except for class A7 surfaces);
  • exposure of reinforcement, except for working outlets of reinforcement and mounting fasteners of the formwork;
  • exposure of steel embedded products without anti-corrosion treatment;
  • cracks with an opening width specified by the design organization (recommended value is 0.1 mm for structures without protection from atmospheric precipitation, 0.2 mm - indoors);
  • sinks, chipped concrete ribs for surface class:
    • A3 - shells with a diameter of more than 4 mm, a depth of more than 2 mm, chips of a rib 5 mm deep, a total length of more than 50 mm per 1 m of the rib;
    • A4 - shells with a diameter of more than 10 mm, a depth of more than 2 mm, chips of a rib 5 m deep, a total length of more than 50 mm per 1 m of the rib;
    • A6 - shells with a diameter of more than 15 mm, a depth of more than 5 mm, chips of a rib 10 mm deep, a total length of more than 100 mm per 1 m of the rib;
    • A7 - shells with a diameter of more than 20 mm and chipped ribs with a depth of more than 20 mm, the length of the chips is not regulated.

Local irregularities (beads, protrusions or depressions), the dimensions of which exceed the tolerances for surface classes according to Table C.1 at a measured distance of 0.1 m. For surfaces of class A3, nodules and protrusions are not allowed.

On concrete surfaces are allowed:

  • for wall structures - holes for tie rods with plastic protective tubes of the tie left in them, holes for anchors (sealing of holes should be specified in the project documentation or PPR separately);
  • imprints of boards and formwork elements;
  • exposure of reinforcing clamps;
  • for the lower surface of the floors - imprints of boards and deck elements, fastening elements of plastic structures, electrical wiring, etc.

To meet the requirements for concrete surfaces of classes A3 and A4, grinding of local protrusions and grouting of local depressions is recommended to achieve the required performance.

1 area of ​​use

1.1 This set of rules applies to the production and acceptance of work performed during the construction and reconstruction of enterprises, buildings and structures in all sectors of the national economy: in the construction of monolithic concrete and reinforced concrete structures from heavy, extra heavy, porous aggregates, heat-resistant and alkali-resistant concrete, production of works on shotcrete and underwater concreting; in the manufacture of prefabricated concrete and reinforced concrete structures in the conditions of a construction site; during the installation of prefabricated reinforced concrete, steel, wooden structures and structures made of light efficient materials; when welding assembly joints of building steel and reinforced concrete structures, reinforcement joints and embedded products of monolithic reinforced concrete structures; in the production of works on the construction of stone and reinforced masonry structures from ceramic and silicate bricks, ceramic, silicate, natural and concrete stones, brick and ceramic panels and blocks, concrete blocks. The requirements of this set of rules should be taken into account when designing the structures of buildings and structures.

1.2 When erecting special structures - roads, bridges, pipes, steel tanks and gas tanks, tunnels, subways, airfields, hydraulic engineering reclamation and other structures, as well as when erecting buildings and structures on permafrost and subsidence soils, undermined territories and in seismic areas, be additionally guided by the requirements of the relevant regulatory documents.

