"Guidelines for labor rationing for maintenance and repair of electrical networks, electrical power devices and equipment" (approved by Rosstroy). Methodological recommendations methodological recommendations for the rationing of electricity consumption

CENTER OF MUNICIPAL ECONOMY AND LAW

ON RATE OF LABOR FOR WORKS ON MAINTENANCE AND REPAIR OF ELECTRIC NETWORKS, ELECTRIC POWER DEVICES AND EQUIPMENT

Moscow, 2005

1. GENERAL

2. ORGANIZATION OF WORK

3. REGULATORY PART

3.1. Overhaul

3.1.1. Electrical equipment of substations

3.1.2. Relay protection and automation

3.1.3. Overhead power lines

3.1.4. Mast transformer substations

3.1.5. Outdoor lighting networks

3.1.6. electrical equipment diesel power plants

3.2. Maintenance

3.2.1. Electrical equipment of substations

3.2.2. Overhead power lines 0.4 - 10 kV

3.2.3. Cable power lines 0.4 - 10 kV

3.2.4. Relay protection and automation

3.2.5. Electrical equipment of diesel power plants

3.3. Repair and maintenance service

3.3.1. Counters electrical energy

3.3.2. Power transformers

3.3.3. Internal and outdoor installation

3.3.4. Measuring voltage transformers

3.3.5. Oil circuit breakers

3.3.6. Switchgear drives

3.3.7. Battery installations

3.3.8. Circuit breakers

3.3.9. Control stations

3.3.10. Relay protection and automation

3.3.11. Panel devices

3.3.12. Recording instruments

3.3.13. Complex appliances

3.3.14. cable lines

3.3.15. Distribution devices

3.3.16. Lightning protection devices

3.3.17. Overhead power lines

3.3.18. protective equipment

3.3.19. Diesel generators

Annex 1 Average coefficients to the norms of time and prices for construction, installation and repair and construction work performed in winter conditions

These guidelines are intended to determine the cost of repair and maintenance of electric power devices, equipment and installations electrical networks, outdoor lighting and electrical part of power plants.

The Methodological Recommendations are based on the Standard Standards for Overhaul, Current Repair and Maintenance of Electric Networks, Electric Power Devices and Equipment, developed by the Central Regulatory Research Station (CNIS) (approved by order of the Ministry of Housing and Communal Services of the RSFSR of September 21, 1990 No. 11) .

1. GENERAL

1.1. Methodological recommendations include time standards for overhaul, current repairs and operational maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants.

1.2. The guidelines are intended to determine the cost of repair and maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants. Methodological recommendations make it possible to calculate the labor intensity of repair work, the standard number of workers, labor costs in the cost price, and, consequently, in the tariff for electric energy, to bill workers, and to carry out a rational placement of personnel.

1.3. The norms of time are advisory in nature and are the basis for the development and approval by the executive authorities of the subjects Russian Federation and local government regional regulatory and methodological materials.

1.4. The basis for the development of time standards is based on the current legal documents:

Standard norms of time for overhaul, current repairs and maintenance of electrical networks, electrical power devices and equipment, approved by order of the Ministry of Housing and Communal Services of the RSFSR dated September 21, 1990 No. 11;

Intersectoral rules for labor protection (safety rules) for the operation of electrical installations, approved by the Decree of the Ministry of Labor and Social Development of the Russian Federation dated 05.01.01 No. 3;

Photochronometric observations, technical calculations and photographs of working time;

Materials for the study of organizational and technical conditions for the performance of work and organization of labor.

1.5. The concept of "norm of time" means the amount of time spent working, established for the performance of a unit of work by an employee or a group of employees of appropriate qualifications in certain organizational and technical conditions.

1.6. The time standards are given in man-hours per unit of work for performers, the number and qualifications of which are given in each paragraph of the normative part, provided the necessary materials, tools and fixtures are provided.

1.7. The Methodological Recommendations include time standards for the most common conditions for performing work in accordance with the current safety and technical operation rules, taking into account the provision of workplaces with the necessary machinery, inventory and equipment in relation to the nature of the work performed.

1.8. Time taken into account:

For carrying out shutdowns during work performed with complete removal of voltage;

For preparatory and final work and maintenance of the workplace;

For rest and personal needs;

For moving and carrying units, assemblies and materials within the work area at a distance of up to 50 meters.

Movements of aggregates, assemblies and materials at distances in excess of those taken into account should be normalized according to the collection E1 "Internal transport work" common norms and prices for construction, installation and repair and construction work.

1.9. The rules do not take into account the time spent on:

Implementation of measures to ensure the safety of work during partial stress relief;

Transitions (transfers) of workers to the facility and from the facility. Installed on the ground, taking into account rational route schemes that ensure minimal time spent on the movement of workers;

Development of soil and painting of structures. These works should be standardized according to the collections E2 "Earthworks" Issue 1 "Mechanized and manual excavation" and E8 "Finishing coatings of building structures" Issue 1 "Finishing work" of the Uniform norms and prices for building installation and repair and construction work.

1.10. When performing work in winter conditions in the open air; in hard-to-reach places; Correction factors are applied near operating power lines, critical communication lines, as well as near equipment under high voltage, associated with the implementation of additional safety measures.

1.11. In the case of application of organizational and technical conditions other than those provided for in the Methodological Recommendations (organization of labor, machines and mechanisms), as well as when performing work not provided for by the Methodological Recommendations, it is recommended to develop local technically justified time standards or apply other regulatory and methodological documents.

When introducing at an enterprise more advanced than provided for in the recommendations, the organization of production and labor, the technology for performing work, equipment, equipment of machines, systems, mechanisms, etc., which increase the productivity of workers, should be developed by the method of technical regulation and introduced in the established reasonable local time standards.

1.13. The names of workers' professions are indicated in accordance with the All-Russian classifier of workers' professions, positions of employees and wage categories OK 016-94 (OKPDTF). The content of the work performed is given in accordance with issues 1, 2, 3, 9 of the Unified Tariff and Qualification Reference Book of Works and Professions of Workers.

The performance of work by workers whose qualifications do not correspond to the tariff category specified in the Methodological Recommendations cannot serve as a basis for any changes in the norms.

In these Guidelines, if all work on the repair of any equipment is performed by a worker of the same category, then the worker's profession, indicating the category of work, is placed in front of the table with the names of the operations and the time standards for these operations, otherwise, the worker's profession, indicating the category of work located directly in the table.

1.14. The administration of the enterprise distributes workers among departments and sections, based on production needs, ensuring their rational loading. At the same time, in each individual case, the issue of fulfillment by employees additional features taking into account economic feasibility and ensuring the quality of work.

2. ORGANIZATION OF WORK

2.1. Overhaul of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants includes work related to their complete revision (regardless of technical condition); repair or replacement of worn-out elements of assemblies and parts; testing and adjustment of devices, equipment and installations in general.

2.2. The current repair of devices, equipment and installations includes all work in the period between major repairs, aimed at ensuring the normal operation of devices, equipment and installations.

2.3. Operational maintenance includes monitoring the condition of devices, equipment, installations, and eliminating minor malfunctions.

2.4. The sequence of current and major repairs is established in accordance with the schedules of the system of preventive maintenance.

2.5. Works on capital, current repairs, maintenance of equipment and installations are carried out at their location, as well as in laboratories, workshops and repair shops of electric power enterprises.

2.6. The work must be carried out by workers of appropriate qualifications, familiar with the rules for the production of work and safety precautions.

2.7. Before starting work, workers are given an order or a standardized work assignment, in accordance with which they prepare their workplace: they deliver the necessary tools, parts, assemblies, receive drawings and instructions from the foreman or foreman.

2.8. Capital, current repairs and maintenance of equipment, installations and networks, depending on the nature of the work, are carried out by one performer or a link of performers. If the work is performed by a link of 2 performers, then one of the workers is the direct executor of the corresponding operation, and the second one conducts supervision, which ensures normal conditions for the performance of work, due to safety regulations, and also performs auxiliary work (supply of materials, tools, preparation of bindings, installation of fences, etc.).

2.9. The organization of labor at workplaces must comply with the requirements of labor protection, safety measures and the rules of industrial sanitation and hygiene.

2.10. The development of time standards was made taking into account the provision of workers with special vehicles, mechanisms and tools in relation to the nature of the work performed, as well as spare parts, materials, overalls and protective equipment necessary for the repair and maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and electrical parts power plants. For work related to lifting to a height, the use of aerial platforms and auto-hydraulic lifts is provided.

MINISTRY OF TRANSPORT CONSTRUCTION

STATE ALL-UNION ROAD SCIENTIFIC RESEARCH INSTITUTE

SOYUZDORNII

BY RATE OF CONSUMPTION
ELECTRIC ENERGY
IN ROAD CONSTRUCTION

MOSCOW 1983

Approved by the deputy director of Soyuzdornia for scientific work, Ph.D. tech. Sciences B.S. Maryshev.

Approved by Glavzapsibdorstroy (letter No. 6205/428 dated 08/21/1980), Glavdorstroy (letter No. 5606/723 dated 10/31/1980)

The main provisions on the organization of rationing the consumption of electrical energy in road construction, on the organization of control and accounting for its use are outlined. The main methods for developing scientifically based progressive consumption rates of electrical energy, their advantages and disadvantages, as well as the conditions for use, taking into account the technological features of production and the composition of equipment, are given. A detailed methodology for calculating individual technological and group norms of electrical energy consumption per unit of output and per 1 thousand rubles is given. construction and installation works. The composition of the norms of consumption of electrical energy for road construction enterprises by cost elements is given. The appendix provides the basic necessary reference data.

Foreword

At present, in conditions when the volumes of fuel and energy consumption are increasing, the costs of extraction, production and transportation are significantly increasing, it is necessary to radically improve the work to improve the efficiency of the use of fuel, electric and thermal energy.

Of paramount importance in solving these problems is the rationing of energy consumption, since in the absence of specific scientifically based consumption rates and strict control over their implementation, it is impossible to save energy resources. Reasonable norms contribute to the development of new, less energy-intensive technological processes, the elimination of irrational losses of energy resources. Therefore, systematic work is being carried out in Soyuzdornia to develop energy consumption standards in all areas of road construction:

These "Methodological recommendations for the regulation of electrical energy consumption in road construction" are intended to develop progressive scientifically based norms for the consumption of electrical energy in road construction. "Methodological recommendations" was made by Ph.D. tech. Sciences B.N. Solovyov.

1. General Provisions

1.1. Rationing of electrical energy consumption in road construction is a planned measure of its consumption with the effective use of equipment, technology and best practices.

1.2. Rationing of electrical energy consumption is understood as the development, introduction into production of progressive, technically and economically justified norms of its consumption for the implementation of savings, rational distribution and the most efficient use. The developed norms should be brought to the attention of those working at construction sites and their implementation should be monitored.

1.3. The consumption rate of electrical energy is a planned indicator of its consumption in the production of a unit of output (for example, 1 ton of asphalt concrete or cement concrete mixture, 1 km of road, etc.) established normative documents quality, or in kilowatt-hours per 1 thousand rubles. construction and installation works.

1.4. The consumption rates of electrical energy are necessary for planning its consumption and evaluating the efficiency of use.

Compliance with established consumption rates should be taken into account when providing financial incentives for saving fuel and energy resources.

2. Classification, composition and dimension of electrical energy consumption norms

2.1. The consumption rates of electrical energy are classified according to the following main features: according to the degree of enlargement - into individual and group; according to the composition of expenses - for technological and general production; by period of validity - for annual and quarterly.

2.2. The individual rate of consumption of electrical energy for the production of a unit of production is established by the types of operating units or technological schemes in relation to certain production conditions.

Group norms of electrical energy consumption are weighted averages of the totality of the corresponding individual norms.

2.3. The technological standard should take into account the consumption of electrical energy for the main and auxiliary technological processes production, namely: the cost of electrical energy in the starting mode at the beginning of work and after current repairs, as well as its technically inevitable losses during the operation of the equipment.

The technological norms for the consumption of electrical energy should not include costs caused by deviation from the accepted technology, operating modes, recipes, non-compliance with the requirements for the quality of raw materials and materials; expenses associated with defective products, unsatisfactory technical condition of equipment, and other unsustainable expenses.

Technological standards should not include the costs of construction and repair of buildings and structures, installation of equipment, putting it into operation and adjustment after a major overhaul; for research and experimental work; leave to third parties.

Such items of expenditure should be normalized separately.

2.4. Individual norms for the consumption of electrical energy must be developed for each road construction enterprise in relation to specific technological and organizational conditions that affect the consumption of electricity: the range of products, the method of delivery of materials, the location of construction organizations, the composition of technological and power equipment and other features.

2.5. The composition of the consumption rates of electrical energy includes articles of its consumption for the production of a unit of output (see Appendix).

The given composition of consumption rates must be periodically reviewed and improved as the production technology and equipment composition change.

2.6. The units of measurement of consumption rates must correspond to the volumes of production of products (works) adopted in the planning and accounting of electricity, and also provide the practical possibility of monitoring the implementation of the norms.

3. Methods for developing individual norms for the consumption of electrical energy

3.1. The development of progressive individual rates of electricity consumption is carried out on the basis of calculation-analytical and experimental methods of rationing. The main method should be taken as a calculation and analytical calculation, according to which it is carried out on the basis of determining the amount of electricity consumed per unit of final product. It is possible to use these methods together.

3.2. Settlement- analytical method individual norms are developed on the basis of an element-by-element calculation of the consumed electricity, taking into account progressive indicators of the use of equipment and electricity.

3.3. For the main initial data when determining the norms of consumption of electrical energy by the calculation and analytical method, the following should be taken:

primary technical and technological documentation, data of technological maps of the production process, technological modes and parameters, technical data of equipment and its modes of operation;

experimentally established energy characteristics of the equipment;

approved production plan, operational downtime, equipment idle time;

design and passport data of equipment manufacturers;

data of special tests and measurements carried out directly at construction sites;

plan of organizational and technical measures at the facility for saving and rational use of electricity;

reporting data on actual electricity consumption in the production of a unit of output;

the production program of the construction object for the planned period;

data on the specific consumption of electrical energy, achieved by advanced enterprises that produce similar products and have a similar composition of equipment.

3.4. The norms of electrical energy consumption obtained by calculation must be compared with the actual unit costs in advanced enterprises and with average values ​​indicated in technical data sheets equipment. In case of significant deviations, the reasons for such a discrepancy should be established.

3.5. When using an experimental method, the useful power consumption is determined on the basis of direct measurements.

3.6. In order to develop norms for the consumption of electrical energy by an experimental method, it is necessary to carry out energy tests of equipment within the established time limits. Such tests are also necessary when changing the parameters of the equipment or the technological process.

At the same time, it is necessary to systematically monitor, take into account and analyze the operating specific consumption of electricity in order to eliminate its irrational costs.

3.7. When establishing the norms for the consumption of electrical energy by an experimental method, the following conditions must be observed:

the equipment must be in a technically sound condition and adjusted in accordance with the requirements of factory instructions and technical documentation;

the mode of operation of the equipment must comply with the technological maps for the production of products;

4. Development of tasks and organizational and technical measures to reduce the cost of electrical energy

4.1. Tasks for saving electrical energy are set at all levels of planning for an average reduction in consumption rates for the planned period.

4.2. The starting materials for approving tasks for saving electricity can be proposals for an average reduction in consumption rates with calculations to justify them and plans for organizational and technical measures to reduce electricity consumption, which are submitted by the relevant planning authorities, starting from the lowest, in the order of their subordination.

4.3. The average reduction in electricity costs is planned as a percentage of the costs in the base year, for which, in current planning, the previous year is taken, and in long-term planning, the final year of the current five-year period.

4.4. To save electricity, the following main measures are being developed: the introduction of new types of equipment; introduction of new and improvement of existing technological processes; modernization and reconstruction of power and technological equipment; replacement of obsolete equipment and individual components and assemblies; reduction of electricity losses; introduction of organizational measures and a system for accounting for electricity consumption.

4.5. The plan of organizational and technical measures to save electricity consumption, the task for the average reduction in standards is developed in the manner prescribed by the "Basic Provisions for the regulation of fuel consumption, heat and electricity in national economy"(NIIPiN under the State Planning Committee of the USSR. M., 1980).

4.6. The feasibility of implementing organizational and technical measures to save electricity is evaluated in accordance with the "Methodology for a feasibility study of measures to save fuel, heat and electricity planned for implementation in industry" (NIIPiN under the State Planning Committee of the USSR. M., 1976).

5. Organization of regulation of the consumption of electrical energy and control of its use

5.1. When rationing the consumption of electrical energy, it is necessary to take into account the conditions of production, the achievements of scientific and technological progress, plans for organizational and technical measures that provide for the rational and efficient use of electricity. The norms should be systematically reviewed taking into account the planned technical progress of production, the most economical indicators of the use of energy resources, changes in technologies or the composition of equipment.

5.2. The organization of rationing the consumption of electrical energy is as follows:

develop a methodology for rationing the consumption of electrical energy and bring it to the immediate specific performers;

analyze and provide control over the implementation of the established norms of electricity consumption and tasks for their average reduction;

develop and implement a plan of organizational and technical measures to reduce the consumption of electrical energy;

control the timing of the implementation of the plan of organizational and technical measures and tasks for the average reduction in electrical energy consumption for the planned period.

5.3. Documents on the rationing of the consumption of electrical energy are developed and approved in accordance with the "Basic provisions for the rationing of the consumption of fuel, heat and electricity in the national economy."

5.4. Methods and instructions for rationing electricity should be periodically reviewed, taking into account changes in the technology used, the composition of equipment and the organization of production.