2.1 This set of rules uses references to the following regulatory documents: GOST 379-95 Brick and silicate stones. Specifications GOST 450-77 Technical calcium chloride. Specifications GOST 530-07 Ceramic brick and stone. General specifications GOST 828-77 Technical sodium nitrate. Specifications GOST 965-89 White Portland cements. Specifications GOST 969-91 Aluminous and high aluminous cements. Specifications GOST 1581-96 Oil-well portland cements. Specifications GOST 2081-2010 Carbamide. Specifications GOST 2246-70 Welding steel wire. Specifications GOST 3242-79 Welded joints. Quality control methods GOST 5264-80 Manual arc welding. Connections are welded. Main types, structural elements and dimensions GOST 5578-94 Crushed stone and sand from slags of ferrous and non-ferrous metallurgy for concrete. Specifications GOST 5686-94 Soils. Field test methods for piles GOST 5802-86 Building mortars. Test methods GOST 6402-70 Spring washers. Specifications GOST 6996-66 Welded joints. Methods for determining mechanical properties GOST 7076-99 Building materials and products. Method for determining thermal conductivity and thermal resistance under stationary thermal conditions GOST 7473-2010 Concrete mixes. Specifications GOST 7512-82 Non-destructive testing. Connections are welded. Radiographic method GOST 7566-94 Steel products. Acceptance, marking, packaging, transportation and storage GOST 8267-93 Crushed stone and gravel from dense rocks for construction work. Specifications GOST 8269.0-97 Crushed stone and gravel from dense rocks and industrial waste for construction work. Methods of physical and mechanical tests GOST 8713-79 Submerged arc welding. Connections are welded. Main types, structural elements and dimensions GOST 8735-88 Sand for construction work. Test methods GOST 8736-93 Sand for construction work. Specifications GOST 9087-81 Fused welding fluxes. Specifications GOST 9206-80 Diamond powders. Specifications GOST 9467-75 Coated metal electrodes for manual arc welding of structural and heat-resistant steels. Types GOST 9757-90 Gravel, crushed stone and sand, artificial porous. Specifications GOST 9758-2012 Porous inorganic aggregates for construction work. Test methods GOST 10060-2012 Concrete. Methods for determining frost resistance GOST 10178-85 Portland cement and Portland slag cement. Specifications GOST 10180-90 Concrete. Methods for determining strength according to control samples GOST 10181-2000 Concrete mixes. Test methods GOST 10243-75 Steel. Methods for testing and evaluating the macrostructure GOST 10541-78 Universal motor oils and for automobile carburetor engines. Specifications GOST 10690-73 Commercial potassium carbonate (potash). Specifications GOST 10832-2009 Expanded perlite sand and crushed stone. Specifications GOST 10906-78 Oblique washers. SpecificationsGOST 10922-90 Reinforcing and embedded products, their welded, knitted and mechanical connections for reinforced concrete structures. General specifications GOST 11052-74 Expanding gypsum alumina cement GOST 11371-78 Washers. Specifications GOST 11533-75 Automatic and semi-automatic submerged arc welding. Connections are welded at acute and obtuse angles. Main types, structural elements and dimensions GOST 11534-75 Manual arc welding. Connections are welded at acute and obtuse angles. Main types, structural elements and dimensions GOST 12730.5-84 Concrete. Methods for determining water resistance GOST 12865-67 Expanded vermiculite GOST 13015-2003 Concrete and reinforced concrete products for construction. General technical requirements. Rules for acceptance, marking, transportation and storage GOST 13087-81 Concrete. Methods for determining abrasion resistance GOST 14098-91 Welded fittings and embedded products of reinforced concrete structures. Types, designs and dimensions GOST 14771-76 Arc welding in shielding gas. Connections are welded. Basic types, structural elements and dimensions GOST 14782-86 Non-destructive testing. Connections are welded. Ultrasonic methods GOST 15150-69 Machines, instruments and other technical products. Versions for different climatic regions. Categories, conditions of operation, storage and transportation in terms of the impact of climatic factors of the environment GOST 15164-78 Electroslag welding. Connections are welded. Main types, structural elements and dimensions GOST 15825-80 Colored Portland cement. Specifications GOST 16037-80 Welded steel pipeline joints. Basic types, structural elements and dimensions GOST ISO/IEC 17025-2009 General requirements for the competence of testing and calibration laboratories GOST 17624-87 Concrete. Ultrasonic method for determining the strength of GOST 18105-2010 Concrete. Rules for control and evaluation of strength GOST 18442-80 Non-destructive testing. capillary methods. General requirements GOST 19906-74 Technical sodium nitrite. Specifications GOST 20276-99 Soils. Methods for field determination of strength and deformability characteristics GOST 20799-88 Industrial oils. Specifications GOST 20850-84 Glued wooden structures. General specifications GOST 20910-90 Heat-resistant concrete. Specifications GOST 21104-75 Non-destructive testing. Ferroprobe method GOST 21105-87 Non-destructive testing. Magnetic particle method GOST 21779-82 System for ensuring the accuracy of geometric parameters in construction. Technological tolerances GOST 21780-2006 System for ensuring the accuracy of geometric parameters in construction. Accuracy calculationGOST 22263-76 Crushed stone and sand from porous rocks. Specifications GOST 22266-94 Sulphate-resistant cements. Specifications GOST 22690-88 Concrete. Determination of strength by mechanical methods of non-destructive testing GOST 22845-85 Electric passenger and freight elevators. Rules for the organization, production and acceptance of installation work GOST 23118-99 Steel building structures. General specifications GOST 23407-78 Inventory fencing of construction sites and sites for the production of construction and installation works. Specifications GOST 23518-79 Shielded arc welding. Connections are welded at acute and obtuse angles. Basic types, structural elements and dimensions GOST 23683-89 Petroleum solid paraffins. Specifications GOST 23732-2011 Water for concrete and mortar. Specifications GOST 23858-79 Welded butt and tee fittings for reinforced concrete structures. Ultrasonic quality control methods. Acceptance rules GOST 24045-2010 Bent steel sheet profiles with trapezoidal corrugations for construction. Specifications GOST 24211-2008 Additives for concrete and mortar. General specifications GOST 24379.0-80 Foundation bolts. General specifications GOST 24846-81 Soils. Methods for measuring deformations of the foundations of buildings and structures GOST 25192-82 Concrete. Classification and general technical requirements GOST 25225-82 Non-destructive testing. Seams of welded joints of pipelines. Magnetographic method GOST 25246-82 Chemically resistant concretes. Specifications GOST 25328-82 Cement for mortars. Specifications GOST 25485-89 Cellular concrete. Specifications GOST 25592-91 Ash and slag mixtures from thermal power plants for concrete. Specifications GOST 25818-91 Fly ash from thermal power plants for concrete. Specifications GOST 25820-2000 Lightweight concrete. Specifications GOST 26271-84 Flux-cored wire for arc welding of carbon and low-alloy steels. General specifications GOST 26633-91 Heavy and fine-grained concrete. Specifications GOST 26644-85 Crushed stone and sand from slags of thermal power plants for concrete. Specifications GOST 26887-86 Platforms and ladders for construction and installation works. General specifications GOST 27005-86 Lightweight and cellular concrete. Rules for the control of average density GOST 27006-86 Concrete. Rules for selecting the composition of GOST 28013-98 Building mortars. General specifications GOST 28570-90 Concrete. Methods for determining the strength of samples taken from structuresGOST 30515-97 Cements. General specifications GOST 30971-2002 Mounting seams for adjoining window blocks to wall openings. General specifications GOST 31108-2003 General construction cements. Specifications GOST 31384-2008 Protection of concrete and reinforced concrete structures against corrosion. General technical requirements GOST 12.1.046-85 SSBT. Construction. Lighting standards for construction sites GOST R 12.4.026-2001 SSBT. Signal colors, safety signs and signal markings. Purpose and rules of application. General technical requirements and characteristics. Test methods GOST R 51254-99 Mounting tool for normalized tightening of threaded connections. Keys are momentary. General specifications GOST R 51263-99 Polystyrene concrete. Specifications GOST R 51634-2000 Autotractor motor oils. General technical requirements GOST R 52085-2003 Formwork. General specifications GOST R 52752-2007 Formwork. Test methods SP 15.13330.2012 "SNiP II-22-81* Stone and reinforced masonry structures" SP 16.13330.2011 "SNiP II-23-81* Steel structures" SP 20.13330.2011 "SNiP 2.01.07-85* Loads and impacts" SP 25.13330.2012 SNiP 2.02.04-88 Foundations and foundations on permafrost and foundations" SP 46.13330.2012 "SNiP 3.06.04-91 Bridges and pipes" SP 48.13330.2011 "SNiP 12-01-2004 Organization of construction" SP 50.13330.2012 "SNiP 23-02-2003 Thermal protection of buildings" SP 130.13330. 2011 "SNiP 3.09.01-85 Production of precast concrete structures and products"

Note- When using this set of rules, it is advisable to check the effect of reference standards in the public information system - on the official website of the national bodies of the Russian Federation for standardization on the Internet or according to the annually published information index "National Standards", which was published as of January 1 of the current year, and according to the corresponding monthly published information signs published in the current year. If the referenced document is replaced (modified), then when using this set of rules, one should be guided by the replaced (modified) document. If the referenced document is canceled without replacement, then the provision in which the link to it is given applies to the extent that this link is not affected.

3 General requirements

3.1 Organization and performance of works on the construction of buildings and structures, arrangement of the construction site and workplaces must meet the requirements and.

3.2 The organization and performance of work at the construction site must be carried out in compliance with the legislation of the Russian Federation and the requirements,.