5.5. Control over the implementation of electrical energy consumption standards must be carried out with the help of appropriate instruments - wattmeters, meters, etc., which are installed in accordance with the rules for their technical operation. All large units (dryers, bitumen heaters, mixers) must be equipped with devices for individual metering of consumed electricity.

6. Methodology for calculating the norms of consumption of electrical energy in road construction

6.1. With the calculation and analytical method, the total rate of electricity consumption for a separate work area (facility) W about(kWh) is obtained by calculating each cost element and summing them:

W about = W01 /W02 + W03 + W0,

where W0- electricity consumption for each individual technological operation or work, kWh.

The rate of electricity consumption for one construction object (or one type of product) H 0 (kW h / thousand rubles) is calculated by the formula

where By- the planned volume of construction and installation works at the design facility, thousand rubles.

To calculate the rate of electricity consumption for several objects on the construction site Well(kW h / thousand rubles) use the formula

where W vol.1,…Wi- electricity consumption at individual facilities, kWh;

P 1,…Pi- the volume of construction and installation works at individual facilities, thousand rubles;

W y- total electricity consumption at all site facilities, kWh;

P y- the volume of construction and installation works at all sites of the site, thousand rubles.

6.2. Technological norms for the consumption of electrical energy are established by expense items in accordance with the structure of the norms (see Appendix).

6.3. Technological rate of electricity consumption per unit of finished product (for example, 1 ton of asphalt concrete or cement concrete mixture, 1 m 3 of reinforced concrete products, etc.) H 1(kW h / t) is determined in relation to certain types of consumers of electrical energy according to the formula

where W M- electricity consumption for the drive of technological mechanisms for the billing period, kWh;

ΔW M- electricity losses in the electrical equipment of technological mechanisms, kWh;

P- the planned volume of output for the billing period in the accepted units of measurement (t, m 3, etc.).

6.4. Calculation of the general shop rate of electricity consumption H 2(kWh per 1 unit of finished product) is recommended to be carried out according to the formula

where W2- power consumption for the drive of mechanisms of the second group, not directly included in the technological process, kWh (ventilation of workshop premises, heating, etc. according to the structure given in the appendix);

W os- electricity consumption for lighting industrial premises, kWh;

Δ W2- loss of electricity in the electrical networks of the workshop, kWh.

6.5. Factory-wide rate of electricity consumption H 3(kWh per 1 unit of finished product)

where W 3- electricity consumption by electric consumers of the third group, auxiliary work performed on their own, kWh (operation of electric forklifts, etc. according to the structure given in the appendix);

W FROM- electricity consumption for lighting the territory of the enterprise, kWh;

∆W3- electricity losses in factory electrical networks and transformers, kWh.

6.6. Electricity consumption by individual consumers or by each group W T(kWh) should be determined by the formula

W T = P y K n,

where RU- installed power, kW;

K N- installed capacity utilization factor;

R cf- average power consumption for the busiest shift during the billing period, kW (determined experimentally);

ΣP N- total installed power of electrical receivers, kW.

6.7. Useful time of use power load electricity consumers in the billing period τ (for example, year), h:

where t- the number of hours of equipment operation per day, depending on the number of shifts, is taken as 24, 16 or 8 hours);

m- the number of holidays and days off in a year;

BUT- the number of days of equipment downtime due to overhaul and other reasons;

A r- equipment downtime during the shift, % (of the total time of its operation for the billing period).

6.8. Electricity consumption H(kWh per 1 unit of production, for example, 1 ton of asphalt concrete or cement concrete mixture, 1 m 3 reinforced concrete structures and parts, etc.) are determined by the formula

where Wc- total electricity consumption over time τ all technological electrical consumers involved in the production of products, kWh;

P in- planned output for the billing period τ (t, m 3, etc.).

6.9. The technological rate of consumption of electrical energy (kW h / m 3) in the production of 1 m 3 of non-metallic materials for the planned period is calculated by the formula

where W K- electricity consumption in a quarry for technological goals, kWh;

W d- electricity consumption in the crushing and screening shop for technological purposes, kW;

Etc- the number of products produced for the billing period.

6.10. Annual electricity consumption for heating and ventilation W av kWh) is calculated by the formula

W av = W f Tτ in K,

where W f, - actual power consumed by drive motors, kW (determined by calculation or by control measurements);

T- number of days of operation of the fan (or heating installation) in the planned period;

τ in- fan operation time for a “typical” day, h;

To- power reserve factor (Table 1).

Table 1

A "characteristic" day is defined as follows:

a) according to the calculated load schedule, or according to the entries in the logbook, or according to the diagrams of recorders for previous periods of work, the electricity consumption for the reporting period of time (month, year) is established;

b) by dividing the established consumption by the number of working days, calculate the average daily consumption of electricity;

c) according to entries in the watch log or instrument diagrams for the previous period, a day is identified in which the electricity consumption is equal to or close to the average daily consumption obtained.

The day determined in this way and the actual schedule of their load are taken as a "characteristic" day.

6.11. Electricity consumption for lighting W os(kW h) is determined by the formula

W os = PSK c K d τ o 10 -3 ,

where R- specific power consumption per unit of illuminated area, W / m 2 (for a warehouse of raw materials - 7 W / m 2, molding shops - 8 - 10, other premises - 7, public buildings and laboratories - 15 - 18, territories - 0.4 W / m 2);

S- area of ​​industrial premises, m 2;

K s- average value of the demand factor for lighting loads:

Small industrial buildings 1.00

Outdoor and emergency lighting 1.00

industrial buildings,

including individual large spans 0.95

administrative buildings, libraries,

catering establishments 0.90

Industrial buildings, consisting

from several separate rooms 0.85

Laboratories, offices, medical and

children's institutions 0.80

Warehouses, distribution devices and substations 0.60;

τ about- time of using the maximum lighting load for the billing period, h;

K d- safety factor of lighting installations (Table 2).

table 2

6.12. Electricity consumption for welding work in electric arc welding and power supply of welding machines with alternating current Wc in(kW h) is determined by the formula

where U- welding arc voltage, V;

J- strength of the welding current, A (from the passport data of the equipment);

τ s- total welding time, h;

To- coefficient taking into account the burning time of the arc ( To=0.35÷0.55 in serial production);

η - efficiency of the welding installation, η = 0.6÷0.85.

6.13. Losses of electricity in electrical units and networks Δ W with(kWh) in aggregated calculations can be calculated by the formula

Δ W with= (0.03÷0.06) W c ,

where W with- total electricity consumption by the corresponding electrical consumers, kWh.

in electrical devices (including electric motors) and technological mechanisms 3-6

in electrical networks of workshop 3-6

in factory electrical networks and transformers 2-4.

Losses for the calculation period (month, quarter, year) can also be calculated by multiplying the losses for a "typical" day by the number of days in the calculation period.

6.14. To calculate the group weighted average rates of electricity consumption H gr(kWh per unit of production) use the formula

where P- the number of production units included in the subordination of this level of planning;

Hi- norms of electrical energy consumption for the production of a unit of the same product for lower subdivisions of a given level of planning (for example, trusts in relation to central offices; TsBZ, ABZ subordinate to the trust, etc.);

Pi- the planned volume of subordinated to this level of planning (m 3; t; thousand rubles of construction and installation works or in other units of measurement).

Appendix

Approximate composition of electrical energy consumption rates for road construction enterprises

Electricity consumption items

Unit of measurement, m 3, t, etc.

Electricity consumption per unit of measurement, kWh

Energy consumption rate per unit of measurement

Technological standards

Electric energy consumption for technological processes (including keeping the process equipment in a hot state, its heating and start-up after current repairs and downtime)

Losses of electrical energy in technological devices and installations

General production shop norms

Consumption of electrical energy, which is part of the technological standards

Consumption of electrical energy for auxiliary needs of workshops:

heating

ventilation

lighting

air curtains

operation of internal transport

work of shop repair shops

household needs ( hot shower, wash basins, etc.)

energy losses in intrashop electrical networks

General production factory norms

Consumption of electrical energy, included in the general production shop norms

Electric energy consumption:

for the production of compressed air

water supply

production needs of auxiliary services (laboratories, warehouses, etc.), including their heating, lighting, ventilation

operation of intra-factory transport (electric cars, cranes, railway transport)

outdoor lighting of the territory and construction sites

electricity losses in factory networks and transformers

Consumption of electrical energy for construction and installation work performed on our own:

work of lifting mechanisms and machines and electrified tools

ground heating

drying and heating of buildings and structures under construction

construction site lighting

welding work

production needs of auxiliary shops and services, including lighting, heating, ventilation

water supply and pumping of water at construction sites

sanitary and hygienic and household needs

losses in electrical networks and transformers

MINISTRY OF AGRICULTURE OF THE RUSSIAN FEDERATION

ON REGULATION OF WORK OF VETERINARY SPECIALISTS

Developed in order to establish the procedure and determine the labor costs of veterinary specialists when carrying out preventive, health-improving, therapeutic, veterinary and sanitary measures, veterinary and sanitary examination of food raw materials, products of animal and vegetable origin, laboratory research biological objects, state veterinary supervision and other veterinary works.

They are advisory in nature and can be used by the executive authorities of the constituent entities of the Russian Federation in the field of veterinary medicine, the Rosselkhoznadzor and its territorial bodies, as well as organizations and institutions subordinate to them, to make calculations on the rationing of the work of specialists engaged in activities in the field of veterinary medicine.

1. GENERAL PROVISIONS

1.1. The recommendations were developed in order to establish the procedure for determining the labor costs of veterinary specialists when carrying out preventive, health-improving, therapeutic, veterinary and sanitary measures, veterinary and sanitary examination of food raw materials, products of animal and plant origin, laboratory studies of biological objects, state veterinary supervision and other veterinary work .

Methodology for rationing the work of workers, adopted in the agro-industrial complex of the Russian Federation;

Methods for diagnosing, preventing infectious diseases, rules for veterinary and sanitary examination of products of animal and plant origin, laboratory studies of biological objects in veterinary medicine and other veterinary work;

Other regulatory legal acts of the Russian Federation regulating activities in the field of veterinary medicine.

1.4. Time norms are developed for the most common conditions for the implementation of veterinary activities, veterinary work and contain the norms of operational time, time for preparatory-final and other types of work, time for rest and personal needs.

1.5. Operational time norms are determined per unit of veterinary activities and work, taking into account norm-forming factors.

1.6. Taking into account the peculiarities of veterinary activities, the norms of operational time are established for individual, group and mass veterinary work. Individual work is associated with the implementation of such types of work that are performed in relation to one animal, individual treatments, research, group work - in relation to a group of animals, group treatments, research, mass work covers big number animals, numerous simultaneous studies of samples of biological materials.

1.7. The norms of time for preparatory-final and other types of work, rest and personal needs are determined for veterinarians, inspectors, paramedics, laboratory assistants and veterinary orderlies per year.

1.8. Time norms are divided into typical and individual. Standard time standards are developed and applied in the presence of highly qualified performers and the provision of their workplace with tools, equipment, medicines and other means in accordance with the mandatory lists of equipment necessary for the work of veterinary specialists. Individual time standards are developed in case of a significant difference in the conditions for the implementation of veterinary work from those laid down in the standard ones (lack of highly qualified specialists, use non-standard equipment etc.). When introduced into the practice of veterinary specialists, more modern methods and methods of work, new more productive machines, tools and equipment not provided for by these standards, individual time standards are also established.

1.9. Prior to the introduction of the recommended time standards in veterinary institutions, manufacturing enterprises, it is necessary to bring the organizational and technical conditions of veterinary activities in line with the accepted standards and instruct the performers.

1.10. Equipping veterinary institutions, veterinary services of enterprises with tools, equipment, medicines, biological products, reagents and other means is carried out according to the mandatory list of equipment necessary for the work of veterinary institutions and specialists.

2. CLASSIFICATION OF WORKING TIME

VETERINARY WORKERS

The working time of veterinary workers is divided into work time and break time.

2.1. Hours of work - this is the period of performance of the production task, during which the employee performs: preparatory and final, operational, casual, unproductive work and work to maintain the workplace.

The time of the preparatory and final work is spent by the performer (a group of performers - two or more veterinary specialists performing veterinary work) on methods and actions related to preparing for the performance of the production task (veterinary work) and its completion. It includes the time for putting on and taking off overalls and shoes at the beginning and end of the working day, during the lunch break; to receive production assignments and instructions from managers and specialists; transition from the sanitary checkpoint to the place of work and back; washing hands, shoes, preparing and cleaning the workplace; work with literature, etc.

Time of operational work - time of direct performance of veterinary work. It consists of time to perform the main and auxiliary work.

The time of the main work is spent on actions aimed at the object of labor, changing its quantitative and qualitative state. The impact results are the ultimate technological goal.

Auxiliary work time is spent on techniques and actions that ensure the successful completion of the main work. It is not associated with a direct impact on the object of labor, but without it it is impossible to perform the main work.

The time of organizational and technical maintenance of the workplace is spent on methods and actions related to maintaining the workplace in a normal state, caring for equipment, adjusting instruments, tools, checking the quality of their work, and eliminating minor technical problems.

The time of casual, unproductive work is the time spent by veterinary workers on work not related to the performance of the production task, i.e. not covered by their official duties.

2.2. The break time is subdivided into the time of regulated (normalized) breaks, i.e. expedient, included in the norms of labor costs, and the time of unregulated (non-standardized) breaks.

The time of regulated breaks in work is connected with the personal needs and rest of the performers, with the technology and organization of work.

Rest breaks are the time used by performers to maintain normal performance throughout the working day.

The time of breaks due to production technology and the organization of the work process (organizational and technological breaks) includes the time of forced waiting by veterinary workers for the beginning, continuation and completion of work, during which the worker cannot be engaged in other types of work (short-term waiting for the result of setting up a reaction, monitoring operation of the equipment during the execution of work, etc.).

Unscheduled breaks include downtime due to untimely issuance of tasks, inconsistency in the actions of veterinary specialists and heads of production units, irrational placement of veterinary workers at certain stages of the workflow, untimely supply of the necessary materials and tools for uninterrupted work. Unscheduled breaks can also depend on the performers and are often associated with violations of labor discipline.

All unscheduled breaks are classified as non-standardized time, although they are recorded in the actual balance of working time during photochronometric observations.

The amount of time spent on preparatory and final, operational work, on organizational and technical maintenance of the workplace, as well as time for rest, personal needs of the performer and breaks due to technology and organization of work, constitute the normalized time.

3. METHODS OF REGULATION OF LABOR

3.1. To carry out work on labor rationing, state veterinary institutions and veterinary services of enterprises with a well-established work technology are selected, if possible, with equal organizational and technical conditions, with the best organization labor of employees performing work in a timely manner according to approved methods.

3.3. With the total rationing method, the labor process is not divided into constituent elements. Time norms are established experimentally and statistically for veterinary work as a whole according to average labor costs or on the basis of the experience of raters. With such rationing, it is impossible to establish the causes of low or high labor productivity, to identify reserves for its increase based on the optimization of the labor process. This method is used when rationing the cost of working time for rarely performed work (development of plans for veterinary measures, reporting, business trips, etc.).

3.4. The main method of rationing is analytical, which involves the decomposition of labor processes into component parts (elements of work) followed by a detailed study of the cost of working time for each element of work. The organization of element-by-element rationing consists of the following elements:

the study of production conditions and the labor process itself: methods and techniques for performing work, the cost of working time for each element of work, the actual production and its dependence on different working conditions (norm-forming factors);

analysis of the results of photochronometric and timing observations in order to identify opportunities for reducing working time for the implementation of individual elements of the labor process;

designing a rational construction of labor processes and calculating a scientifically based labor standard;

rationalization of the labor process, including the choice of the most effective forms division and cooperation of labor, the expedient organization of labor at workplaces, their uninterrupted supply of instruments and materials, the use of advanced techniques, etc.;

development of organizational and technical measures to ensure the introduction of progressive standards into the practice of veterinary institutions and services.

3.5. The analytical method of normalization has two varieties: analytical-experimental and analytical-calculative. The first involves conducting chronometric and other observations under typical conditions to determine the norms of labor costs, the second - the definition of labor standards using pre-prepared standards for the elements of the labor process.

3.6. When determining the time spent on performing work by type, photo timing, photos of the working day and timing are used.

3.7. The photo of the working day of the performers is carried out in order to study the actual workload of veterinary workers during the working day, develop measures to improve the organization of work and eliminate the loss of working time.

The main tasks of working day photography are:

determination of the composition of the costs of working time, labor intensity and employment of employees during working hours;

rationing the time of preparatory-final and other types of work, regulated and unregulated breaks, as well as determining the unit time spent on the performance of work not provided for by the official duties of employees;

identifying the causes and measuring the loss of working time.

A photograph of the working day of a veterinarian, veterinary paramedic, laboratory assistant, veterinary orderly is carried out several days in a row in any month of the year and continues for a period during which the entire cycle of work is performed.

During the period of photographing the working day, the observer must record the current time and the names of sequentially performed works and operations. At the same time, a separate entry is made for each new type of work performed by the observed.

Each entry in the observation list must be formulated in such a way that it is clear what kind of work and operation was performed by the observed, the scene of action, the tools used, the amount of material, animals.

3.8. Chronometric observations are carried out to determine the time spent on performing veterinary work by their types and elements.

In the process of timing, the scope of duties and the specific weight of the participation of the relevant category of performers in this type of work are specified. Timing is carried out in the presence of the required number of specialists, support personnel, the provision of performers with reagents, tools in accordance with the standards, subject to the performance of work at a pace designed for the average level of qualification of workers.

Timekeeping observations by types and elements of work are carried out in the following stages:

Selection of qualified performers with at least three years of experience in their specialty and at least a year in this position;

The division of the timed type of work into its constituent elements;

Monitoring the work of the performer and fixing the time spent on each element of the work;

Processing of the results of chronometric observations.

Timing of certain types and elements of work is carried out within one or several days, depending on their organization and technology. Accounting for the costs of working time by types and elements of work is carried out in at least three repetitions, followed by the calculation of their arithmetic mean values.

When performing some elements of the work that do not require the constant presence of the performer, the time is taken into account partially, since other types of work are also performed in parallel.

3.9. Photochronometry is a combined type of observation, which is a combination of photography of the working day and timing of individual types of work.

Photochronometric and timing data are entered into observation sheets, which contain information about the performers (last name, first name, patronymic, position, work experience in the specialty and positions in this institution).

Sheet of chronometric observation of the labor process

veterinary specialist

Type of work performed: _____________________________________________________

Date of observation: ____________________________________________________________

Start of observation: ______________ End of observation: __________________________

Address of the veterinary institution: ______________________________________________

Veterinary Specialist: __________________________________________________________

Assistants: _________________________________________________________________

(in the presence of)

Kind of animal: ______________________________________________________________

Age: _____________________________________________________________________

Note: _________________________________________________________________

____________________________________________________________________________

Fixing points, min

The duration of the labor reception, min

Types of employment

the ending

3.10. In the process of performing a particular work, unscheduled breaks may occur for reasons beyond the control of the performers. Therefore, the duration of such breaks should not be included in the time spent on the work during which they occurred.

4. REGULATION OF WORK OF VETERINARY SPECIALISTS

STATE BUDGETARY INSTITUTIONS SERVING

FARM ANIMALS

4.1. Organization of work of veterinary specialists of state budgetary veterinary institutions (organizations) (hereinafter referred to as veterinary institutions) serving farm animals.

4.1.1. Veterinary specialists of veterinary institutions carry out preventive and forced anti-epizootic, veterinary-sanitary and therapeutic measures on farms of enterprises different forms property, peasant (farm) and personal subsidiary plots of citizens in accordance with the requirements of federal legislation in the field of veterinary medicine.

4.1.2. Veterinary specialists of veterinary institutions carry out mandatory veterinary activities in accordance with the state task.

4.1.3. In addition to the state assignment, veterinary institutions provide public services to consumers of veterinary services and carry out other veterinary activities on the basis of contracts for a fee.

4.1.4. Veterinary specialists of veterinary institutions in municipalities of rural areas and cities plan and carry out veterinary services for livestock farms, animals of peasant (farm) and personal subsidiary plots of citizens located in their area of ​​activity. The organization of the work of specialists complies with the provisions.

4.2. The work performed by the heads of veterinary institutions includes:

Selection and placement of personnel of veterinary workers, organization of jobs, preparation job descriptions;

Organization, control and coordination of the activities of subordinate veterinary workers;

Conclusion of contracts, agreements, contracts;

Drawing up business papers;

Preparation of veterinary reports and their submission to higher institutions, governing bodies;

Organization of paid veterinary services;

Drawing up and monitoring the implementation of the plan of financial and economic activities;

Control of accounting and use of material resources;

Dealing with letters, applications and complaints from legal and individuals;

Training.

4.3. The work performed by veterinarians of veterinary institutions serving farm animals includes:

Preparation, registration and issuance of veterinary accompanying documents;

Registration of passports, chipping (identification) of animals, entering data about the animal and the owner into a single database;

Implementation of anti-epizootic measures (allergic tests, vaccinations, deworming and other treatments);

Epizootological survey of farms;

Monitoring the fulfillment by the owners of animals of the appointments of veterinary specialists;

Visits to the owners of animals for the implementation of planned and forced veterinary measures;

Autopsy of animal corpses, making pathoanatomical diagnoses, taking pathological material, referral to the laboratory, execution of protocols (acts) of autopsy;

Drawing up contracts for veterinary services for animals and performing veterinary work;

Drawing up veterinary reports, veterinary accompanying documents, maintaining other veterinary office work on paper and electronic media;

Accounting and safety of forms of documents of strict accountability;

Registration of animals for veterinary care;

Control of the veterinary and sanitary condition of livestock farms, complexes, poultry farms, storage facilities and other objects;

Participation in seminars, congresses, meetings and other events;

Implementation of educational work among the population, owners of animals on veterinary issues;

Training.

4.4. The work performed by veterinary paramedics of veterinary institutions serving farm animals includes:

Collection of biological materials from animals for laboratory research;

Maintenance of animals in a hospital, isolation ward of a veterinary institution or farm;

Preparation and implementation of veterinary measures (vaccination, deworming, disinfection, deratization, disinfestation, disinfestation, other treatments, administration of drugs, surgical manipulations, simple surgical operations, obstetric and gynecological care, euthanasia of animals according to indications);

Assistance to the veterinarian in accounting for the institution's material resources;

Participation in collective meetings of the veterinary institution;

Training.

5. REGULATION OF WORK OF VETERINARY

SPECIALISTS OF PRODUCTION ENTERPRISES SERVING

FARM ANIMALS

5.1. Organization of work of veterinary specialists of industrial enterprises of the agro-industrial complex (hereinafter referred to as industrial enterprises) serving farm animals.

5.1.1. Veterinary specialists of production enterprises carry out preventive and forced anti-epizootic, veterinary-sanitary and therapeutic measures on farms of enterprises of various forms of ownership and farms in accordance with the requirements of federal legislation in the field of veterinary medicine.

5.1.2. Veterinary specialists of manufacturing enterprises are employees. Their work schedule is approved by the heads of enterprises in accordance with the Labor Code of the Russian Federation.

5.2. The work performed by the heads of veterinary services of production enterprises includes:

Selection and placement of personnel of veterinary workers, organization of jobs, preparation of job descriptions for employees;

Control and coordination of the activities of subordinate veterinary workers;

Conducting meetings, planning meetings;

Drawing up prospective, current and operational plans for veterinary activities;

Organization of work of employees of veterinary services;

Drawing up applications for veterinary drugs, consumables, tools, equipment;

Drawing up veterinary reports and submitting them to veterinary institutions of rural municipal districts (cities);

Organization of treatment and preventive measures;

Organization of measures for the prevention and elimination of infectious and parasitic animal diseases;

Notification of veterinary institutions of districts (cities) on cases of detection of infectious and parasitic diseases;

Training.

5.3. The work performed by veterinarians of production enterprises serving farm animals includes:

Reception of animals (clinical examination, prescription of treatment);

Re-admission of animals, adjustment of treatment;

Consultation of personnel serving animals on veterinary issues;

Taking biomaterial for laboratory research (blood, scrapings, secretions, etc.);

Diagnostic tests ( ultrasound procedure, radiography, endoscopy, electrocardiography, ophthalmoscopy, gynecological and andrological examinations, etc.);

Treatment of animals suffering from internal non-contagious, obstetric-gynecological, surgical, infectious and parasitic diseases;

Implementation of local, general, combined anesthesia;

Implementation of anti-epizootic measures (allergic research, sampling of biological materials for laboratory research, vaccination, deworming and other treatments);

Epizootic survey of enterprises;

Control over the fulfillment by personnel serving animals of the appointments of veterinary specialists;

Autopsy of animal corpses, making pathoanatomical diagnoses, taking pathological material, referral to the laboratory, registration of protocols for autopsy of corpses;

Obstetric and gynecological care for normal and pathological childbirth;

Organization of the implementation of plans for veterinary measures;

Drawing up veterinary reports, maintaining other veterinary records on paper and electronic media;

Accounting for material resources used in the treatment of animals, carrying out preventive treatments for animals;

Control of the sanitary condition of enterprises;

Managing the activities of subordinate employees;

Implementation of educational work on veterinary issues;

Training.

5.4. The work performed by veterinary paramedics of production enterprises serving farm animals includes:

Reception of sick animals under the guidance of a veterinarian;

Performing preventive, therapeutic and surgical procedures as prescribed by a veterinarian;

Collection of animal biological materials for laboratory research;

Preparation of animals for diagnostic, therapeutic, surgical and other procedures;

Maintenance of animals in a hospital, insulator of the economy;

Preparation and implementation of veterinary measures (vaccination, deworming, disinfection, deratization, disinsection, disinfestation, treatment, administration of drugs, surgical manipulations, simple surgical operations, obstetric and gynecological care, euthanasia of animals according to indications);

Preparation of the animal for surgery, assistance to the veterinarian during surgical procedures and operations;

Assistance to the veterinarian in maintaining veterinary records on paper and electronic media;

Preparation of the workplace, maintaining it in proper sanitary condition during the work shift;

Assistance to the veterinarian in accounting for the material resources of the veterinary service of the enterprise;

Participation in collective meetings of the enterprise;

Training.

6. REGULATION OF WORK OF VETERINARY SPECIALISTS,

PERFORMING STATE VETERINARY SUPERVISION

6.1. Organization of work of veterinary specialists exercising state veterinary supervision (hereinafter referred to as veterinary inspectors).

6.1.1. Veterinary inspectors organize and conduct state veterinary supervision over compliance by enterprises and organizations of all forms of ownership with the requirements of the legislation of the Russian Federation, including veterinary rules in the production, processing, storage and sale of raw materials and products of animal and vegetable origin.

6.1.2. Veterinary inspectors exercise control over ensuring the release of food, feed, technical products and raw materials of animal origin that are safe in veterinary and sanitary terms, carrying out activities aimed at diagnosing, preventing and eliminating infectious and other animal diseases; promoting veterinary knowledge.

6.1.3. State veterinary supervision is carried out on a scheduled and unscheduled basis through documentary and on-site inspections. The organization of work of veterinary specialists of state veterinary inspections complies with the provisions of the Labor Code of the Russian Federation.

6.2. The work performed by the heads of state veterinary inspections of the executive authorities of the constituent entities of the Russian Federation (hereinafter referred to as inspections), territorial departments of the Rosselkhoznadzor include:

Selection and placement of personnel of veterinary inspectors, organization of their jobs;

Organization of work, management and control of the activities of veterinary inspectors of inspections, territorial departments of Rosselkhoznadzor;

State veterinary supervision over compliance by all state bodies and public associations, organizations and institutions, enterprises and other economic entities, regardless of their subordination and form of ownership, officials and individual citizens with the requirements of the legislation of the Russian Federation and its subjects in the field of veterinary medicine;

Control of conditions of storage and use of biological and other veterinary drugs;

Analysis and control of the activities of veterinary services of production enterprises serving farm animals, making proposals for improving their work, improving the organizational structure, selection and placement of personnel;

Implementation of state control in the sphere of circulation medicines, monitoring the safety of medicines, analysis of activities related to state control in the field of circulation of medicines (territorial departments of Rosselkhoznadzor);

Preparation of draft reports for the management of Rosselkhoznadzor, speeches at meetings, seminars, boards of Rosselkhoznadzor, draft decisions of boards of Rosselkhoznadzor on issues of state control in the field of circulation of medicines (territorial departments of Rosselkhoznadzor);

Organization of inspections of compliance of medicines in circulation with the established mandatory requirements for their quality. Preparation of analytical information on the implementation of state control (supervision) in the field of circulation of medicines. Conducting an analysis of the results of professional activities of employees performing the functions of exercising state control (supervision) in the field of circulation of medicines, carrying out activities on licensing the production of medicines and pharmaceutical activities (territorial departments of Rosselkhoznadzor);

Monitoring the execution of orders to eliminate the identified violations of the legislation of the Russian Federation by its subjects in the field of veterinary medicine;

Conducting meetings, planning meetings;

Preparation and approval of annual inspection plans;

Drawing up applications for consumables, equipment, machinery;

Interaction with higher authorities, institutions of Rosselkhoznadzor, Rospotrebnadzor, prosecutor's office, police authorities, other supervisory authorities and executive authorities of municipalities of districts (cities);

Notification of the executive authorities of the constituent entities of the Russian Federation in the field of veterinary medicine on cases of detection of infectious and parasitic diseases;

Analysis of the effectiveness of the activities of inspections (territorial departments of Rosselkhoznadzor);

Preparation of proposals to improve the efficiency of inspections (territorial departments of Rosselkhoznadzor);

Work with letters, statements and complaints of legal entities and individuals regarding the controlled objects and activities of veterinary inspectors of inspections (territorial departments of Rosselkhoznadzor);

Ensuring the accounting and safety of forms of documents of strict accountability;

Participation in seminars, meetings and other events;

Training.

6.3. The work performed by veterinary inspectors of inspections (territorial departments of Rosselkhoznadzor) includes:

State veterinary supervision over compliance by all state bodies and public associations, organizations and institutions, enterprises and other economic entities, regardless of their subordination and form of ownership, officials and individual citizens with the requirements of legislation in the field of veterinary medicine of the Russian Federation and its subjects;

Control of conditions of storage and use of biological and other veterinary drugs;

State veterinary supervision over compliance with veterinary (veterinary and sanitary) rules for international (interstate), domestic transportation (transportation) of animals, other controlled goods by all modes of transport, as well as postal items and hand luggage;

Analysis and control of the activities of veterinary services of production enterprises serving farm animals, making proposals for improving their work, improving their organizational structure, selection and placement of personnel;

Monitoring compliance by public authorities, local governments, legal entities, individual entrepreneurs and citizens in the course of their activities with the Uniform veterinary (veterinary and sanitary) requirements for goods subject to veterinary control (supervision), approved by the relevant decisions of the Customs Union, international treaties of the Russian federation, technical regulations Customs Union;

Implementation of veterinary-sanitary and anti-epizootic measures aimed at preventing and eliminating diseases common to humans and animals, animal diseases with contagious and non-contagious diseases, protecting the territory of the Russian Federation from the introduction of contagious animal diseases from foreign countries;

Monitoring the completeness and quality of the exercise by state authorities of the constituent entities of the Russian Federation of delegated powers with the right to conduct inspections, issue mandatory instructions in accordance with the established procedure: on the elimination of identified violations and bringing to responsibility established by the legislation of the Russian Federation officials state authorities of the constituent entities of the Russian Federation exercising delegated powers (territorial departments of Rosselkhoznadzor);

Carrying out checks of compliance of medicines in circulation with the established mandatory requirements for their quality. Presentation of analytical information on the implementation of state control (supervision) in the field of circulation of medicines, as well as the implementation of activities related to licensing the production of medicines and pharmaceutical activities (territorial departments of Rosselkhoznadzor);

Registration of veterinary accompanying documents;

Registration of permits for import, export and transit through the relevant territories of goods controlled by the state veterinary supervision;

Monitoring the execution of orders to eliminate identified violations of the legislation in the field of veterinary medicine of the Russian Federation and its constituent entities;

Participation in meetings, planning meetings, seminars and other events;

Submission of the necessary information to the Rosselkhoznadzor, to regional and local government bodies;

Work with letters, statements and complaints of legal entities and individuals in relation to controlled objects;

Conducting veterinary office work, including filling out registers, issuing orders for control and supervision measures, acts of inspections, orders to eliminate identified violations, protocols for bringing to administrative responsibility, acts of sampling (samples), reports on the work done, etc. d.;

Ensuring the accounting and safety of forms of documents of strict accountability;

Carrying out educational work among officials of controlled objects, owners of animals on issues of state veterinary supervision;

Training.

7. REGULATION OF WORK OF VETERINARY SPECIALISTS,

SERVING SMALL PETS

7.1. Organization of work of veterinarians serving small animals.

7.1.1. Veterinary work in veterinary institutions and private veterinary clinics when servicing small domestic animals is carried out in accordance with the schedules of veterinary work and market demand for work (services).

7.1.2. Responsibility for the timing and quality of veterinary work carried out by veterinarians (paramedics).

7.1.3. Diagnostic, preventive and therapeutic measures for diseases of small domestic animals are carried out on an individual basis.

7.1.4. Laboratory research of biomaterials of small domestic animals is carried out in accredited veterinary laboratories, medical institutions and private veterinary clinics.

7.1.5. The staff of private veterinary clinics and veterinary treatment and prophylactic institutions in cities may include therapists, surgeons, ophthalmologists, cardiologists, anesthesiologists, specialists in X-ray diagnostics, ultrasound diagnostics, dermatologists, dentists, zoopsychologists, etc.

7.2. The work performed by veterinarians when servicing small pets includes:

Acceptance of sick animals;

Re-admission of animals;

Consultation of pet owners;

Departure to sick animals at their place of detention;

Diagnostic studies (ultrasound, radiography, endoscopy, electrocardiography, fluorescent examination, otoscopy, ophthalmoscopy, tonometry, punctures of the chest, abdominal cavities, stomach, bladder for diagnostic purposes, etc.);

Laboratory study of animal biomaterials (general blood, urine, feces; biochemical analysis of blood, feces; helminthocoprological studies; enzyme-linked immunosorbent assay for infectious and parasitic animal diseases, hormone levels; express methods for diagnosing animal diseases, etc.);

Implementation of preventive anti-epizootic measures and control over their implementation;

Treatment of animals suffering from infectious, invasive, non-contagious, surgical, obstetric and gynecological diseases;

Preoperative examination of the animal, the implementation of premedication, the introduction of anesthesia, monitoring of vital body functions, maintaining the animal in a state of anesthesia during surgical operations, withdrawal from anesthesia;

Implementation of local anesthesia;

Performing surgical manipulations, performing surgical and cosmetic operations;

Observation of an animal under inpatient treatment, in an isolation ward, postoperative box;

Extract of test results, results of diagnostic tests, accompanying documents, referrals for diagnostic tests, certificates, etc.;

Managing the work of subordinate employees;

Development of plans for anti-epizootic and veterinary and sanitary measures;

Drafting contracts for veterinary services;

Maintenance of veterinary records on paper and electronic media, preparation of veterinary reports;

Registration of orders for the purchase of materials for veterinary purposes and their accounting;

Control over the fulfillment by the owners of animals of the appointments of veterinary specialists;

Maintaining the workplace in a proper sanitary condition;

Training.