3.3 The work should be carried out in accordance with the project for the production of works (PPR), which, along with the general requirements, should provide for: the sequence of installation of structures; measures to ensure the required accuracy of the installation; spatial immutability of structures in the process of their pre-assembly and installation in the design position; stability of structures and parts of the building (structure) in the process of construction; the degree of enlargement of structures and safe working conditions. The combined installation of structures and equipment should be carried out according to the PPR, which contains the procedure for combining work, interconnected schemes of installation tiers and zones, schedules for lifting structures and equipment. If necessary, as part of the WEP, additional technical requirements should be developed aimed at improving the construction manufacturability of the structures being erected, which should be agreed upon in the prescribed manner with the organization - the project developer and included in the executive working drawings.

3.4 The construction site must be fenced in accordance with the requirements of GOST 23407 and marked with safety signs and inscriptions of the established form in accordance with the requirements of GOST R 12.4.026. The construction site, work sites, workplaces, driveways and approaches to them at night must be illuminated in accordance with the requirements of GOST 12.1.046.

3.5 Data on the production of construction and installation works should be entered daily in the logs of work on the installation of building structures (Appendix A), welding (Appendix B), anti-corrosion protection of welded joints (Appendix C), embedment of field joints and assemblies (Appendix D), performance assembly connections on bolts with controlled tension (Appendix E), a concrete work log (Appendix F), and also to fix their position on geodetic executive diagrams during the installation of structures. The quality of construction and installation works must be ensured by the current control of the technological processes of preparatory and main works, as well as during the acceptance of works. According to the results of the current control of technological processes, certificates of examination of hidden works are drawn up.

3.6 Structures, products and materials used in the construction of concrete, reinforced concrete, steel, wood and stone structures must meet the requirements of the relevant standards, codes of practice and working drawings.

3.7 Transportation and temporary storage of structures (products) in the installation area should be carried out in accordance with the requirements of state standards for these structures (products), and for non-standardized structures (products), the following requirements must be observed: structures should, as a rule, be in a position corresponding to the design (beams, trusses, slabs, wall panels, etc.), and if this condition cannot be met, in a position convenient for transportation and transfer to installation (columns, flights of stairs, etc.), provided that their strength is ensured; structures should be based on inventory linings and gaskets of rectangular section, located in the places indicated in the project; the thickness of the gaskets must be at least 30 mm and at least 20 mm higher than the height of the sling loops and other protruding parts of the structures; in case of multi-tiered loading and storage of the same type of structures, linings and gaskets should be located on the same vertical along the line of lifting devices (loops, holes) or in other places indicated in the working drawings; structures must be securely fastened to protect against overturning, longitudinal and transverse displacement, mutual impacts on each other or on the structure of vehicles; fastenings should ensure the possibility of unloading each element from vehicles without violating the stability of the rest; textured surfaces of load-bearing structures must be protected from damage and contamination; reinforcement outlets and protruding parts must be protected from damage; factory marking must be accessible for inspection; small parts for mounting connections should be attached to the shipping elements or sent simultaneously with the structures in a container equipped with tags indicating the brands of the parts and their number; these parts should be stored under a canopy; fasteners should be stored indoors, sorted by type and brand, bolts and nuts - by strength classes and diameters, and high-strength bolts, nuts and washers - and by lot.

3.8 Facade cladding and roofing structures with textured and other finishes, thin-walled galvanized elements of load-bearing structures, fasteners and parts of load-bearing and enclosing structures, shaped elements of facade and roofing, insulation and vapor barrier materials should be stored in an unheated warehouse with a hard floor covering. Storage of structures, cladding panels and parts in a warehouse is carried out in a packaged form on wooden beams up to 10 cm thick, with a step of 0.5 m. The warehouse must be closed, dry, with hard flooring. It is not allowed to store the structures, panels and parts specified in this paragraph in open areas and together with aggressive chemical products.

3.9 During storage, structures should be sorted by brands and stacked taking into account the sequence of installation.

3.11 To ensure the safety of wooden structures during transportation and storage, inventory devices (lodges, clamps, containers, soft slings) should be used with installation of soft gaskets and linings in places of support and contact of structures with metal parts. Structures should be stored under a canopy to protect them from exposure to solar radiation, alternating moistening and drying.

3.12 Prefabricated structures should be installed, as a rule, from vehicles or enlargement stands.

3.13 Before lifting each mounting element, it is necessary to check: compliance with its design mark; the condition of embedded products and installation marks, the absence of dirt, snow, ice, damage to the finish, priming and painting; availability of the necessary connecting parts and auxiliary materials at the workplace; correctness and reliability of fastening of load-handling devices. Each mounting element must be equipped in accordance with the PPR with scaffolding, ladders and railings.

3.14 Slinging of mounted elements should be carried out in the places indicated in the working drawings, and ensure their lifting and supply to the installation site in a position close to the design one. If it is necessary to change the places of slinging, they must be agreed with the organization - the developer of the working drawings. Lifting operations with thin-walled galvanized structures, facing panels and slabs should be carried out using textile tape slings, vacuum grippers or other devices that prevent damage to structures and panels. It is forbidden to sling structures in arbitrary places, as well as for the release of reinforcement. Slinging schemes for enlarged flat and spatial blocks must ensure their strength, stability and invariability of geometric dimensions and shapes when lifting.

3.15 Mounted elements should be lifted smoothly, without jerks, rocking and rotation, as a rule, using braces. When lifting vertically located structures, one guy is used, horizontal elements and blocks - at least two. The structures should be lifted in two stages: first, to a height of 20–30 cm, then, after checking the reliability of the slinging, further lifting should be carried out.

3.16 When installing mounting elements, the following must be ensured: stability and immutability of their position at all stages of installation; work safety; the accuracy of their position with the help of constant geodetic control; strength of mounting connections.

3.17 Structures should be installed in the design position according to the accepted guidelines (risks, pins, stops, edges, etc.). Structures with special embedded or other fixing devices should be installed on these devices.

3.18 Installed mounting elements must be securely fastened before bridging.

3.19 Until the end of the reconciliation and reliable (temporary or design) fixing of the installed element, it is not allowed to rest on it the overlying structures, if such support is not provided for by the PPR.

3.20 If there are no special requirements in the working drawings, the maximum deviations of the alignment of landmarks (edges or marks) during the installation of prefabricated elements, as well as deviations from the design position of structures completed by installation (erection) should not exceed the values ​​given in the relevant sections of this set of rules. Deviations for the installation of mounting elements, the position of which may change in the process of their permanent fixing and loading with subsequent structures, should be assigned in the PPR so that they do not exceed the limit values ​​after the completion of all installation work. In the absence of special instructions in the PPR, the deviation of the elements during installation should not exceed 0.4 of the maximum deviation for acceptance.

3.21 The use of installed structures for attaching cargo chain hoists, pull-off blocks and other lifting devices to them is allowed only in cases provided for by the PPR and agreed, if necessary, with the organization that completed the working drawings of the structures.

3.22 Installation of structures of buildings (structures) should, as a rule, begin with a spatially stable part: a tie cell, stiffening cores, etc. Installation of structures of buildings and structures of great length or height should be carried out in spatially stable sections (spans, tiers, floors , temperature blocks, etc.).

3.23 Production quality control of construction and installation works should be carried out in accordance with SP 48.13330. During the acceptance control, the following documentation must be submitted: as-built drawings with the introduced (if any) deviations allowed by the manufacturer of the structures, as well as the installation organization, agreed with the design organizations - developers of the drawings, and documents on their approval; factory technical passports for steel, reinforced concrete and wooden structures; documents (certificates, passports) certifying the quality of materials used in the construction and installation works; certificates of examination of hidden works; acts of intermediate acceptance of critical structures; Executive geodetic schemes of the position of structures; work logs; documents on quality control of welded joints; acts of testing structures (if tests are provided for by additional rules of this set of rules or working drawings); other documents specified in additional rules or working drawings.

3.24 It is allowed in projects, with appropriate justification, to assign requirements for the accuracy of parameters, volumes and methods of control that differ from those provided for by these rules. In this case, the accuracy of the geometric parameters of structures should be assigned on the basis of the accuracy calculation in accordance with GOST 21780.

Approved
Order of the Federal
construction agencies
and housing and communal
household (Gosstroy)
dated December 25, 2012 N 109/GS

SET OF RULES

UPDATED VERSION OF SNiP 3.03.01-87

LOAD-BEARING AND ENVELOPED STRUCTURES

Load-bearing and separating constructions

SP 70.13330.2012

OKS 91.080.10
91.080.20
91.080.30
91.080.40

Foreword

The goals and principles of standardization in the Russian Federation are established by the Federal Law of December 27, 2002 N 184-FZ "On technical regulation", and the development rules - by the Decree of the Government of the Russian Federation of November 19, 2008 N 858 "On the procedure for developing and approving sets of rules ".

About the set of rules

1. Performers - CJSC "TsNIIPSK named after Melnikov"; Institutes of JSC "National Research Center "Construction": NIIZHB named after A.A. Gvozdev and TsNIISK named after V.A. Kucherenko; Association of Manufacturers of Ceramic Wall Materials; Association of Manufacturers of Silicate Products, Siberian Federal University.
2. Introduced by the Technical Committee for Standardization TC 465 "Construction".
3. Prepared for approval by the Department of Urban Planning Policy.
4. Approved by the Order of the Federal Agency for Construction, Housing and Communal Services (Gosstroy) dated December 25, 2012 N 109 / GS and entered into force on July 1, 2013.
5. Registered by the Federal Agency for Technical Regulation and Metrology (Rosstandart). Revision of SP 70.13330.2011 "SNiP 3.03.01-87 Bearing and enclosing structures".

Information about changes to this updated set of rules is published in the annually published information index "National Standards", and the text of changes and amendments - in the monthly published information indexes "National Standards". In case of revision (replacement) or cancellation of this set of rules, a corresponding notice will be published in the monthly published information index "National Standards". Relevant information, notification and texts are also posted in the public information system - on the official website of the developer (Gosstroy) on the Internet.

Introduction

This set of rules was developed in order to improve the quality of construction and installation works, the durability and reliability of buildings and structures, as well as the level of safety of people at the construction site, the safety of material assets in accordance with the Federal Law of December 30, 2009 N 384-FZ "Technical regulation on the safety of buildings and structures", increasing the level of harmonization of regulatory requirements with European and international regulatory documents; application of uniform methods for determining operational characteristics and evaluation methods.
The updating of SNiP 3.03.01-87 was carried out by the following team of authors: CJSC "TsNIIPSK named after Melnikov" consisting of specialists: candidates of techn. Sciences N.I. Presnyakov, V.V. Evdokimov, V.F. Belyaev; Dr. tech. Sciences B.V. Ostroumov, V.K. Vostrov; engineers S.I. Bochkova, V.M. Babushkin, G.V. Kalashnikov; Siberian Federal University - Associate Professor, Ph.D. tech. Sciences V.L. Igoshin; Institutes of OAO "National Research Center "Construction": NIIZhB named after A.A. Gvozdev - Doctor of Technical Sciences B.A. Krylov, V.F. Stepanova, N.K. Rozental; Candidates of Technical Sciences V.R. Falikman , M. I. Brusser, A. N. Bolgov, V. I. Savin, T. A. Kuzmich, M. G. Korevitskaya, L. A. Titova, I. I. Karpukhin, G. V. Lyubarskaya, D V. Kuzevanov, N. K. Vernigora and TsNIISK named after V. A. Kucherenko - Doctors of Engineering Sciences I. I. Vedyakov, S. A. Madatyan, Candidates of Engineering Sciences O. I. Ponomarev, S. B. Turkovsky, A. A. Pogoreltsev, I. P. Preobrazhenskaya, A. V. Prostyakov, G. G. Gurova, M. I. Gukova, A. V. Potapov, A. M. Gorbunov, E. G. Fokin, Association of Manufacturers of Ceramic Wall Materials - VN Gerashchenko, Association of Manufacturers of Silicate Products - NV Somov.