7.3. The work performed by veterinary paramedics when servicing small pets includes:

Reception of sick animals under the guidance of a veterinarian;

Consultation of animal owners on feeding, maintenance, implementation of preventive vaccinations and procedures;

Preparation of the workplace, tools and equipment for the reception and treatment of the animal;

Collection of animal biological materials for appropriate laboratory tests;

Preparation of the animal for diagnostic, therapeutic, surgical and other procedures;

Performing preventive, anti-epizootic, therapeutic, surgical procedures as prescribed by a veterinarian;

Servicing animals that are hospitalized or quarantined in a separate isolation room;

Registration of veterinary documents under the guidance of a veterinarian;

Assistance to the veterinarian in maintaining veterinary records on paper and electronic media;

Control over the sanitary condition of the premises of the veterinary institution;

Assistance to the veterinarian in accounting and ordering medicines, biomaterials, consumables, etc.;

Participation in meetings held in a veterinary institution;

Training.

8. REGULATION OF WORK OF VETERINARY SPECIALISTS,

SERVICE PROCESSING ENTERPRISES

8.1. Organization of work of veterinary specialists serving processing enterprises.

8.1.1. At present, at the enterprises of the processing industry, in accordance with the current legislation, veterinary services are provided by veterinary specialists of veterinary institutions (subdivisions of the state veterinary service at enterprises for the storage (sale) and processing of products and raw materials of animal origin). Technical control departments, physico-chemical and microbiological laboratories carry out quality control of manufactured products at dairy industry enterprises.

8.1.2. The veterinary service of processing enterprises is formed in accordance with the staffing of the enterprise and unites veterinarians - experts, paramedics, laboratory assistants, trichinelloscopists, veterinarians, disinfectors.

8.1.3. Veterinary specialists of processing enterprises carry out their activities under an employment contract in accordance with job descriptions.

8.1.4. The veterinary service of the processing enterprise ensures the release of high-quality and safe products through regular veterinary and sanitary control at all production sites.

8.1.5. The products of processing enterprises should not reach consumers without veterinary and sanitary control.

8.1.6. In their activities, employees of the veterinary service of the enterprise are guided by the law of the Russian Federation "On Veterinary Medicine", technical regulations of the Customs Union, etc.

8.1.7. In modern enterprises of the meat and dairy industry, a separate quality management system is responsible for the safety and quality of products, where an important role is assigned to the veterinary and sanitary service.

8.2. To the work performed by veterinarians - experts (included in the staff of the territorial veterinary institution and maintained at the expense of funds received from paid provision paid veterinary services) at processing plants include:

Monitoring the fulfillment by processing enterprises of the requirements of the legislation of the Russian Federation in the field of veterinary medicine;

Regular control of animals and products entering the processing plant;

Control of pre-slaughter keeping of animals;

Implementation of veterinary and sanitary measures at all production sites and assessment of the sanitary well-being of products;

Carrying out veterinary sanitary examination of meat, other slaughter products, ensuring the safety of food, feed, technical products and raw materials of animal origin;

Microbiological control of the sanitary state of production;

Sampling for laboratory research of finished products and raw materials of animal origin in accredited veterinary laboratories;

Monitoring compliance with veterinary and sanitary rules when sending substandard products for special processing, disinfection, disposal or destruction in accordance with the veterinary and sanitary conclusion;

Checking the quality of cleaning, deboning and trimming of meat, preparation of offal;

Registration of acts on low-quality raw materials and materials received by the enterprise;

Participation in the consideration of claims for the quality of the company's products; participation in establishing the reasons for the release of low-quality products, as well as in the development and implementation of measures to eliminate them;

Monitoring the state and storage conditions of products and raw materials of animal origin in warehouses (refrigerators) of the enterprise;

Control of sanitary treatment of the territory, industrial premises, equipment, transport, inventory, containers and work clothes;

Sampling for disinfection quality control;

Monitoring the correct storage of manufactured and processed products;

Control of modes of production and processing of products;

Preparation, registration and issuance of veterinary accompanying documents;

Management of the work of veterinary paramedics, laboratory assistants, orderlies;

Maintaining veterinary records, compiling veterinary reports based on the results of the work of the veterinary service of the enterprise and submitting them to a veterinary institution;

Informing the veterinary institution about the establishment (detection) of zooanthroponotic and other infectious animal diseases on the territory of the processing enterprise;

Participation in commissions that take into operation newly built workshops or determine the readiness of the enterprise for the season of mass reception and processing of livestock;

Consultation of owners of animals, products of animal origin, employees of the enterprise;

Regular notification of the management of the processing enterprise about the state of veterinary and sanitary control of the enterprise's products;

Registration of requirements for the material and technical support of the veterinary service of the enterprise;

Participation in planning meetings, meetings of the labor collective of the enterprise;

Training.

8.3. The work performed by veterinary paramedics-experts (included in the staff of the territorial veterinary institution and maintained at the expense of funds received from the provision of paid veterinary services) at processing enterprises includes:

Preparation of the workplace for veterinary specialists of the enterprise, tools, equipment, consumables, etc.;

Assistance to expert veterinarians in the implementation of veterinary and sanitary measures at all production sites and in assessing the sanitary well-being of products;

Implementation of sanitization of the territory, industrial premises, equipment, transport, inventory and packaging of the enterprise;

Monitoring the process of processing the company's products;

Monitoring the receipt of incoming products and the correct storage of manufactured and processed products;

Maintaining veterinary records based on the results of veterinary and sanitary examination, microbiological control, etc.;

Training.

8.4. The work performed by laboratory assistants at processing plants includes:

Selection, registration and preparation of samples for laboratory research;

Conducting laboratory studies of selected samples from suspicious products of animal origin;

Extract of the conclusion based on the results of laboratory tests;

Preparation of the workplace for work, laboratory glassware, tools and equipment, maintaining the workplace in a sanitary condition during the shift and cleaning it at the end of the work shift;

Disposal of examined samples, materials, reagents;

Maintaining veterinary records;

Timely notification of the results of the product examination of the head of the product quality department, the management of the enterprise;

Training.

8.5. The work performed by trichenelloscopists at processing plants includes:

Preparing the workplace and the trichinelloscope for work, maintaining the workplace in a sanitary condition during the shift and cleaning it at the end of the working shift;

Registration of incoming samples for trichinoscopy;

Extract of conclusions based on the results of laboratory tests;

Timely informing the chief veterinarian, the management of the enterprise about cases of detection of trichinella in meat and taking urgent measures to neutralize the carcass;

Disposal of the examined samples;

Training.

8.6. The work performed by veterinary orderlies at processing plants includes:

Constant maintenance of cleanliness of the workplace of veterinary specialists;

Preparation and cleaning of the workplace at the end of the shift;

Waste disposal after laboratory examination of the company's products;

Preparation of reagents, consumables, disinfectants for work;

Sterilization of instruments and consumables;

Washing and disinfection of work clothes of veterinary specialists of the enterprise.

9. REGULATION OF WORK OF VETERINARY SPECIALISTS

STATE LABORATORIES OF VETERINARY AND SANITARY

EXPERTISE ON FOOD (AGRICULTURAL)

9.1. Organization of labor of employees of state laboratories of veterinary and sanitary examination in food markets.

9.1.1. The State Laboratory of Veterinary and Sanitary Expertise, regardless of the scope of work and location, is located in isolated premises for the following purposes:

Department of Veterinary and Sanitary Examination of Meat and Fish;

Department of Veterinary and Sanitary Expertise of Milk and Dairy Products;

Department of examination of products of plant origin and honey;

Room for radiological research;

Staff room;

Washing room with pantry for small inventory;

Refrigerator (isolated refrigerating chamber) for temporary storage of meat carcasses, meat products (by-products) and other products from which samples were taken for laboratory research;

A room for the disinfection of meat and meat products (offal), equipped with digesters, autoclaves or special sterilizers;

Office of the head of the laboratory.

9.1.2. In the observation halls of the laboratory of veterinary and sanitary examination, there should be visual propaganda, posted rules for delivering food products to the market and the procedure for trading them, sampling rates and prices for veterinary and sanitary examination of food products.

9.1.3. The products entering the study are registered in the journals of the established form and the presence and correctness of the veterinary accompanying documents are checked.

9.1.4. In the laboratories of veterinary and sanitary examination, a functional, technological and qualification division of labor is provided.

9.2. The work performed by the head of the state laboratory of veterinary and sanitary examination in the food market includes:

Organization of measures to prevent the spread of contagious animal diseases through products of animal and vegetable origin;

Monitoring compliance with federal and regional legislation in the field of veterinary medicine, rules for the veterinary and sanitary examination of meat and other food products;

Consultation of owners of products of animal and vegetable origin;

Managing the work of subordinate veterinary specialists;

Notification of the head of the veterinary service of the district (city) on cases of detection of infectious and parasitic animal diseases;

Drawing up a report in the form of a 5-vet. and providing it to a higher veterinary institution on paper and electronic media;

Drawing up applications for laboratory glassware, tools, equipment, reagents, household equipment for submission to a higher veterinary institution;

Accounting for the collection of funds for paid services, registration in the statement, delivery of money to the cash desk of the institution;

Training.

9.3. The work performed by veterinarians of state laboratories of veterinary and sanitary examination in food markets includes:

Veterinary and sanitary examination of meat, dairy and other food products;

Veterinary examination, sanitary assessment of meat, milk and other food products;

Sampling for laboratory research;

Carrying out bacteriological, biochemical and other special studies of products of animal and vegetable origin;

Branding of meat;

Issuance of permits for the sale of meat and other food products;

Sampling of samples of meat and other food products for bacteriological, toxicological and other types of research in a veterinary laboratory;

Providing methodological and practical assistance to laboratory assistants in matters of veterinary and sanitary examination of milk, honey, vegetable and other food products;

Prevention of the sale of food products not subjected to veterinary and sanitary examination and recognized as poor quality, as well as livestock and poultry without veterinary accompanying documents;

Confiscation of unsuitable food products with the preparation of acts;

Organization and quality control of disinfection of conditionally suitable products;

Organization of disposal of unsuitable food products, waste samples;

Control of the sanitary condition of trade places, warehouses, refrigerators and the territory of the market;

Prohibition of the use of equipment, inventory, trade and storage of products in places that do not meet sanitary requirements;

Keeping records and registration of incoming products and performed analyzes in journals of the established form, on electronic media;

Study of veterinary certificates, certificates, references;

Quality control of disinfection;

Passing periodic internships in veterinary institutions, educational institutions;

Participation in seminars, meetings, meetings;

Collection of money from owners of animals, products, registration and issuance of receipts, cashier's checks;

Maintaining veterinary records;

Training.

9.4. The work performed by laboratory assistants of state laboratories of veterinary and sanitary examination includes:

Conducting veterinary and sanitary examination of milk and dairy products, honey, vegetable and other food products;

Study of veterinary certificates, certificates, references;

Laboratory research of milk and dairy products, honey, vegetable and other products;

Issuance of a permit for the sale of milk and other products;

Keeping records and registration of emerging products and ongoing analyzes in journals or on electronic media;

Market duty: control over the sale of dairy, vegetable and other products;

Preparation of special paints, working solutions, laboratory glassware, other means for analysis (testing);

Monitoring the operation of equipment, devices and their adjustment;

Carrying out high-quality cleaning in the market;

Preparation and cleaning of the workplace at the beginning and end of the working day;

Compliance with the instructions of veterinarians-veterinarians;

Disinfection in the laboratory premises;

Training.

10. REGULATION OF WORK OF SPECIALISTS

VETERINARY LABORATORIES

10.1. Features of labor rationing for veterinary laboratory workers:

Compliance with labor standards for the same work performed by veterinarians and laboratory assistants under similar production conditions;

Ensuring the optimality of labor costs at the same intensity for all labor processes associated with laboratory research;

Compliance of labor standards of an advanced organization with modern technologies and equipment;

Ensuring the growth of labor productivity based on the use of modern domestic and imported laboratory equipment;

Revision of labor standards as the organizational and technical conditions for performing laboratory tests change;

Strict consideration of norm-forming factors (types of means of labor, qualifications and experience of workers, organization of workplaces, sanitary and hygienic conditions, work and rest regime, volume of diagnostic studies, types of diseases, test material, methods and results of studies);

Drawing up a balance of the annual fund of working hours, depending on the duration of the working week, public holidays established by the Government of the Russian Federation and the executive authorities of the constituent entities of the Russian Federation;

Improving the material and technical base of veterinary laboratories, causing the expansion of laboratory diagnostics and the emergence of new types of laboratory work;

Regular advanced training of veterinary laboratory workers;

Narrow specialization of the staff of veterinary laboratories: veterinarian - bacteriologist, virologist, toxicologist, etc.;

Maintaining primary veterinary records in laboratory research journals and (or) in special computer programs, drawing up veterinary reports of the form N 4-vet (4-vet A, 4-vet B, 4-vet C, 4-vet G), examinations, extracting the results of analyzes of laboratory tests, etc.

10.2. The work performed by veterinarians of veterinary laboratories includes:

Preparation of equipment for work;

Laboratory study of animal biomaterials (blood, urine, feces, scrapings, mucus, secretions, hair, secrets);

Laboratory research of products of animal and vegetable origin of non-industrial production, sent for laboratory research;

Drawing up plans for diagnostic studies, logistics departments and laboratories;

Laboratory study of pathological material;

Laboratory research of feed, feed additives, etc.;

Analysis of the results of bacteriological, virological, biochemical, toxicological, mycological, serological, radiological, pathomorphological, histological and other studies;

Maintaining the workplace in a proper sanitary condition during the work shift;

Study of accompanying documents and accounting of incoming pathological material, samples of biological materials, etc.;

Visits to agricultural enterprises for examination and sampling of biological (cadaveric) material, sampling (samples), drawing up acts of sampling;

Registration of the conducted studies, execution of conclusions, examinations, answers based on the results of laboratory studies, drawing up protocols for the autopsy of animal corpses;

Advisory assistance to animal owners, representatives of agricultural enterprises, veterinary specialists;

Preparation of veterinary reports and submission to higher executive authorities in the field of veterinary medicine;

Implementation of veterinary educational work;

Accounting for the logistics departments of the laboratory;

Preparation of reports, applications, acts for the write-off of various diagnostic tools and materials, preparation of accompanying documents;

Participation in meetings, seminars, master classes;

Participation in collective meetings held in the veterinary laboratory;

Advanced training.

10.3. Work performed by veterinarians or in collaboration with laboratory assistants includes:

Acceptance of pathological material;

Pathological anatomical examination of corpses and organs of dead animals;

Preparation of pathological material for histological examination;

Preparation of smears;

Sowing on nutrient media and studying cultures of microorganisms;

Growing crops in a thermostat;

Staining of smears and their examination under a microscope;

Preparation of test samples, laboratory glassware, equipment, reagents, antigens, control sera for testing;

View cultures and their selection for the museum;

Neutralization and destruction of materials used in laboratory research;

Preparation, storage of nutrient media, checking their quality;

Implementation of serological surveys;

Bacteriological studies of water, air, feed, semen, meat, fish, milk, eggs, bees, mucus, swabs from dairy equipment, places of trade food products, samples in determining the quality of disinfection; counting somatic cells of milk, determining the species of meat, etc.;

Histological studies;

Histochemical studies;

Chemical-toxicological studies of feed, products of animal and vegetable origin;

Studies of environmental objects, feed and food products for the content of pesticides;

Determination of the sensitivity of microorganisms to antibiotics;

Research on mycoses, mycotoxicoses;

Hematological studies for leukemia;

Virological research;

Determination of the intensity of immunity in Newcastle disease, classical swine fever, etc.;

Analysis of the amino acid composition of proteins, free amino acids in blood serum, the content of macro- and microelements, vitamins;

Setting up a bioassay on laboratory animals;

Food research;

Radiological and radiochemical studies;

Study of the content of antibiotics;

Investigation of feed for nutritional value, content of vitamins, macro- and microelements.

10.4. The work performed by laboratory assistants in veterinary laboratories includes:

Preparation of the workplace, laboratory glassware and equipment for laboratory research;

Preparation of reagents, reagents, special paints, nutrient media for research;

Primary preparation of samples for research;

Regular care of laboratory animals in vivariums, control of their health;

Work on high pressure equipment;

Utilization of biological waste, materials after laboratory tests;

Preparation of laboratory animals for testing (setting up a bioassay, taking blood, etc.);

Assistance to the veterinarian in conducting laboratory tests (bacteriological, virological, biochemical, toxicological, mycological, serological, radiological, pathomorphological, histological, etc.);

Registration of the results of examinations in special journals or an electronic database;

Registration of the results of the analysis and other documents under the guidance of a veterinarian;

Monitoring the sanitary condition of instruments, equipment, premises of the veterinary laboratory;

Accounting for material resources used in laboratory tests;

Participation in meetings, meetings held by the veterinary laboratory;

Training.

11. BALANCE OF THE ANNUAL FUND OF WORKING TIME

VETERINARY SPECIALISTS

11.1. The balance of the annual working time fund of veterinary specialists is determined taking into account the number calendar days per year, the number of working days, weekends and holidays, the length of the working day, the number of working hours per week, planned absences from work.

11.2. The balance of the annual fund of working hours of veterinary specialists of state institutions of veterinary treatment and prophylaxis.

Indicators

Meaning

Calendar days

Work days

Weekends and holidays

illnesses, etc. (working days)

11.3. The balance of the annual fund of working hours of veterinary specialists of state laboratories of veterinary and sanitary examination in food markets and specialists exercising state veterinary supervision.

Indicators

Meaning

Calendar days

Work days

Weekends and holidays

Working hours according to the legislation, h

Working hours for a 40-hour work week

Planned absences from work:

next vacation (calendar days)

additional vacation (working days)

illnesses, etc. (working days)

Non-working hours in accordance with planned absenteeism

Annual effective working time fund, h

11.4. Balance of the annual fund of working hours of veterinary specialists of veterinary laboratories.

Indicators

Meaning

Calendar days

Work days

Weekends and holidays

Working hours according to the legislation, h

Working hours in a 36-hour work week

Planned absences from work:

next vacation (calendar days)

additional vacation (calendar days)

illnesses, etc. (working days)

Non-working hours in accordance with planned absenteeism

Annual effective working time fund, h

11.5. Balance of the annual fund of working hours of veterinary specialists of enterprises of the agro-industrial complex.

Indicators

Meaning

Calendar days

Work days

Weekends and holidays

Working hours according to the legislation, h

Working hours for a 40-hour work week

Planned absences from work:

next vacation (calendar days)

illnesses, etc. (working days)

Non-working hours in accordance with planned absenteeism

Annual effective working time fund, h

11.6. Annual norms for the expenditure of working time of employees of veterinary institutions for regulated breaks and other types of work, h.

Types of work and breaks

paramedics, laboratory assistants

junior staff

1. Veterinary institutions of medical and preventive profile

Preparatory and final work

Other types of work

2. District and inter-district veterinary laboratories

Preparatory and final work

Breaks for rest and personal needs

Other types of work

3. Regional, regional, republican veterinary laboratories

Preparatory and final work

Breaks for rest and personal needs

Other types of work

4. Interregional, interregional veterinary laboratories of Rosselkhoznadzor, Central Research and Production Veterinary Radiobiological Laboratory (FGBU) (hereinafter referred to as interregional, interregional veterinary laboratories)

Preparatory and final work

Breaks for rest and personal needs

Other types of work

5. FSBI TsNMVL (Central Scientific and Methodological Veterinary Laboratory) (hereinafter referred to as the Central Scientific and Methodological Veterinary Laboratory)

Preparatory and final work

Breaks for rest and personal needs

Other types of work

6. Diagnostic rooms of district (city) stations for combating animal diseases

Preparatory and final work

Breaks for rest and personal needs

Other types of work

7. State laboratories of veterinary and sanitary examination in food markets

Preparatory and final work

Breaks for rest and personal needs

Other types of work

8. Inspections and territorial departments of Rosselkhoznadzor

Preparatory and final work

Breaks for rest and personal needs

Other types of work

11.7. Annual norms for the expenditure of working time of veterinary workers of enterprises of the agro-industrial complex for preparatory and final work, regulated breaks and other types of work, h.

Types of work and breaks

veterinarians

veterinarians, laboratory assistants

junior veterinary staff

Preparatory and final work

Breaks for rest and personal needs

Other types of work

11.8. The annual fund of operational working time of veterinary workers in institutions of the State Veterinary Service of the Russian Federation and enterprises of the agro-industrial complex, part 1

Types of work and breaks

paramedics, laboratory assistants

Veterinary institutions of medical and preventive profile

Veterinary Laboratories:

regional, inter-district

regional, regional, republican

interregional, regional

Central Scientific and Methodological Veterinary Laboratory

Diagnostic rooms of district (city) stations for combating animal diseases

State laboratories of veterinary and sanitary examination in food markets

Enterprises of the agro-industrial complex

Inspections and territorial departments of Rosselkhoznadzor

12. CALCULATION OF THE LOAD ON VETERINARY SPECIALISTS

WHEN CARRYING OUT VETERINARY WORKS

12.1. To calculate the load on veterinary specialists during veterinary work, the norms of operational time for the performance of each type of work, the norms of time for preparatory and final work and regulated breaks are established.

12.2. The norms of operational time for the performance of each type of veterinary work are established based on the materials of photochronometric observations and are given in regulatory reference books.

12.3. The time limits for each type of preparatory and final work are established by photographing the working day or photochronometric observations for each category of veterinary workers separately. By adding up the costs of working time for all types of preparatory and final work performed per day, the daily norm of time for these works is established. The annual rate of time for preparatory and final work is calculated by multiplying the average daily rate of time spent by the number of working days in a year.

12.4. The time of regulated breaks (for personal needs and rest of performers) is determined by the Labor Code of the Russian Federation (Article 108), which provides for such breaks of at least 30 minutes per day, which are not included in working hours. The annual time of regulated breaks is determined by multiplying the daily norm by the number of working days.

12.5. The load on veterinary specialists (Nn) is determined by dividing the daily fund of operational time by the norm of time to perform a specific type of work according to the formula

Hn \u003d (Td - Tpz - Totl): Hb,

where Td - duration of the working day, min; Tpz - daily norm of time for preparatory and final work, min; Totl - daily norm of recommended breaks, min; Hb - the norm of time to perform a specific type of veterinary work, min.

12.6. The norm of the number of employees of state veterinary institutions and industrial enterprises is determined by the complexity of performing veterinary work according to the formula

where Ncis. - the norm of the number of employees of the corresponding category for the annual volume of veterinary work; , , , ... - norms of operational time of employees of the relevant categories to perform a unit of volume of veterinary work, min; , , ... - the annual volume of veterinary work by their types in the appropriate units of measurement; Тyear - annual effective working time fund of a veterinary worker, h; Tpz - annual rate time for preparatory and final work of employees of the corresponding category, h; Трп - annual norm of time for regulated breaks, h; Tdr - the annual norm of time for other types of work, h.

12.7. The reserves for increasing labor productivity of employees of state veterinary institutions and manufacturing enterprises by reducing the time to perform other work (), eliminating unscheduled breaks () and the general reserve for increasing labor productivity (Tp total) are determined by the formulas

,

where Tdr is the time for performing other work not included in the official duties, min; Top - time of operational work, min; Tbn - time of unscheduled breaks, min.

12.8. The effectiveness of the use of working time by veterinary workers is estimated by the coefficient of use of the working time fund (Kr) and the level of employment of veterinary workers with operational work (Uzr) according to the formulas

Kp \u003d (Top + Tpz + Trp): Trd;

Uzr \u003d Top: Trd x 100%,

where Top - time of operational work, min; Tpz - time of preparatory and final work, min; Trp - time of regulated breaks, min, Trd - length of the working day, min.

project

MINISTRY OF LABOR AND SOCIAL PROTECTION

RUSSIAN FEDERATION

REGULATION OF THE NUMBER OF FEDERAL STATE CIVIL EMPLOYEES PERFORMING STATE FUNCTIONS OF CONTROL (SUPERVISION) AND THE PROVISION OF PUBLIC SERVICES

Moscow, 2014

General provisions

II.

Calculation of typical industry norms of time for work on the implementation of state functions for control (supervision) and the provision of public services

III.

Monitoring of quantitative indicators characterizing the need for the performance of state functions for the relevant types of activities

Calculation of the number of federal state civil servants performing state functions of control (supervision) and the provision of public services

Final provisions

Appendix 1. Duty Time Photo Card

Appendix 2: Summary of duty time elements

Appendix 3. Norms of time for work for the implementation
functions of control (supervision) and provision of public services

Appendix 4

ChapterI. General provisions

1. Methodological recommendations for standardizing the number of federal state civil servants (hereinafter referred to as civil servants) performing state functions of control (supervision) and the provision of public services (hereinafter referred to as methodological recommendations) have been prepared in order to form the main approaches to determining the number of civil servants of federal bodies executive power exercising the powers to exercise state control (supervision) and to provide public services. The application of methodological recommendations will ensure a uniform approach to the calculation of labor costs for the performance of relevant functions by civil servants.

2. The Guidelines were developed in accordance with Articles 159-163 of the Labor Code of the Russian Federation, the provisions of the Federal Law of December 26, 2008 No. 294-FZ "On the protection of the rights of legal entities and individual entrepreneurs in the exercise of state control (supervision) and municipal control”, Federal Law of July 27, 2010 “On the organization of the provision of state and municipal services”, Decree of the Government of the Russian Federation of 01.01.01 No. 804 “On the rules for the development and approval of standard labor standards”, Decree of the Government of the Russian Federation of May 16 2011 No. 373 "On the development and approval of administrative regulations for the performance of state functions and administrative regulations for the provision of public services", by order of the Ministry of Labor of Russia dated 01.01.01 No. 235 "On the approval of guidelines for federal executive authorities on the development of standard industry labor standards ”, minutes of the meeting of the Government Commission for Administrative Reform dated 01.01.01 No. 137, minutes of the meeting working group on issues of development and improvement of the efficiency of the civil service, optimization of the number of its personnel dated 01.01.01 No. 5.

3. Basic concepts used in the guidelines:

labor norms - production norms, time norms, number norms and other norms - are established in accordance with the achieved level of technology, technology, organization of production and labor;

intersectoral norms - are intended for labor rationing at work performed in federal executive bodies of two or more sectors of the economy;

professional (industry) standards - are intended for the regulation of labor in work performed in federal executive bodies of one branch of the economy;

norm of time - the regulated amount of the cost of official time for the performance of a unit of work by one or more performers of the appropriate qualification in certain organizational and technical conditions at the workplace (set in hours or man-hours);

production rate - a regulated number of units of work in physical terms, which must be performed by one or more performers of the appropriate qualification per unit of time in the organizational and technical conditions characteristic of a given official place;

service rate - the number of objects (pieces of equipment, jobs, etc.) that one or more performers of appropriate qualifications are required to service during a unit of working time in certain organizational and technical conditions;

headcount standard - the regulated number of civil servants of the appropriate qualification, which is necessary to perform a certain amount of work while ensuring normal organizational and technical conditions at the workplace;

working time - the time spent by a civil servant to perform a particular job, provided and not provided for by the task;

preparatory-final time - the time spent by a civil servant to prepare for the performance of a given work and actions related to its completion;

operational time - time spent directly on the performance of a given work and equal to the sum of the main and auxiliary time;

main time - part of the operational time spent on fulfilling the goal of this process for a qualitative or quantitative change in the means of labor;

auxiliary time - part of the operational time spent on the performance of actions that create the possibility of performing the main work;

service time of the office - the time spent by a civil servant to maintain the means of technological equipment in working condition and care for them and the office;

break time - the period when a civil servant is not involved in work (divided into regulated and unregulated);

regulated breaks - time for personal needs, as well as unavoidable breaks due to the peculiarities of technology and the organization of the labor process;

time for personal needs - time spent by a civil servant for personal needs and, in case of tedious work, for additional rest;

unscheduled breaks - usually due to equipment breakdowns, shortcomings in the organization of the labor process, violation of the daily routine by civil servants and other reasons;

photograph of working time - a method for solving problems of assessing and analyzing the structure of costs and losses of working time, developing measures to improve the organization of work and increase its productivity by eliminating losses and waste of working time.

4. When developing standard labor standards for civil servants performing state functions of control (supervision) and the provision of public services (hereinafter referred to as standard labor standards):

4.1. comprehensively substantiated labor standards are used, established for homogeneous work in relation to standard labor processes and standard organizational and technical conditions for their implementation;

4.2. the most rational and expedient labor process is selected, characteristic of the entire set of homogeneous processes;

4.3. the necessary and justified number of (economic) entities is determined, in respect of which the state functions of control (supervision) are implemented and public services are provided;

4.4. a comprehensive substantiation of labor standards is established using the method of labor rationing, or the calculation and analytical method by determining the dependencies between quantitative and qualitative factors and the cost of working time based on the processing of data from the reporting of the federal executive body and research results. The establishment of labor standards can be carried out through an independent assessment of the time spent on the implementation of state functions of control (supervision) and the provision of public services, including with the involvement of an independent organization.

5. When developing population standards, it is necessary to distinguish the following stages:

5.1. calculation of typical professional labor standards;

5.2. monitoring of quantitative indicators characterizing the need for the performance of state functions for the relevant types of activities;

5.3. calculation the number of civil servants.

6. It is recommended to revise standard professional labor standards when changing the organization of labor, introducing new equipment and technologies.

7. On the basis of these methodological recommendations, the federal executive authorities are developing professional labor standards, taking into account the specifics of the activities carried out.

8. Typical professional labor standards are approved by the federal executive body in agreement with the Ministry of Labor and Social Development of the Russian Federation in accordance with the rules for the preparation of regulatory legal acts of federal executive bodies.

9. Typical intersectoral labor standards are approved by the Ministry of Labor and Social Development of the Russian Federation in accordance with the current legislation.

ChapterII. Calculation of typical industry norms of time for work on the implementation of state functions for control (supervision) and the provision of public services

1. In the standard professional time standards for the performance of state functions for control (supervision) and the provision of public services (hereinafter referred to as time standards), it is recommended to establish indicators of time standards for homogeneous work in relation to standard technological (labor) processes and standard organizational and technical conditions for their implementation .

2. When developing time standards, it is recommended to determine, for homogeneous work, the cost of official time to perform a unit of work (functions, services) by one or a group of civil servants of appropriate qualifications, including, as a rule, the cost of official time to prepare for the performance of work, as well as to process and presentation of its results.

For these purposes, it is recommended to apply the analytical method of labor rationing using the type of observation - a photograph of working time, accounting and reporting data, the results of an analysis of the organization of labor and the development of measures to improve it.

3. For the calculation of typical time standards, it is advisable:

3.1. conduct a selection of civil servants for observation (it is recommended to conduct observations of civil servants whose qualifications correspond to the level of complexity of the work and who have more than 2 years of civil service experience). At the same time, it is not recommended to select civil servants whose individual state of health can significantly affect the results of observation (persons with handicapped, pregnant women, people who have recently started work after a long break, etc.) performing the duties of a temporarily absent civil servant;

3.2. determine the intensity of labor based on indicators of the normal pace of work;

3.3. determine the number of observations (the number of civil servants and the number of observations for each of them), taking into account the nature, duration, mass character, frequency of work, the degree of their determinism and other factors, as well as sufficient accuracy of the results;

3.4. take photographs of working time, in which the following must be ensured: the serviceability of the objects of labor; the availability of the required quantity and quality of materials necessary for the performance of the work, and their timely submission; timely supply of electricity and other sources of energy supply, technical documentation; safe conditions labor. A photo of working time, in which all the costs of working time are recorded from the beginning to the end of working time, can be taken using a video surveillance system with the obligatory filling in of the photo card of working time (hereinafter referred to as the observation sheet), a sample of which is provided in Appendix No. 1 to the methodological recommendations. The observation sheet indicates all the actions of a civil servant during the working day, indicating breaks in work in the order in which they actually occurred, while fixing the current end time of each element of the operation (labor process), which, in turn, are the beginning of the next type of elements of the operation (labor process). Each entry shows either what the civil servant did or what caused his inaction;

3.5. process research results.

4. When filling out the observation sheet, the duration of each of the elements of the operation (labor process) is calculated by subtracting from the current time of the operation (labor process) each subsequent measurement of the current time of the previous operation (labor process), the results of which are recorded in the observation sheet.

5. Based on the results of observations, a summary of the elements of the cost of official time is compiled according to the model provided for in Appendix No. 2 to the methodological recommendations, preparatory and final time, time for servicing the office and time for rest and personal needs, as an arithmetic average based on the results of research.

6. Based on the average indicators of the cost of working time obtained from the results of observations, indicators of typical time norms are calculated, taking into account the preparatory and final time, the main time for doing work, auxiliary time for doing work, service time for a work place, time for rest and personal needs and time for rest allocated depending on working conditions.

7. Based on the results of the observations, labor intensity indicators for each work are determined, taking into account the conditions of the work.

8. Determining the conditions for carrying out work is carried out taking into account indicators developed on the basis of statistical data and the calculation of time for rest: depending on the degree of monotony of work, the pace of work.

The duration of the lunch break is recommended to be set from 30 to 60 minutes. Scheduled breaks are recommended to be set 2 hours after the start of the working day and 2 hours after the lunch break of 5 minutes each.

9. When developing standard norms of time for the performance of standard administrative procedures in the exercise of state functions of control (supervision) and the provision of public services by the federal executive body, standard deadlines for their execution may be established in administrative regulations.

10. The developed indicators of typical time standards are drawn up in the form special form provided for Appendix No. 3 to methodological recommendations, indicating the complexity of the work.

11. Time limits are set in hours per accepted unit of measure for the volume of each specific type of work.

12. Information on the norms of time for the implementation of administrative procedures is subject to inclusion in the administrative regulations for the performance of state functions, the provision of public services.

13. The conditions for the professional performance of a civil servant must comply with the requirements of the legislation of the Russian Federation, sanitary rules and regulations, building codes and regulations, as well as special requirements established for work using computer technology.

14. The duties of civil servants are regulated by official regulations developed in accordance with the regulatory legal acts of the Russian Federation.

15. The implementation of state functions of control (supervision) and the provision of public services by employees who are not civil servants cannot serve as a basis for any changes in time standards.

ChapterIII. Monitoring of quantitative indicators characterizing the need for the performance of state functions for the relevant types of activities

1. For information aboutvolume of work in physical terms (the actual number of inspections, public services provided), it is necessary to monitor quantitative indicators characterizing the need to perform a specific public function for the relevant types of activities (hereinafter referred to as monitoring).

2. Monitoring must be carried out for the last 3 years - a period that allows obtaining representative information on the quantitative characteristics of the implementation of the state function of control (supervision) or the provision of public services.