1 area of ​​use

1.1. This set of rules applies to the production and acceptance of work performed during the construction and reconstruction of enterprises, buildings and structures in all sectors of the national economy:
in the construction of monolithic concrete and reinforced concrete structures from heavy, extra heavy, on porous aggregates, heat-resistant and alkali-resistant concrete, in the performance of shotcrete and underwater concreting;
in the manufacture of prefabricated concrete and reinforced concrete structures in the conditions of a construction site;
during the installation of prefabricated reinforced concrete, steel, wooden structures and structures made of light efficient materials;
when welding assembly joints of building steel and reinforced concrete structures, reinforcement joints and embedded products of monolithic reinforced concrete structures;
in the production of works on the construction of stone and reinforced masonry structures from ceramic and silicate bricks, ceramic, silicate, natural and concrete stones, brick and ceramic panels and blocks, concrete blocks.
The requirements of this set of rules should be taken into account when designing the structures of buildings and structures.
1.2. When erecting special structures - roads, bridges, pipes, steel tanks and gas tanks, tunnels, subways, airfields, hydraulic engineering reclamation and other structures, as well as when erecting buildings and structures on permafrost and subsidence soils, undermined territories and in seismic areas, additional be guided by the requirements of the relevant regulatory documents.

2.1. This set of rules uses references to the following regulatory documents:
GOST 379-95 Brick and silicate stones. Specifications
GOST 450-77 Technical calcium chloride. Specifications
GOST 530-07 Ceramic brick and stone. General specifications
GOST 828-77 Technical sodium nitrate. Specifications
GOST 965-89 White Portland cements. Specifications
GOST 969-91 Aluminous and high aluminous cements. Specifications
GOST 1581-96 Oil-well portland cements. Specifications
GOST 2081-2010 Carbamide. Specifications
GOST 2246-70 Steel welding wire. Specifications
GOST 3242-79 Welded joints. Quality control methods
GOST 5264-80 Manual arc welding. Connections are welded. Main types, structural elements and dimensions
GOST 5578-94 Crushed stone and sand from slags of ferrous and non-ferrous metallurgy for concrete. Specifications
GOST 5686-94 Soils. Piling Field Test Methods
GOST 5802-86 Building mortars. Test Methods
GOST 6402-70 Spring washers. Specifications
GOST 6996-66 Welded joints. Methods for determining mechanical properties
GOST 7076-99 Construction materials and products. Method for determining thermal conductivity and thermal resistance in a stationary thermal regime
GOST 7473-2010 Concrete mixes. Specifications
GOST 7512-82 Non-destructive testing. Connections are welded. radiographic method
GOST 7566-94 Steel products. Acceptance, marking, packaging, transportation and storage
GOST 8267-93 Crushed stone and gravel from dense rocks for construction work. Specifications
GOST 8269.0-97 Crushed stone and gravel from dense rocks and industrial waste for construction work. Methods of physical and mechanical tests
GOST 8713-79 Submerged arc welding. Connections are welded. Main types, structural elements and dimensions
GOST 8735-88 Sand for construction work. Test Methods
GOST 8736-93 Sand for construction work. Specifications
GOST 9087-81 Fused welding fluxes. Specifications
GOST 9206-80 Diamond powders. Specifications
GOST 9467-75 Coated metal electrodes for manual arc welding of structural and heat-resistant steels. Types
GOST 9757-90 Artificial porous gravel, crushed stone and sand. Specifications
GOST 9758-2012 Porous inorganic aggregates for construction work. Test Methods
GOST 10060-2012 Concrete. Methods for determining frost resistance
GOST 10178-85 Portland cement and Portland slag cement. Specifications
GOST 10180-90 Concrete. Methods for determining the strength of control samples
GOST 10181-2000 Concrete mixtures. Test Methods
GOST 10243-75 Steel. Test methods and evaluation of macrostructure
GOST 10541-78 Universal motor oils and for automotive carburetor engines. Specifications
GOST 10690-73 Technical potassium carbonate (potash). Specifications
GOST 10832-2009 Expanded perlite sand and crushed stone. Specifications
GOST 10906-78 Oblique washers. Specifications
GOST 10922-90 Reinforcing and embedded products, their welded, knitted and mechanical connections for reinforced concrete structures. General specifications
GOST 11052-74 Expanding gypsum alumina cement
GOST 11371-78 Washers. Specifications
GOST 11533-75 Automatic and semi-automatic submerged arc welding. Connections are welded at acute and obtuse angles. Main types, structural elements and dimensions
GOST 11534-75 Manual arc welding. Connections are welded at acute and obtuse angles. Main types, structural elements and dimensions
GOST 12730.5-84 Concrete. Methods for determining water resistance
GOST 12865-67 Expanded vermiculite
GOST 13015-2003 Concrete and reinforced concrete products for construction. General technical requirements. Rules for acceptance, labeling, transportation and storage
GOST 13087-81 Concrete. Methods for determining abrasion
GOST 14098-91 Welded fittings and embedded products of reinforced concrete structures. Types, designs and sizes
GOST 14771-76 Shielded arc welding. Connections are welded. Main types, structural elements and dimensions
GOST 14782-86 Non-destructive testing. Connections are welded. Ultrasonic methods
GOST 15150-69 Machinery, instruments and other technical products. Versions for different climatic regions. Categories, conditions of operation, storage and transportation in terms of the impact of environmental climatic factors
GOST 15164-78 Electroslag welding. Connections are welded. Main types, structural elements and dimensions
GOST 15825-80 Colored Portland cement. Specifications
GOST 16037-80 Welded steel pipeline joints. Main types, structural elements and dimensions
GOST ISO/IEC 17025-2009 General requirements for the competence of testing and calibration laboratories
GOST 17624-87 Concrete. Ultrasonic strength determination method
GOST 18105-2010 Concrete. Strength control and assessment rules
GOST 18442-80 Non-destructive testing. capillary methods. General requirements
GOST 19906-74 Technical sodium nitrite. Specifications
GOST 20276-99 Soils. Methods for field determination of strength and deformability characteristics
GOST 20799-88 Industrial oils. Specifications
GOST 20850-84 Glued wooden structures. General specifications
GOST 20910-90 Heat-resistant concrete. Specifications
GOST 21104-75 Non-destructive testing. Ferroprobe method
GOST 21105-87 Non-destructive testing. Magnetic particle method
GOST 21779-82 System for ensuring the accuracy of geometric parameters in construction. Technological approvals
GOST 21780-2006 System for ensuring the accuracy of geometric parameters in construction. Accuracy calculation
GOST 22263-76 Crushed stone and sand from porous rocks. Specifications
GOST 22266-94 Sulphate-resistant cements. Specifications
GOST 22690-88 Concrete. Determination of strength by mechanical methods of non-destructive testing
GOST 22845-85 Electric passenger and freight elevators. Rules for the organization, production and acceptance of installation work
GOST 23118-99 Steel building structures. General specifications
GOST 23407-78 Inventory fences for construction sites and sites for construction and installation works. Specifications
GOST 23518-79 Shielded arc welding. Connections are welded at acute and obtuse angles. Main types, structural elements and dimensions
GOST 23683-89 Petroleum solid paraffins. Specifications
GOST 23732-2011 Water for concrete and mortar. Specifications
GOST 23858-79 Welded butt and tee fittings for reinforced concrete structures. Ultrasonic quality control methods. Acceptance rules
GOST 24045-2010 Bent steel sheet profiles with trapezoidal corrugations for construction. Specifications
GOST 24211-2008 Additives for concrete and mortars. General specifications
GOST 24379.0-80 Foundation bolts. General specifications
GOST 24846-81 Soils. Methods for measuring deformations of the foundations of buildings and structures
GOST 25192-82 Concrete. Classification and general technical requirements
GOST 25225-82 Non-destructive testing. Seams of welded joints of pipelines. Magnetographic method
GOST 25246-82 Chemically resistant concretes. Specifications
GOST 25328-82 Cement for mortars. Specifications
GOST 25485-89 Cellular concrete. Specifications
GOST 25592-91 Ash and slag mixtures for thermal power plants for concrete. Specifications
GOST 25818-91 Fly ash from thermal power plants for concrete. Specifications
GOST 25820-2000 Lightweight concrete. Specifications
GOST 26271-84 Flux-cored wire for arc welding of carbon and low-alloy steels. General specifications
GOST 26633-91 Heavy and fine-grained concrete. Specifications
GOST 26644-85 Crushed stone and sand from slags of thermal power plants for concrete. Specifications
GOST 26887-86 Platforms and ladders for construction and installation works. General specifications
GOST 27005-86 Light and cellular concretes. Medium Density Control Rules
GOST 27006-86 Concrete. Squad selection rules
GOST 28013-98 Building mortars. General specifications
GOST 28570-90 Concrete. Methods for determining strength from samples taken from structures
GOST 30515-97 Cements. General specifications
GOST 30971-2002 Mounting seams for adjoining window blocks to wall openings. General specifications
GOST 31108-2003 General construction cements. Specifications
GOST 31384-2008 Protection of concrete and reinforced concrete structures against corrosion. General technical requirements
GOST 12.1.046-85 SSBT. Construction. Building site lighting standards
GOST R 12.4.026-2001 SSBT. Signal colors, safety signs and signal markings. Purpose and rules of application. General technical requirements and characteristics. Test Methods
GOST R 51254-99 Mounting tool for normalized tightening of threaded connections. Keys are momentary. General specifications
GOST R 51263-99 Polystyrene concrete. Specifications
GOST R 51634-2000 Motor and tractor oils. General technical requirements
GOST R 52085-2003 Formwork. General specifications
GOST R 52752-2007 Formwork. Test Methods
SP 15.13330.2012 "SNiP II-22-81* Stone and reinforced masonry structures"
SP 16.13330.2011 "SNiP II-23-81* Steel structures"
SP 20.13330.2011 "SNiP 2.01.07-85* Loads and impacts"
SP 25.13330.2012 "SNiP 2.02.04-88 Bases and foundations on permafrost soils"
SP 28.13330.2012 "SNiP 2.03.11-85 Protection of building structures against corrosion"
SP 45.13330.2012 "SNiP 3.02.01-87 Earthworks, foundations and foundations"
SP 46.13330.2012 "SNiP 3.06.04-91 Bridges and pipes"
SP 48.13330.2011 "SNiP 12-01-2004 Organization of construction"
SP 50.13330.2012 "SNiP 23-02-2003 Thermal protection of buildings"
SP 130.13330.2011 "SNiP 3.09.01-85 Production of prefabricated reinforced concrete structures and products".
Note. When using this set of rules, it is advisable to check the effect of reference standards in the public information system - on the official website of the national bodies of the Russian Federation for standardization on the Internet or according to the annually published information index "National Standards", which was published as of January 1 of the current year, and according to the corresponding monthly published information indexes published in the current year. If the referenced document is replaced (modified), then when using this set of rules, one should be guided by the replaced (modified) document. If the referenced document is canceled without replacement, then the provision in which the link to it is given applies to the extent that this link is not affected.