4. Typical administrative procedures in the exercise of state functions of control (supervision) include:

4.1. approval of the annual plan for conducting inspections;

4.2. coordination with the prosecutor's office of an unscheduled inspection (if necessary);

4.3. conducting a documentary check:

4.3.1. a request (requirement) for the subject of verification to provide materials and documents necessary for conducting a documentary verification;

4.3.2. analysis of the received materials and documents;

4.3.3. drawing up an inspection report;

4.4. field inspection:

4.4.1. informing about the conduct of the inspection and the powers of the employees conducting the on-site inspection, as well as about the goals, objectives, grounds for conducting the inspection, the types and scope of control measures, the terms and conditions for its implementation;

4.4.2. direct on-site inspection;

4.4.3. drawing up an inspection report.

5. Typical administrative procedures in the provision of public services include:

5.1. acceptance of applications (documents) for the provision of public services;

5.2. analysis of received applications (documents);

5.3. making a decision on the result of the provision of public services;

5.4. execution of a document on the result of the provision of public services;

5.5. issuance of a document on the result of the provision of public services;

5.6. provision of documents and information, including in electronic form using a unified system of interdepartmental electronic interaction and regional systems of interdepartmental electronic interaction connected to it at the interdepartmental request of a body providing a public service, a body providing a municipal service, an organization subordinate to a state body or a local government body participating in the provision of state and municipal services, or a multifunctional center.

6. Typical quantitative indicators recommended for use in monitoring include the following:

6.1. within the framework of control and supervision activities:

6.1.1. the number of objects of control (supervision);

6.1.2. planned number of checks;

6.1.3. the number of unscheduled inspections;

6.1.4. the number of inspections carried out;

6.1.5. the number of raids carried out;

6.1.6. substantiation of the scope of inspections.

6.2. as part of the provision of public services:

6.2.1. the number of applications for the provision of public services;

6.2.2. the number of public services rendered;

6.2.3. the number of refusals to provide public services.

6.3. according to the complexity of the checks:

6.3.1. checks that take more than 48 hours;

6.3.2. checks that take from 12 to 48 hours;

6.3.3. checks taking less than 12 hours.

7. Along with typical quantitative indicators, the assessment and forecasting of the volume of work should take into account the following qualitative characteristics:

7.1. within the framework of state functions for control (supervision):

7.1.1. the quality of the implementation of the state function of control (supervision), including:

7.1.1.1. number and nature of complaintseconomic entities (citizens) filed in connection with the implementation of control (supervision) measures in relation to them;

7.1.1.2. qualifications and experience of civil servants and other employees involved in the implementation of the state function of control (supervision);

7.1.2. level of information technology implementation, including:

7.1.2.1 technical equipment of the federal executive body;

7.1.2.2. automation of administrative procedures implemented in the exercise of the state function of control (supervision);

7.1.2.3. development of a system of interdepartmental and interlevel interaction;

7.1.3. the need for the level of state control (supervision), taking into account the socio-economic situation, international experience in the execution of similar state powers, including:

7.1.3.1. the number of violations that caused damage;

7.1.3.2. the need to reduce administrative barriers in order to stimulate entrepreneurial activity and others;

7.2. as part of the provision of public services:

7.2.1. the quality of the provision of public services, including:

7.2.1.1. qualifications and experience of civil servants and other employees involved in the provision of public services;

7.2.1.2. number and nature of complaintseconomic entities (citizens) filed in connection with the provision of public services;

7.2.2. implementation level information technologies, including:

7.2.2.1. technical equipment of the federal executive body;

7.2.2.2. automation of administrative procedures implemented in the provision of public services;

7.2.2.3. development of a system of interdepartmental and interlevel interaction;

7.2.3. the need to provide public services, taking into account the socio-economic situation.

8. In order to create departmental data records, federal executive authorities are recommended to collect departmental statistical information on the volume of performance of state functions of control (supervision) and the provision of public services (quarterly, semi-annual, annual) on an ongoing basis. This statistical information must be confirmed by the signature of the head of the federal executive body and posted on the official website of the body.

9. In the case of vesting an existing federal executive body with new functions, the application of these methodological recommendations must be ensured as part of a pilot project, and when determining the initial data for monitoring, use statistical information in the relevant sector of the economy.

10. In the case of a new federal executive body, when determining the initial data for monitoring, it is advisable to use statistical information in the relevant sector of the economy.

ChapterIV. Calculation of the number of civil servants performing state functions of control (supervision) and the provision of public services

1. Based on the quantitative indicators obtained at the previous stages, which make it possible to predict the norms of time for conducting one inspection (audit, diagnostics, raid, inspection, etc.) or the provision of a public service and the volume of work performed in natural terms (the actual number of inspections, public services provided ), labor costs are calculated for the performance of the state function of control (supervision) or the provision of public services (T):

where:

T - total labor costs for the performance of the state function of control (supervision), the provision of public services for 1 month (person/hour);

R - volume of work in physical terms(actual number of documents, inspections, days, public services provided, refusals to provide public services);

Tnorm - the norm of time for conducting administrative procedures implemented within the framework of one inspection or the provision of one public service (person/hour).

2. General calculation of the number of civil servants of the federal executive body performing state functions of control (supervision) or providing public services:

,

Document as of August 2014


These guidelines are intended to determine the cost of repair and maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants.

The Methodological Recommendations are based on the Standard Standards for Overhaul, Current Repair and Maintenance of Electric Networks, Electric Power Devices and Equipment, developed by the Central Regulatory Research Station (CNIS) (approved by order of the Ministry of Housing and Communal Services of the RSFSR dated September 21, 1990 N 11).

1. GENERAL

1.1. Methodological recommendations include time standards for overhaul, current repairs and operational maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants.

1.2. The guidelines are intended to determine the cost of repair and maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants. Methodological recommendations make it possible to calculate the labor intensity of repair work, the standard number of workers, labor costs in the cost price, and, consequently, in the tariff for electric energy, to bill workers, and to carry out a rational placement of personnel.

1.3. The time standards are advisory in nature and are the basis for the development and approval by the executive authorities of the constituent entities of the Russian Federation and local self-government of regional regulatory and methodological materials.

1.4. The basis for the development of time standards is based on the current legal documents:

Standard norms of time for overhaul, current repairs and maintenance of electrical networks, electrical power devices and equipment, approved by order of the Ministry of Housing and Communal Services of the RSFSR dated September 21, 1990 N 11;

Intersectoral rules for labor protection (safety rules) for the operation of electrical installations, approved by the Decree of the Ministry of Labor and Social Development of the Russian Federation of 05.01.2001 N 3;

Photochronometric observations, technical calculations and photographs of working hours;

Materials for the study of organizational and technical conditions for the performance of work and organization of labor.

1.5. The concept of "norm of time" means the amount of time spent working, established for the performance of a unit of work by an employee or a group of employees of appropriate qualifications in certain organizational and technical conditions.

1.6. The time standards are given in man-hours per unit of work for performers, the numerical and qualification composition of which is given in each paragraph of the normative part, provided that the necessary materials, tools and fixtures are provided.

1.7. The Methodological Recommendations include time standards for the most common conditions for performing work in accordance with the current safety and technical operation rules, taking into account the provision of workplaces with the necessary machinery, inventory and equipment in relation to the nature of the work performed.

1.8. Time taken into account:

For carrying out shutdowns during work performed with complete removal of voltage;

For preparatory and final work and maintenance of the workplace;

For rest and personal needs;

For moving and carrying units, assemblies and materials within the work area at a distance of up to 50 meters.

Movements of units, assemblies and materials over distances taken into account should be normalized according to the collection E1 "Internal transport work" of the Uniform norms and prices for construction, installation and repair and construction work.

1.9. The rules do not take into account the time spent on:

Implementation of measures to ensure the safety of work during partial stress relief;

Transitions (transfers) of workers to the facility and from the facility. Installed on the ground, taking into account rational route schemes that ensure minimal time spent on the movement of workers;

Development of soil and painting of structures. These works should be standardized according to the collections E2 "Earthworks" Issue 1 "Mechanized and manual earthworks" and E8 "Finishing coatings of building structures" Issue 1 "Finishing works" of the Uniform norms and prices for construction installation and repair and construction work.

1.10. When performing work in winter conditions in the open air; in hard-to-reach places; correction factors are applied near operating power lines, critical communication lines, as well as near equipment under high voltage, associated with the implementation of additional safety measures.

1.11. In the case of application of organizational and technical conditions other than those provided for in the Methodological Recommendations (organization of labor, machines and mechanisms), as well as when performing work not provided for by the Methodological Recommendations, it is recommended to develop local technically justified time standards or apply other regulatory and methodological documents.

When introducing at an enterprise more advanced than provided for in the recommendations, the organization of production and labor, the technology for performing work, equipment, equipment of machines, systems, mechanisms, etc., which increase the productivity of workers, should be developed by the method of technical regulation and introduced in the established reasonable local time standards.

1.13. The names of workers' professions are indicated in accordance with the All-Russian classifier of workers' professions, positions of employees and wage categories OK 016-94 (OKPDTF). The content of the work performed is given in accordance with issues 1, 2, 9 of the Unified Tariff and Qualification Reference Book of Works and Professions of Workers.

The performance of work by workers whose qualifications do not correspond to the tariff category specified in the Methodological Recommendations cannot serve as a basis for any changes in the norms.

In these Guidelines, if all work on the repair of any equipment is performed by a worker of the same category, then the worker's profession, indicating the category of work, is placed in front of the table with the names of the operations and the time standards for these operations, otherwise, the worker's profession, indicating the category of work located directly in the table.

1.14. The administration of the enterprise distributes workers among departments and sections, based on production needs, ensuring their rational loading. At the same time, in each individual case, the issue of performing additional functions by employees is decided, taking into account economic feasibility and ensuring the quality of work.

2. ORGANIZATION OF WORK

2.1. Overhaul of electric power devices, equipment and installations of electrical networks, outdoor lighting and the electrical part of power plants includes work related to their complete revision (regardless of technical condition); repair or replacement of worn-out elements of assemblies and parts; testing and adjustment of devices, equipment and installations in general.

2.2. The current repair of devices, equipment and installations includes all work in the period between major repairs, aimed at ensuring the normal operation of devices, equipment and installations.

2.3. Operational maintenance includes monitoring the condition of devices, equipment, installations, and eliminating minor malfunctions.

2.4. The sequence of current and major repairs is established in accordance with the schedules of the system of preventive maintenance.

2.5. Works on capital, current repairs, maintenance of equipment and installations are carried out at their location, as well as in laboratories, workshops and repair shops of electric power enterprises.

2.6. The work must be carried out by workers of appropriate qualifications, familiar with the rules for the production of work and safety precautions.

2.7. Before starting work, workers are given an order or a standardized work assignment, in accordance with which they prepare their workplace: they deliver the necessary tools, parts, assemblies, receive drawings and instructions from the foreman or foreman.

2.8. Capital, current repairs and maintenance of equipment, installations and networks, depending on the nature of the work, are carried out by one performer or a link of performers. If the work is performed by a link of 2 performers, then one of the workers is the direct executor of the corresponding operation, and the second one conducts supervision, which ensures normal conditions for the performance of work, due to safety regulations, and also performs auxiliary work (supply of materials, tools, preparation of bindings, installation of fences, etc.).

2.9. The organization of labor at workplaces must comply with the requirements of labor protection, safety measures and the rules of industrial sanitation and hygiene.

2.10. The development of time standards was made taking into account the provision of workers with special vehicles, mechanisms and tools in relation to the nature of the work performed, as well as spare parts, materials, overalls and protective equipment necessary for the repair and maintenance of electric power devices, equipment and installations of electrical networks, outdoor lighting and electrical parts power plants. For work related to lifting to a height, the use of aerial platforms and auto-hydraulic lifts is provided.

3. REGULATORY PART

3.1. Overhaul

3.1.1. Electrical equipment of substations

Name of operations and content of work Profession Category of work Time norm N Power of transformers, kVA up to 63 100 160 180 250 320 400 560 1000 3.1.1.1. Transformers, power oil, voltage 6 - 10 kV

Electrician for the repair of switchgear equipment 2 0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61 1

Preliminary tests to measure the insulation resistance R 60 of the windings, the adsorption coefficient R60/R15 or to determine the need for drying the active part

0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 0.33 2 Electrician for repair of switchgear equipment 2

Draining oil from the transformer tank expander and withdrawable part

The same 2 0.50 0.56 0.58 0.63 0.71 0.71 0.84 1.27 1.69 3

Disassembly of the transformer with lifting of the withdrawable part

-"- 3 2,33 2,66 2,97 3,51 4,12 4,60 5,27 6,42 8,27 4

Holding electrical measurements

Test and measurement electrician 4

0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 0.91 5 Electrician for repair of switchgear equipment 4

Inspection, cleaning and checking parts

The same 4 2.43 3.03 3.32 3.69 4.10 4.43 4.78 5.81 6.17 6

Replacing the winding of one phase with unloading and back loading of the magnetic circuit and replacing all necessary parts

Electrician for repair of windings and insulation of electrical equipment 3 5.00 5.34 5.76 6.32 6.88 7.21 8.38 9.30 14.37 7

Carrying out electrical measurements during the drying process

Test and measurement electrician 4

1.95 1.99 1.99 1.99 2.33 2.38 2.45 2.92 3.43 8 Electrician for repair of switchgear equipment 4

Transformer assembly

The same 4 2.79 3.10 4.10 4.66 4.70 5.35 7.02 8.95 11.43 9

Filling oil into the transformer

-"- 4 0,44 0,49 0,51 0,58 0,59 0,64 0,83 1,04 1,69 10

Carrying out measurements and testing of the transformer after repair

Test and measurement electrician 4 2.95 3.22 3.46 3.53 3.56 3.80 3.95 4.11 5.42 11

Electrician for the repair of switchgear equipment 4

Transportation of the transformer to the warehouse using a hoist

The same 4 0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61 0.61 12

Name of operations and content of work Profession Category of work Norm of time N pos. 3.1.1.2. Voltage transformers 6 - 10 kV (in workshop conditions)

Time limits for 1 transformer

Transportation of the transformer by hoist to the workplace (up to 50 m)

Electrician for the repair of switchgear equipment 2 0.50 1

External inspection of the transformer

The same 2 0.07 2

Draining the oil from the transformer

-"- 2 0,42 3

Unscrewing bolts and covers, dismantling the contact system and marking

-"- 3 0,95 4

Determination of the adsorption coefficient to determine the need for drying

Chemical analysis laboratory assistant 3 1.26 5

Immersion of the active part in clean transformer oil

Electrician for the repair of switchgear equipment 3 0.38 6

Gasket replacement

The same 2 0.56 7

Cleaning contacts and lubricating them with Vaseline

-"- 2 0,90 8

Transformer assembly

-"- 3 3,38 9

Vacuuming and pouring oil into the transformer

-"- 3 0,82 10

Cleaning the external surfaces of the transformer

-"- 2 1,31 11

Transformer painting

(See collection E 8-1)

Megaohmmeter voltage

2 500 V primary windings,

1,000 V secondary windings

Electrician for testing and measurements 4 0.50 12 Electrician for repair of switchgear equipment 4

Voltage instrument transformers with normal insulation

Electrician for testing and measurements 4 1.37 13 Electrician for repair of switchgear equipment 2

Checking the group of connections of three-phase and polarity of single-phase

Electrician for testing and measurements 4 1.13 14 Electrician for repair of switchgear equipment 2

3.1.1.3. Load switch VNR-10, VNRP-10, VNA-10

Removing dust and dirt

Electrician for the repair of switchgear equipment 2 0.42 1

Circuit Breaker Inspection

The same 2 0.12 2

Disconnecting tires and rods

-"- 2 2,14 3

Circuit breaker recess

-"- 2 0,05 4

Drive disassembly

-"- 2 0,37 5

Inspection, repair or replacement of defective parts

-"- 2 0,57 6

Cleaning and lubricating contacts

-"- 2 0,71 7

Checking the density of contact between moving and fixed contacts

-"- 2 0,29 8

Checking the simultaneous contact of the knives with the contacts

-"- 2 0,23 9

Assembly of the drive and installation of the circuit breaker

-"- 2 1,35 10

Installation of rods and connection of tires

-"- 2 1,56 11

Drive and lock adjustment

-"- 2 0,68 12

Switch painting

(See collection E 8-1)

Testing the circuit breaker with increased voltage of industrial frequency, measuring the insulation resistance of rods made of organic materials with a megohmmeter for 2500 V

Test and measurement electrician 3 1.04 13

Checking operation by turning it on and off repeatedly

Electrical fitter for repair of switchgear equipment 2 0.26 14

Measuring the force of pulling the knife out of the fixed contact is switched off

The same 2 0.37 15 3.1.1.4. Disconnectors RLND-6-10 kV, RV-6-10 kV, RVO, RVZ

The same 2 0.60 2

Insulation resistance measurement

Test and measurement electrician 3 0.30 3

Repair of contact blades, fixed contacts - removal flexible connections, spark-extinguishing horns, springs, disassembly, cleaning, checking of ice breaking devices, anti-corrosion coatings, cleaning of contact systems.