3. General requirements

3.1. The organization and performance of work on the construction of buildings and structures, the arrangement of the construction site and workplaces must meet the requirements and.
3.2. The organization and production of work at the construction site must be carried out in compliance with the legislation of the Russian Federation and the requirements,.
3.3. The work should be carried out in accordance with the project for the production of works (PPR), which, along with the general requirements, should provide for: the sequence of installation of structures; measures to ensure the required accuracy of the installation; spatial immutability of structures in the process of their pre-assembly and installation in the design position; stability of structures and parts of the building (structure) in the process of construction; the degree of enlargement of structures and safe working conditions.
The combined installation of structures and equipment should be carried out according to the PPR, which contains the procedure for combining work, interconnected schemes of installation tiers and zones, schedules for lifting structures and equipment.
If necessary, as part of the WEP, additional technical requirements should be developed aimed at improving the construction manufacturability of the structures being erected, which should be agreed upon in the prescribed manner with the organization - the project developer and included in the executive working drawings.
3.4. The construction site must be fenced in accordance with the requirements of GOST 23407 and marked with safety signs and inscriptions of the established form in accordance with the requirements of GOST R 12.4.026. The construction site, work sites, workplaces, driveways and approaches to them at night must be illuminated in accordance with the requirements of GOST 12.1.046.
3.5. Data on the production of construction and installation works should be entered daily in the work logs for the installation of building structures (Appendix A), welding works (Appendix B), anti-corrosion protection of welded joints (Appendix C), embedment of assembly joints and assemblies (Appendix D), assembly joints on bolts with controlled tension (Appendix D), a log of concrete work (Appendix F), as well as to fix their position in the course of installation of structures on geodetic executive diagrams. The quality of construction and installation works must be ensured by the current control of the technological processes of preparatory and main works, as well as during the acceptance of works. According to the results of the current control of technological processes, certificates of examination of hidden works are drawn up.
3.6. Structures, products and materials used in the construction of concrete, reinforced concrete, steel, wood and stone structures must meet the requirements of the relevant standards, codes of practice and working drawings.
3.7. Transportation and temporary storage of structures (products) in the installation area should be carried out in accordance with the requirements of state standards for these structures (products), and for non-standardized structures (products), the following requirements must be observed:
structures should, as a rule, be in a position corresponding to the design one (beams, trusses, slabs, wall panels, etc.), and if this condition cannot be met, in a position convenient for transportation and transfer to installation (columns, flights of stairs etc.), provided that their strength is ensured;
structures should be based on inventory linings and gaskets of rectangular section, located in the places indicated in the project; the thickness of the gaskets must be at least 30 mm and at least 20 mm higher than the height of the sling loops and other protruding parts of the structures; in case of multi-tiered loading and storage of the same type of structures, linings and gaskets should be located on the same vertical along the line of lifting devices (loops, holes) or in other places indicated in the working drawings;
structures must be securely fastened to protect against overturning, longitudinal and transverse displacement, mutual impacts on each other or on the structure of vehicles; fastenings should ensure the possibility of unloading each element from vehicles without violating the stability of the rest;
textured surfaces of load-bearing structures must be protected from damage and contamination;
reinforcement outlets and protruding parts must be protected from damage; factory marking must be accessible for inspection;
small parts for mounting connections should be attached to the shipping elements or sent simultaneously with the structures in a container equipped with tags indicating the brands of the parts and their number; these parts should be stored under a canopy;
fasteners should be stored indoors, sorted by type and brand, bolts and nuts - by strength classes and diameters, and high-strength bolts, nuts and washers - and by lot.
3.8. Facade cladding and roofing structures with textured and other finishes, thin-walled galvanized elements of load-bearing structures, fasteners and parts of load-bearing and enclosing structures, façade and roofing fittings, insulation and vapor barrier materials should be stored in an unheated warehouse with a hard floor covering.
Storage of structures, cladding panels and parts in a warehouse is carried out in a packaged form on wooden beams up to 10 cm thick, with a step of 0.5 m. The warehouse must be closed, dry, with hard flooring.
It is not allowed to store the structures, panels and parts specified in this paragraph in open areas and together with aggressive chemical products.
3.9. Structures during storage should be sorted by brands and stacked taking into account the sequence of installation.
3.10. It is forbidden to move any structures by dragging.
3.11. To ensure the safety of wooden structures during transportation and storage, inventory devices (lodgements, clamps, containers, soft slings) should be used with installation of soft pads and linings in places of support and contact of structures with metal parts. Structures should be stored under a canopy to protect them from exposure to solar radiation, alternating moistening and drying.
3.12. Prefabricated structures should be installed, as a rule, from vehicles or enlargement stands.
3.13. Before lifting each mounting element, check:
compliance with its design brand;
the condition of embedded products and installation marks, the absence of dirt, snow, ice, damage to the finish, priming and painting;
availability of the necessary connecting parts and auxiliary materials at the workplace;
correctness and reliability of fastening of load-handling devices.
Each mounting element must be equipped in accordance with the PPR with scaffolding, ladders and railings.
3.14. Slinging of the mounted elements should be carried out in the places indicated in the working drawings, and ensure their lifting and supply to the installation site in a position close to the design one. If it is necessary to change the places of slinging, they must be agreed with the organization - the developer of the working drawings.
Lifting operations with thin-walled galvanized structures, facing panels and slabs should be carried out using textile tape slings, vacuum grippers or other devices that prevent damage to structures and panels.
It is forbidden to sling structures in arbitrary places, as well as for the release of reinforcement.
Slinging schemes for enlarged flat and spatial blocks must ensure their strength, stability and invariability of geometric dimensions and shapes when lifting.
3.15. Mounted elements should be lifted smoothly, without jerks, swinging and rotation, as a rule, using braces. When lifting vertically located structures, one guy is used, horizontal elements and blocks - at least two.
The structures should be lifted in two stages: first, to a height of 20 - 30 cm, then, after checking the reliability of the slinging, further lifting should be carried out.
3.16. When installing mounting elements, the following must be ensured:
stability and immutability of their position at all stages of installation;
work safety;
the accuracy of their position with the help of constant geodetic control;
strength of mounting connections.
3.17. Structures should be installed in the design position according to the accepted guidelines (risks, pins, stops, edges, etc.).
Structures with special embedded or other fixing devices should be installed on these devices.
3.18. Mounting elements to be installed must be securely fastened before bridging.
3.19. Until the end of the reconciliation and reliable (temporary or design) fixing of the installed element, it is not allowed to rest on it the overlying structures, if such support is not provided for by the PPR.
3.20. If there are no special requirements in the working drawings, the maximum deviations of the alignment of landmarks (edges or scratches) during the installation of prefabricated elements, as well as deviations from the design position of structures completed by installation (erection) should not exceed the values ​​\u200b\u200bgiven in the relevant sections of this set of rules.
Deviations for the installation of mounting elements, the position of which may change in the process of their permanent fixing and loading with subsequent structures, should be assigned in the PPR so that they do not exceed the limit values ​​after the completion of all installation work. In the absence of special instructions in the PPR, the deviation of the elements during installation should not exceed 0.4 of the maximum deviation for acceptance.
3.21. The use of installed structures for attaching cargo pulley blocks, diverting blocks and other lifting devices to them is allowed only in cases provided for by the PPR and agreed, if necessary, with the organization that completed the working drawings of the structures.
3.22. Installation of building structures (structures) should be started, as a rule, from a spatially stable part: a bond cell, a stiffening core, etc.
Installation of structures of buildings and structures of great length or height should be carried out in spatially stable sections (spans, tiers, floors, temperature blocks, etc.).
3.23. Production quality control of construction and installation works should be carried out in accordance with SP 48.13330.
The following documentation must be submitted during acceptance control:
executive drawings with introduced (if any) deviations, approved by the manufacturer of structures, as well as by the installation organization, agreed with design organizations - developers of drawings, and documents on their approval;
factory technical passports for steel, reinforced concrete and wooden structures;
documents (certificates, passports) certifying the quality of materials used in the construction and installation works;
certificates of examination of hidden works;
acts of intermediate acceptance of critical structures;
Executive geodetic schemes of the position of structures;
work logs;
documents on quality control of welded joints;
acts of testing structures (if tests are provided for by additional rules of this set of rules or working drawings);
other documents specified in additional rules or working drawings.
3.24. It is allowed in projects, with appropriate justification, to assign requirements for the accuracy of parameters, volumes and methods of control that differ from those provided for by these rules. In this case, the accuracy of the geometric parameters of structures should be assigned on the basis of the accuracy calculation in accordance with GOST 21780.

1 area of ​​use
2 Normative references
3 General requirements
4 Installation of steel structures
4.1 General
4.2 Preparing structures for installation
4.3 Pre-assembly
4.4 Installation, alignment and fastening
4.5 Bolted field connections without tension control
4.6 Mounting connections on bolts, including high-strength, with controlled tension
4.7 Special field connections
4.8 Field welds
4.9 Prestressing of structures
4.10 Testing of structures and structures
4.11 Additional rules for the installation of structures of one-story buildings
4.12 Requirements for acceptance inspection
4.13 Additional rules for the installation of structures of multi-storey buildings
4.14 Ensuring the stability of the main structural elements during installation
4.15 Installation of built-in structures
4.16 Installation of structural coating structures
4.17 Installation of cable-stayed structures
4.18 Installation of membrane coating structures
4.19 Additional rules for the installation of structures of conveyor galleries
4.20 Additional rules for the installation of structures of antenna communication structures and chimney towers
4.21 Dismantling and installation of facility structures during the reconstruction of existing production facilities
4.22 Erection and dismantling of structures using helicopters
5 Concrete work
5.1 Materials for heavy and fine-grained concrete
5.2 Concrete mixtures
5.3 Substrate preparation and concrete placement
5.4 Curing and care of concrete
5.5 Concrete testing at structural acceptance
5.6 Concrete on porous aggregates
5.7 Acid and alkali resistant concretes
5.8 Prestressing concrete
5.9 Refractory concretes
5.10 Concrete especially heavy and for radiation protection
5.11 Production of concrete work at negative temperatures
5.12 Concrete work at an air temperature above 25 degrees Celsius
5.13 Special concreting methods
5.14 Cutting expansion joints, technological grooves, openings, holes and surface treatment of monolithic structures
5.15 Cementation of joints. Shotcrete and sprayed concrete works
5.16 Rebar work
5.17 Formwork
5.18 Acceptance of concrete and reinforced concrete structures or parts of structures
6 Installation of precast concrete and concrete structures
6.1 General information
6.2 Construction of bases and foundations
6.3 Installation of columns and frames
6.4 Installation of crossbars, beams, trusses, floor slabs and coverings
6.5 Installing wall panels
6.6 Installation of ventilation units, volumetric units of elevator shafts and sanitary cabins
6.7 Construction of buildings by lifting floors
6.8 Welding and anti-corrosion coating of embedded and connecting products
6.9 Casting joints and seams
6.10 Water, air and vapor permeability, heat and sound insulation of joints of external walls and mounting units adjoining window and door blocks to wall openings
7 Installation of light enclosing structures
7.1 General requirements for the installation of lightweight building envelopes
7.2 Enclosing structures made of chrysotile cement sheets, extrusion panels and slabs
7.3 Installation of metal enclosing roof structures of sheet assembly and sandwich panels
7.4 Suspended ventilated facades
7.5 Frame-sheathed partitions
7.6 Walls made of sandwich panels and sheet assembly
8 Installation of wooden structures
8.1 General provisions for the acceptance and installation of wooden structures
8.2 Installation of wooden columns and posts
8.3 Installation of glued timber beams
8.4 Installation of wooden prefabricated trusses
8.5 Installation of glued wooden arches and frames
8.6 Installation of laminated timber ribbed domes
8.7 Installation of wall panels and floor slabs
9 Stone structures
9.1 General provisions for the construction of masonry structures
9.2 Masonry of ceramic and silicate bricks, of ceramic, concrete, silicate and natural stones of regular shape
9.3 Laying multilayer lightweight exterior walls. Load-bearing exterior walls
9.4 Non-bearing (curtain) multilayer walls
9.5 Requirements for structures and materials of the front layer of multilayer walls
9.6 Masonry of large-format ceramic hollow stones
9.7 Masonry walls of large silicate blocks
9.8 Wall cladding during masonry
9.9 Features of masonry arches and vaults
9.10 Masonry of rubble stone and rubble concrete
9.11 Additional requirements for the performance of work in seismic regions
9.12 Construction of stone structures in winter conditions
9.13 Masonry with antifreeze additives
9.14 Laying on mortars without antifreeze additives with subsequent strengthening of structures by heating
9.15 Freeze masonry
9.16 Quality control of works
9.17 Strengthening of stone structures of reconstructed and damaged buildings
9.18 Acceptance of stone structures
10 Welding field joints of building structures
10.1 General
10.2 Assembly and welding of field joints of steel structures
10.3 Assembly and welding of field joints of reinforced concrete structures
10.4 Quality control of welded joints in steel structures
10.5 Quality control of welded joints during the installation of reinforced concrete structures
Annex A (mandatory). List of regulatory documents
Annex B (mandatory). Design of covers and pages of the journal of works on the installation of building structures
Annex B (mandatory). Design of covers and pages of the magazine of welding works
Annex D (mandatory). Design of covers and pages of the journal of anti-corrosion protection of welded joints
Annex D (mandatory). Design of covers and pages of the magazine for embedding mounting joints and assemblies
Annex E (mandatory). Design of covers and pages of the magazine for performing field connections on bolts with controlled tension
Annex G (mandatory). Torque Wrench Calibration Log
Appendix I (informative). Recommendations for choosing the length of blind rivets depending on the thickness of the package to be joined
Annex K (mandatory). The act of testing the structures of the building and structure (form)
Annex L (mandatory). Calculation of the stability of structural elements
Annex M (recommended). Scope of cements in construction
Annex H (mandatory). Materials for concrete and solutions
Annex P (recommended). Scope of additives in concrete
Appendix P (recommended). Selection of the most economical method of curing concrete during winter concreting of monolithic structures
Annex C (recommended). Recommended grades of powder and bond of diamond tools for processing concrete and reinforced concrete
Annex T (mandatory). Loads and data for the calculation of formwork for monolithic concrete and reinforced concrete structures
Appendix Y (reference). Binders for masonry mortars and their compositions
Appendix F (informative). Antifreeze and plasticizing additives in solutions, conditions for their use and expected strength of the solution
Annex X (mandatory). Journal of Concrete Works
Bibliography