Electrician for the repair of switchgear equipment 3 0.70 4

Checking the conformity of the contacts with the norms. Lubrication of bearings, rubbing surfaces, assembly, installation, adjustment


Repair of insulators of rotary pads - control of multi-element insulators with a rod, their removal. Disassembly of the pedestal. Cleaning, lubrication, replacement of defective parts. Assembly. Checking the installation, operation of bearings

Electrician for the repair of switchgear equipment 3 0.30 5

The same 3 0.50 6

Repair of the drive, blocking of electromagnetic coils - opening, inspection of clutch units, auxiliary contacts, checking the integrity of bevel gears, replacing defective parts, cleaning, lubricating, checking the condition of the magnetic starter. Adjustment

-"- 4 0,90 7

Repair of the drive mechanism - disassembly of rods, levers, inspection, cleaning, lubrication, replacement of defective parts, assembly, adjustment

-"- 4 0,30 8

Adjustment of the disconnector - checking the limitation, longitudinal movement of the knife, smooth running, simultaneity of turning on the knives, measuring and adjusting the contact pressure, blocking operation

Electrician for repair and maintenance of electrical equipment 3 0.60 9

Electrician for the repair of switchgear equipment 3 0.30 10

(See collection E 8-1)

Cleaning, lubrication of clips, installation, fastening of tires

Electrician for the repair of switchgear equipment 2 1.00 11

Test and measurement electrician 3 0.30 12

Electrical fitter for repair of switchgear equipment 3 0.30 13 Additional work:

Electrician for the repair of switchgear equipment 3 0.30 14

Repair of the drive of grounding knives - inspection, cleaning, lubrication of gear clutches, bearings. Adjustment (Drive)

The same 3 0.80 15

Replacing one element of the insulator - inspection, unscrewing the bolts, removing the insulator, cleaning. Installing a new element (Insulator element)

- "- 3 0.30 16 3.1.1.5. Disconnectors RLN-35 kV, RDZ-35 kV, RD-35 kV

Time limits for 1 disconnector

External inspection of the disconnector - detection of defects, determination of the scope of work

Electrician for the repair of switchgear equipment 3 0.20 1

Detaching tires, fixing tire descents

The same 3 1.20 2

Insulation resistance measurement

Test and measurement electrician 3 0.70 3

Repair of contact blades, fixed contacts - removal of flexible connections, spark-extinguishing horns, springs, disassembly, cleaning, checking of ice breaking devices, anti-corrosion coatings, cleaning of contact systems. Checking the conformity of the contacts with the norms.

Lubrication of bearings, rubbing surfaces, assembly, installation, adjustment

Electrician for the repair of switchgear equipment 3 3.40 4

Repair of rotary column insulators - control of multi-element insulators with a rod, their removal. Disassembly of the pedestal. Cleaning, lubrication, replacement of defective parts. Assembly. Checking the installation, operation of bearings

Electrician for the repair of switchgear equipment 3 2.60 5

Checking the condition of insulators - inspection, cleaning, checking the integrity of the surface, fixing the plates

The same 3 1.30 6

Drive repair, blocking, opening, inspection of clutch units, contact block, checking the integrity of bevel gears, replacing defective parts, cleaning, lubricating, checking the condition of the magnetic starter. Adjustment

-"- 4 2,50 7

Repair of the drive mechanism - disassembly of rods, levers, inspection, cleaning, lubrication. Replacement of defective parts, assembly, adjustment

-"- 4 0,90 8

Adjustment of the disconnector - checking the limitation of the longitudinal movement of the knife, smooth running, simultaneity of turning on the knives, measuring and adjusting the contact pressure, blocking operation

-"- 3 2,30 9

Control tightening of bolted connections

-"- 3 1,20 10

Disconnector painting - restoration of reinforcing seams, cleaning with a brush, painting metal structures with a brush

(See collection E 8-1)

Disconnector busbar, cleaning, clamp lubrication, installation, busbar fixing

Electrician for repair and maintenance of electrical equipment 2 1.80 11

Contact contact resistance measurement

Test and measurement electrician 3 0.50 12

Testing the operation of the disconnector

Electrical fitter for repair of switchgear equipment 3 0.70 13 Additional work:

Repair of the grounding knife - disassembly, inspection, cleaning. Coloring. Lubrication of contacts, swivel joints. Checking geometric dimensions. Adjustment (knife phase)

Electrical fitter for repair of switchgear equipment 3 0.60 14

Grounding knife drive repair, inspection, cleaning, lubrication of gear clutch units, bearings. Adjustment (Drive)

Electrician for the repair of switchgear equipment 3 1.60 15

Replacing one element of the insulator - inspection, unscrewing the bolts, removing the insulator, cleaning. Installing a new element. (Insulator element)

The same 3 0.50 16 3.1.1.6. Separator with short circuit 35 kV

Time limits for 1 separator

Removing dust and dirt

Visual inspection

The same 3 0.08 2

Detaching tires from separator

-"- 3 0,65 3

Separator disassembly

-"- 3 2,33 4

Disassembly of contact sponges, knives, their cleaning and repair

-"- 3 1,46 5

Cleaning metal parts from rust

(See collection E 8-1)

Removing the insulators of the rotary speakers

Electrician for the repair of switchgear equipment 3 2.45 6

Disassembly of bearings, flushing with filling with new grease

The same 3 3.08 7

Drive repair and lubrication

-"- 3 2,00 8

Blockage repair

-"- 3 1,76 9

Inspection, tapping and wiping of insulators

-"- 3 2,32 10

Painting of metal parts

(See collection E 8-1)

Installing bearings and insulators in place

Electrical fitter for repair of switchgear equipment 3 2.47 11

Installing knives on insulators and adjusting the separator

The same 3 2.00 12

Disassembly, cleaning, lubrication of terminals

-"- 2 2,00 13

Attaching tires to the separator

Electrician for the repair of switchgear equipment 3 0.89 14

Measurement of contact resistance of direct current contacts

Test and measurement electrician 3 0.74 15

Measurement of pulling forces of moving contacts from fixed ones

Electrician for the repair of switchgear equipment 3 0.42 16

Swivel Lubrication

The same 2 0.98 17

Power frequency surge test

Test and measurement electrician 3 1.01 18

Verify operation by performing 10 to 15 closing and opening operations

Electrical fitter for the repair of switchgear equipment 3 0.94 19 3.1.1.7. Oil switches types VMG-133, VMG-10, VMP-10, VPM-10, VK-10, VVTP

Time limits for 1 switch

Cleaning from dust and dirt

External inspection and reconciliation with the list of defects

The same 2 0.30 2

Oil drain

-"- 2 0,94 3

Disconnecting the busbars from the circuit breaker and stripping the contacts

-"- 2 0,67 4

Removing and disassembling pots

-"- 3 0,52 5

Removing socket contacts

-"- 3 0,85 6

Inspection and repair of contacts or replacement of current-carrying rods with rods with metal-ceramic tips. Replacement of arc extinguishers

-"- 3 1,48 7

Installation of cameras and socket contacts, assembly of pots, switch

-"- 3 1,48 8

Inspection and adjustment of oil and spring dampers. Adjustment, lubrication and checking of drive contacts

-"- 3 1,93 9

Switch adjustment

-"- 3 4,84 10

-"- 3 1,00 11

Checking the simultaneous closing and opening of contacts

-"- 3 1,09 12

Repair of oil-indicating glasses

Electrician for the repair of switchgear equipment 3 0.56 13

Pouring oil into pots

The same 2 0.57 14

Measurement of DC contact resistance and circuit breaker speed characteristics

Test and measurement electrician 3 1.08 15

Painting frames, pots and drive

(See collection E 8-1)

Test and measurement electrician 2 0.57 16

Circuit breaker testing remotely and from the spot

The same 3 0.45 17

-"- 3 0,42 18

Testing for reliable switching on and off by repeated cycle

- "- 3 0.98 19 3.1.1.8. Oil switches VM-14, VM-16, VM-10

Time limits for 1 switch

Cleaning from dust and dirt

Electrician for the repair of switchgear equipment 2 0.17 1

External examination

The same 2 0.31 2

Disconnecting the busbars from the circuit breaker

-"- 2 0,67 3

Oil drain

-"- 2 0,81 4

lowering the pots

-"- 2 0,34 5

Armature repair

-"- 3 0,65 6

Pot cleaning

-"- 2 0,32 7

Repair of moving and fixed contacts

-"- 3 3,26 8

Replacement of arcing contacts

-"- 3 0,48 9

Repair of insulation of moving parts and intra-lateral insulation

-"- 4 1,24 10

Inspection and adjustment of the drive

-"- 3 2,26 11

Checking the operation of the free release mechanism

-"- 3 1,10 12

Contact adjustment

-"- 3 1,54 13

Pouring oil and lifting pots

Electrician for the repair of switchgear equipment 3 1.23 14

Connecting busbars to a circuit breaker

The same 2 0.45 15

Measurement of contact resistance and speed characteristics of the circuit breaker

Test and modification electrician 3 1.54 16

Coloring pots and drive

(See collection E 8-1)

Testing the circuit breaker and drive for external closing and opening

Electrical fitter for repair of switchgear equipment 3 0.90 17

Insulation test with increased power frequency voltage

Test and measurement electrician 3 0.36 18 3.1.1.9. VMP-10P circuit breakers with built-in drive

Time limits for 1 switch

Cleaning from dust and dirt

Electrician for the repair of switchgear equipment 2 0.10 1

External inspection of the oil circuit breaker, its mechanism and drive

The same 2 0.30 2

Draining oil and checking the operation of oil indicators

-"- 2 0,94 3

Removal of interpole barriers

-"- 2 0,50 4

Disconnecting the oil circuit breaker busbars

-"- 2 0,67 5

Breaker pole disassembly

-"- 3 1,89 6

Oil circuit breaker drive repair

-"- 3 2,32 7

Repair of oil gauges

-"- 3 0,56 8

Oil Buffer Inspection and Repair

-"- 3 1,24 9

Inspection and repair of the contact system

-"- 3 1,48 10

Measurement of the stroke of the moving part and the entry (pressing) of the rod into the socket contacts

-"- 3 1,10 11

Adjustment of simultaneous closing and opening of contacts

-"- 3 0,98 12

Flushing and cleaning of arc chambers and support cylinders

-"- 2 0,85 13

Circuit breaker frame repair

-"- 2 0,60 14

Switch pole assembly

-"- 3 1,76 15

Connecting busbars to a circuit breaker

-"- 2 0,85 16

Installation of interpole barriers

Electrician for the repair of switchgear equipment 2 0.70 17

Oil switch adjustment

The same 3 3.74 18

Repair and adjustment of the drive mechanism

-"- 3 4,75 19

Oil filling

-"- 2 0,57 20

Contact resistance measurement

Test and measurement electrician 3 1.09 21

Painting of the frame, tanks and circuit breaker drive

(See collection E 8-1)

Contact speed measurement

Electrician for the repair of switchgear equipment 3 1.08 22

Insulation test with increased power frequency voltage

Test and measurement electrician 3 0.21 23

Repeated switching on and off test

Electrical fitter for repair of switchgear equipment 3 0.30 24 3.1.1.10. Electric motors of three-phase current, power 0.6 - 30 kW, voltage 127 - 1000 V

Time limits for 1 electric motor

Dismantling the electric motor

Electrician for repair and maintenance of electrical equipment 3 0.93 1

Complete disassembly

The same 3 2.12 2

Washing of components and parts

-"- 3 0,17 3

Replacement of defective slot wedges and insulating sleeves

-"- 3 1,01 4

Full or partial replacement winding, impregnation and drying

Electrician for repair of windings and insulation of electrical equipment 2 10.00 5

Editing, turning necks or replacing the rotor shaft

Electrician for repair and maintenance of electrical equipment 3 1.24 6

Bulkhead rings

The same 2 1.00 7

Replacement of fans and flanges

-"- 3 0,46 8

Rotor balancing

-"- 3 1,38 9

Flushing and laying grease in rolling bearings

-"- 3 0,32 10

Replacing worn bearings

-"- 3 0,63 11

Checking and turning the motor covers

Electrician for repair and maintenance of electrical equipment 3 1.31 12

Ring turning and grinding

The same 3 1.64 13

Cleaning, assembly and painting of the electric motor

-"- 3 2,73 14

Insulation resistance measurement, resistance measurement direct current rheostats and ballast resistances; idle check; load test

-"- 3 3,15 15

Motor mounting

-"- 3 1,06 16

Checking the correct selection of fuse-links, automatic machines

-"- 3 0,45 17

Testing the electric motor with checking the absence of extraneous noise in operation; degree of heating of the housing and bearings

-"- 3 0,31 18

Putting into work

- "- 3 0.02 19 3.1.1.11. Grounding reactor (arc coil) 6 - 10 kV

Time limits for 1 reactor

Cleaning from dust and dirt

Electrical fitter for repair of switchgear equipment 2 0.32 1

External inspection and recording of defects

The same 4 0.50 2

Oil drain

-"- 4 0,42 3

Reactor dismantling

-"- 4 3,38 4

Lifting the active part

-"- 4 1,70 5

Inspection, cleaning and checking the condition of the active part

-"- 4 3,56 6

Measurement of insulation characteristics, insulation resistance, determination of the adsorption coefficient R60/R15,

Test and measurement electrician 4 0.50 7

Voltage test

The same 4 1.72 8

-"- 4 0,57 9

Pressing the yoke of the magnetic circuit and windings

Electrician for the repair of switchgear equipment 4 2.07 10

Branch repair

The same 4 1.53 11

Replacement of faulty inputs

Electrician for the repair of switchgear equipment 4 3.79 12

Tank check and repair

The same 4 4.01 13

Repair of expander and radiators

-"- 4 3,63 14

Repair of switching devices

-"- 4 3,75 15

Replacement of defective seals

-"- 4 1,78 16

Reactor Assembly

-"- 4 4,01 17

Filling transformer oil

-"- 4 0,82 18

Reactor cleaning and painting

(See collection E 8-1)

Reactor test

Test and measurement electrician 4 4.53 19

Checking the switching device

Electrician for the repair of switchgear equipment 4 1.44 20

Tank hydraulic pressure test

Test and measurement electrician 4 1.58 21 3.1.1.12. Electromagnetic relays (intermediate, signal) (full check)

Time limits for 1 relay

Relay removal

Electrician for the repair of relay protection and automation equipment 4 0.20 1

Inspection and verification of the mechanical part of the relay during its disassembly and assembly. Revision and adjustment of the magnetic circuit of the relay

The same 4 0.41 2

Inspection and adjustment of the adjusting plate together with the installed traverse of the moving contacts

-"- 4 0,27 3

Adjustment of relay contacts, checking of pressure and NO contacts and distance between moving and fixed contacts

-"- 4 0,12 4

-"- 4 0,19 5

Checking the voltage of the relay operation at a reduced voltage of the operating current

-"- 4 0,10 6

Checking and adjusting the operating time of a DC relay using a damper winding or a set of washers

Complete assembly and commissioning of the relay

The same 4 0.10 8

Re-examination and filling

-"- 4 0,18 9

Relay mounting

- "- 4 0.20 10 3.1.1.13. Induction relays RT-80, RT-90 (full check)

Time limits for 1 relay

Relay removal

Electrician for the repair of relay protection and automation equipment 3 0.20 1

External and internal inspection

The same 3 0.50 2

Disassembly and assembly, mechanical adjustment

-"- 4 0,41 3

Revision and adjustment of the magnetic circuit

-"- 4 0,40 4

Inspection and adjustment of the cut-off anchor

-"- 4 0,59 5

Checking the bearings of the frame and disk, replacing worn parts

-"- 3 0,19 6

Checking the disc for runout

-"- 3 0,17 7

Permanent Magnet Gap Adjustment

-"- 3 0,08 8

Checking the gear sector and adjusting the worm gear

-"- 3 0,17 9

Checking and adjusting the main and signal contacts

-"- 3 0,33 10

Checking settings and electrical characteristics relay when the casing is on and the fastening nuts are tightened (if the casing is metal)

-"- 3 0,41 11

Insulation resistance measurement

-"- 3 0,12 12

Checking the operating current of the inductive element

-"- 3 0,10 13

Checking the Relay Return Factor

-"- 3 0,05 14

Removing the characteristics of the time delay of the induction element

-"- 3 0,23 15

Checking and adjusting the electromagnetic element, cutoff actuation current

Electrician for the repair of relay protection and automation equipment 3 0.27 16

Checking the operation for the absence of vibration of the contacts from 1.05 / rated operating current to the highest short-circuit current

The same 3 0.30 17

Checking the return time of the induction element

-"- 3 0,18 18

Relay installation

-"- 3 0,29 19

re-inspection and electrical check with a cover on the working unit from a direct current source

-"- 3 0,28 20

Relay sealing

- "- 3 0.02 21 3.1.1.14. Differential relays of the type RNT, DZT and others

Time limits for 1 relay

External and internal inspection. Checking and adjusting the mechanical part of the relay

Electrician for the repair of relay protection and automation equipment 5 0.34 1

Checking the reliability of fastening the nodes and parts of the relay, tightening the screws and nuts that fasten the wiring of the internal wiring and the studs of the external installation on the relay outputs

The same 5 0.37 2

Checking the intermediate saturable transformer and the tightness of the screed of the steel sheets of the magnetic circuit

-"- 5 0,17 3

Adjustment on the mechanical part of the relay actuator

-"- 5 0,08 4

Adjustment of the longitudinal play of the anchor axis

-"- 5 0,13 5

Checking the gap between the armature and the pole of the magnetic circuit

-"- 5 0,07 6

Checking the condition of the coil spring and adjusting head

-"- 5 0,08 7

-"- 5 0,18 8

Adjustment of contacts and replacement of faulty ones

-"- 5 0,37 9

Insulation resistance measurement

-"- 5 0,04 10

Relay electrical characterization

-"- 5 0,07 11

Checking the executive body in the differential relay

Electrician for the repair of relay protection and automation equipment 5 0.23 12

Determination of secondary pick-up and return current, pick-up and return voltage

The same 5 0.17 13

Characterization of the relationship between the primary current and the secondary voltage on the BNT

-"- 5 0,15 14

Checking the health of a short-circuited winding

-"- 5 0,30 15

Setting and checking the primary parameters of the RNT relay

-"- 5 0,36 16

Checking the operation of the contacts of the executive body of the relay

-"- 5 0,23 17

Re-inspection and verification of the working installation

-"- 5 0,15 18

Relay sealing

- "- 5 0.02 19 3.1.1.15. Control stations of types PEL-8701, PEKh-8701, PEV, SU-1950, PDU (full check)

Time limits for 1 station

Inspection and testing of the mechanical part

Electrician for the repair of relay protection and automation equipment 4 0.15 1

Device disassembly

The same 4 0.49 2

Replacement of worn parts

-"- 4 0,76 3

Device Assembly

-"- 4 0,65 4

Checking the insulation of primary and secondary circuits

-"- 4 0,41 5

Electrical check and adjustment

Test and measurement electrician 3 0.43 6

Checking the status of the contacts of all elements of the circuit of primary and secondary circuits

Electrician for the repair of relay protection and automation equipment 4 0.12 7

Checking and adjusting the main contacts

The same 4 0.42 8

Checking the condition of arc chutes

-"- 4 0,39 9

Checking and adjusting intermediate relays, auxiliary contacts and automata in the secondary circuit diagram

-"- 4 0,47 10

Checking and adjusting the locking mechanism

Electrician for the repair of relay protection and automation equipment 4 0.41 11

Checking and adjusting the electric latch and mechanism

The same 4 0.12 12

Checking and lubricating bearings

-"- 4 0,10 13

Testing action and interaction

-"- 4 0,14 14

Measurement of insulation resistance with a megohmmeter with a voltage of 500 - 1000 V

Test and measurement electrician 3 0.25 15

Power frequency surge test

The same 3 0.37 16

Checking the operation of contacts at reduced and rated voltages of the operating current

Electrician for the repair of relay protection and automation equipment 4 0.39 17

Verification of fully assembled circuits for correct functioning under different values operating current

The same 4 0.43 18 3.1.1.16. Gas relays type PG-22 (full check)

Time limits for 1 relay

Relay removal

External and internal inspection and check of mechanical serviceability of all relay elements

The same 3 0.58 2

Leak test of shut-off floats of mercury pressure contacts

-"- 3 0,67 3

Checking the buoyancy of the floats and the health of the mercury contacts

-"- 3 0,45 4

Checking and adjusting the disconnecting elements and signal floats of the gas relay

-"- 3 0,42 5

Megger insulation test and 1000 V AC test

-"- 3 0,49 6

Checking the shut-off elements of the gas relay for failure to operate when the oil level drops

-"- 3 0,49 7

Relay mounting

- "- 3 0.52 8 3.1.1.17. Panel-type devices E-30, E-421, E-377, E-378, D-340, E-365

Time limits for 1 device

Dismantling the device

Electrician for the repair of relay protection and automation equipment 3 0.39 1

Opening and complete disassembly

The same 3 0.42 2

-"- 3 0,04 3

Replacement of damaged shunts and resistors up to 30% of the total

-"- 3 0,30 4

Replacement of worn parts

-"- 3 0,32 5

Restoration or replacement of the limit switch, instrument fittings

-"- 3 0,12 6

Fitting instrument readings to an accuracy class

-"- 3 0,09 7

Checking the device for compliance with the accuracy class

-"- 3 0,13 8

Insulation test

-"- 3 0,25 9

Branding and certification

-"- 3 0,06 10

Mounting the instrument on a panel

- "- 3 0.58 11 3.1.1.18. Self-recording devices of types D-33, N-340, N-351

Time limits for 1 device

Dismantling the device

Electrician for the repair of relay protection and automation equipment 4 0.42 1

Opening the device

The same 4 0.04 2

Cleaning from outside and inside

-"- 4 0,33 3

Complete disassembly of the device

-"- 4 0,42 4

Replacement of worn and defective parts up to 30% of the total

-"- 4 0,70 5

Contact stripping

-"- 4 0,10 6

Assembling the instrument, refilling ink and paper

-"- 4 0,65 7

Testing the device at various operating speeds

-"- 4 1,29 8

Mandatory verification and adjustment of indications

-"- 4 0,43 9

Insulation test

-"- 4 0,19 10

Branding and certification

Electrician for the repair of relay protection and automation equipment 4 0.11 11

Installing the instrument

The same 4 0.09 12 3.1.1.19. Complex instruments: oscilloscopes, laboratory instruments

Time limits for 1 device

Dismantling the device

Electrician for the repair of relay protection and automation equipment 4 0.28 1

Opening and cleaning the device

The same 4 0.59 2

Fixing mounts and mechanisms

-"- 4 0,29 3

Resoldering damaged field connections

-"- 4 0,26 4

Insulation test

-"- 4 0,19 5

Replacement or troubleshooting of switching equipment, control knobs, toggle switches, cassettes

-"- 4 0,26 6

Dismantling and checking of component units

-"- 4 0,14 7

Elimination of backlash

-"- 4 0,07 8

Packing new grease

-"- 4 0,04 9

Instrument assembly, partial painting

-"- 4 0,16 10

Full check of the device in all modes

-"- 4 0,55 11

Insulation test and device qualification

-"- 4 0,15 12

Mounting the device

- "- 4 0.30 13 3.1.1.20. Electricity meters of single-phase and three-phase current induction

Time limits for 1 counter

Dismantling the counter

Electrician operating electric meters 3 0.05 1

Opening the device

The same 3 0.05 2

Cleaning the instrument and parts

-"- 3 0,17 3

Inspection and testing of switching circuits

-"- 3 0,06 4

Replacement of glasses and other parts

-"- 3 0,37 5

Disassembly of the counting mechanism, cleaning, flushing, lubrication, disassembly of the thrust bearing

Electrician operating electric meters 3 0.46 6

Stone replacement, ball and cap seaming

The same 3 0.25 7

Rewinding or replacing the coils of the current and voltage circuit, altering the meter to new parameters

-"- 3 0,26 8

Meter Adjustment

-"- 3 0,28 9

Mandatory verification, branding and certification

-"- 3 0,15 10

Mounting the device

-"- 3 0,05 11

Testing the counter

- "- 3 0.08 12 3.1.1.21. Apparatus for testing types AKI-60, AII-70, AMI-60, AID-70, AIM-90, AIP-70 (in a workshop, laboratory)

Time limits for 1 device

Complete disassembly of the device

Electrician for repair and maintenance of electrical equipment 5 2.05 1

Replacement of damaged and defective parts

The same 5 0.78 2

Checking and replacing the winding, impregnation and drying

-"- 5 1,66 3

Checking the insulation of windings and circuits

-"- 5 0,34 4

Cleaning the housing and parts for painting

(See collection E 8-1)

Assembly of the apparatus

Electrician for repair and maintenance of electrical equipment 5 2.70 5

Apparatus painting

(See collection E 8-1)

Changing transformer oil

Electrician for repair and maintenance of electrical equipment 4 0.65 6

Testing and repair of measuring instruments

The same 5 1.36 7

Testing the device

-"- 5 0,28 8

Power transformer test

Test and measurement electrician 3 0.19 9

Name of operations and content of work Profession Category of work Norm of time N pos. Types of equipment compressors centrifuges electric forklifts electric cars 3.1.1.22. Compressors, centrifuges, electric forklifts, electric cars

Time limits for 1 mechanism

Draining oil, electrolyte and other fluids

Electrician for repair and maintenance of electrical equipment 3 0.45 0.35 0.59 0.55 1

Complete disassembly of the unit

The same 5 3.36 2.64 26.71 16.51 2

Replacement of worn and damaged parts (pistons, rings, bushings, bearings)

-"- 5 0,60 0,47 27,96 17,35 3

Cleaning and washing parts

-"- 5 3,02 2,37 2,76 2,12 4

Revision, lapping and adjustment of valves

-"- 5 - - 0,78 0,71 5

Cylinder boring

-"- 5 - 0,23 - - 6

Balancing rotating parts

-"- 5 - 0,27 - - 7

Cleaning of aggregates and preparation for painting

(See collection E 8-1)

8

Assembly of the unit

Electrician for repair and maintenance of electrical equipment 5 4.67 3.67 46.44 21.67 9

Unit painting

(See collection E 8-1)

10

Testing the operation of the units

Electrician for repair and maintenance of electrical equipment 5 1.59 0.20 2.70 1.05 11

Name of operations and content of work Profession Category of work Norm of time N pos. 3.1.1.23. Rechargeable batteries with disassembly of all elements of type C-5

Time limits for 1 battery

Chemical separation treatment, electrolyte drain

Accumulator 3 6.00 1

Dismantling batteries and racks

The same 3 8.00 2

Insert sorting

-"- 3 0,83 3

Weighing negative plates into vessels with distilled water

-"- 3 0,58 4

Repair of plates with cleaning and straightening

Electrician for repair and maintenance of electrical equipment 2 9.42 5

Assembly and installation of racks by level

Accumulator 3 4.34 6

Shelving with acid resistant paint

The same 2 0.49 7

Battery mounting

-"- 3 8,28 8

Separation Assembly

-"- 3 0,69 9

Installing separation into elements

-"- 3 0,44 10

Electrolyte composition

-"- 3 1,42 11

First charge (formation)

-"- 3 37,52 12

Control removal of the container

-"- 3 0,81 13

Charge after control discharge

-"- 3 11,63 14

Element numbering

-"- 3 1,39 15

Insulation resistance measurement

-"- 3 0,15 16

Checking the capacity of a molded battery

-"- 3 0,61 17

Checking the density of the electrolyte depending on the temperature

-"- 3 0,25 18

Cell voltage measurement

-"- 3 0,19 19

Commissioning batteries

-"- 3 0,50 20

The name of the operation and the content of the work Profession Category of work Norm of time N pos. Transformer power, kVA Up to 50 63 100 160 180 250 320 400 560 630 1,000

3.1.1.24. Replacement of power transformers

Time limits for 1 transformer

Disconnecting the transformer busbars from the inputs of the high and low voltage sides

Electrician for the repair of switchgear equipment 3 0.38 0.50 0.58 0.60 0.65 0.68 0.70 0.70 0.75 0.88 0.88 1

Dismantling the old transformer

The same 3 2.34 2.34 2.89 3.10 3.10 3.17 3.90 3.90 4.00 4.00 4.15 2

Loading an old transformer with a truck crane

Truck crane operator 4 0.44 0.49 0.53 0.53 0.58 0.63 0.63 0.65 0.68 0.68 0.74 3

Unloading a new transformer

Electrician for the repair of switchgear equipment 2 0.44 0.49 0.49 0.53 0.55 0.58 0.62 0.65 0.67 0.69 0.75 4

Installation of a new transformer

The same 3 3.02 3.32 3.70 3.76 4.05 4.10 4.10 4.18 4.30 4.50 4.90 5

Connecting the bars of the new transformer

-"- 3 0,34 0,39 0,44 0,44 0,49 0,53 0,54 0,58 0,58 0,59 0,59 6

Name of operations and content of work Profession Category of work Norm of time N pos. 3.1.1.25. Switch replacement

Time limits for 1 knife switch

Dismantling the old switch

Electrician for the repair of switchgear equipment 4 2.03 1

Marking and drilling a hole on the panel (if necessary)

The same 2 0.18 2

Checking the health of the knife switch and fixing it

-"- 4 0,69 3

Knife shaft articulation with drive, knife lubrication

-"- 4 0,36 4

Testing the operation of the knife switch by repeatedly turning it on and off

- "- 4 0.22 5 3.1.1.26. Manual drive type PRA, PRBA

Time limits for 1 drive

Cleaning the drive from dust and dirt

Electrician for the repair of switchgear equipment 2 0.45 1

External inspection, preliminary check of the drive operation

The same 3 0.78 2

Repair and adjustment of the main pawl fixation lever and the free release mechanism

-"- 4 4,73 3

Repair and adjustment of signal block contacts

-"- 4 1,83 4

Lubrication and painting of the drive

-"- 2 0,52 5

Test and measurement electrician 4 1.22 6

Undervoltage trip solenoid test

Electrician for the repair of switchgear equipment 4 0.51 7

Checking the drive after repair and adjustment with repeated switching on and off

The same 4 1.26 8 3.1.1.27. Electromagnetic direct current drive PS and PE series

Time limits for 1 drive

External inspection and verification of the operation of the drive

Electrician for the repair of switchgear equipment 3 0.50 1

Drive mechanism repair

The same 3 8.50 2

Repair of the magnetic system

-"- 3 0,30 3

Buffer flange repair

-"- 3 0,20 4

Repair and adjustment of signal blocking contacts

-"- 4 0,50 5

Drive adjustment

-"- 4 1,00 6

Lubrication and painting

-"- 2 0,30 7

High voltage test of secondary switching of signaling and control circuits

Test and measurement electrician 4 0.80 8

Checking the operation of the circuit breaker drive at increased voltage

Electrician for the repair of switchgear equipment 4 0.50 9

The same 4 0.60 10 3.1.1.28. Spring drive PP-67 (PP-61)

Time limits for 1 drive

External inspection and preliminary check of the drive operation

Electrician for repair of switchgear equipment 3 0.18 1

Power drive repair

The same 3 2.12 2

Repair of the winder automatic motor assembly

-"- 3 2,28 3

Repair of the switching mechanism

-"- 3 0,98 4

Repair of the mechanism of inclusion and free disengagement

-"- 3 2,86 5

Repair of the manual control and blocking mechanism

-"- 3 2,21 6

Repair of signal-command auxiliary contacts, automatic reclosure device and lever system

-"- 3 2,15 7

Drive adjustment

Electrician for the repair of switchgear equipment 4 1.00 8

Lubrication and painting of the drive

The same 2 0.33 9

Secondary switching test of control and signal circuits

Test and measurement electrician 4 0.90 10

Checking the operation of the circuit breaker drive at low voltage

Electrical fitter for repair of switchgear equipment 4 0.45 11

Checking the drive manually and remotely after repair and adjustment with repeated switching on and off

The same 4 0.52 12

3.1.2. Relay protection and automation

Name of operations and content of work Profession Category of work Norm of time N pos. 3.1.2.1. AVR, APV and undervoltage protection devices

Time limits for 1 set

The same 5 0.37 2

-"- 5 0,40 3

Identification and replacement of worn parts

-"- 5 1,10 4

-"- 5 1,13 5

Checking elements of circuit breaker drives and other switching devices with additional adjustment of auxiliary contacts and replacement of parts

-"- 5 1,23 6

Checking automata in the secondary circuits of voltage transformers and, if necessary, replacing contacts

-"- 5 0,37 7

Checking the electrical characteristics of relay equipment, auxiliary devices

-"- 5 0,74 8

Electrician for the repair of relay protection and automation equipment 5 0.50 9

(See collection E 8-1)

Electrician for the repair of relay protection and automation equipment 5 0.47 10

; circuit assembly

The same 5 0.50 11

Checking the interaction of all elements of the device circuit for switches and other switching devices

-"- 5 0,13 12

-"- 5 0.11 13

Time limits for 1 set

A. Maximum current protection, made on the relay type RT-40 (ET)

Electrician for the repair of relay protection and automation equipment

External inspection of the device of all its elements

The same 5 0.10 1

Removal of relay equipment from panels

-"- 5 0,08 2

Internal inspection and verification of the mechanical part of the current relays RT (ET)

-"- 5 0,15 3

Checking and adjusting the longitudinal clearance in the axes

-"- 5 0,11 4

Checking and adjusting the gap between the armature and the poles of the magnetic circuit, correct installation and adjustment of the stop screws

-"- 5 0,20 5

Check of reliability of fastening of an adjusting head and a spiral spring

-"- 5 0,17 6

Inspection and adjustment of the contact system

-"- 5 0,16 7

Checking the serviceability of bearings and axle ends

-"- 5 0,21 8

Insulation resistance measurement

-"- 5 0,11 9

Checking and adjusting the electrical characteristics of the relay

Electrician for the repair of relay protection and automation equipment 5 0.13 10

Measurement of pick-up and reset current on operating installations and determination of the reset factor

The same 5 0.15 11

Checking and Eliminating Contact Vibration

-"- 5 0,33 12

Checking intermediate and signal relays

-"- 5 0,12 13

Checking current transformers:

Measurement of insulation resistance, taking characteristics of the magnetization of current transformers, checking the polarity of the windings and the current transformation ratio; current transformer test for 100% error, power frequency overvoltage test

-"- 5 0,30 14

Checking the drive elements of oil switches and additional adjustment of auxiliary contacts and replacement of parts

-"- 5 0,18 15

Checking control and signaling circuits, secondary current protection circuits

-"- 5 0,16 16

Secondary switching overvoltage test

-"- 5 0,14 17

Comprehensive testing of control and signaling protection schemes

-"- 4 0,18 18

-"- 4 0,15 19

B. Overcurrent protection with a time delay of direct action type PTB on alternating current

-"-

External and internal inspection of equipment and fittings

-"- 4 0,12 1

Checking the mechanical part of the direct acting relay

-"- 4 0,18 2

Checking the correct assembly and adjustment of the mechanical part of the drive

-"- 4 0,26 3

Checking the correct installation, the absence of distortions and the reliability of fastening the relay to the drive

-"- 4 0,24 4

Checking the absence of distortions, bending of the drummer, the size of the gap between the head of the drummer and the shutdown melt; revision of the main mechanism

Electrician for the repair of relay protection and automation equipment 4 0.25 5

Checking the condition of the outputs of the relay coil and current switch, the operating current on the working installation

The same 3 0.30 6

Removing the dependence of the operating time on the current in the relay

-"- 3 0,22 7

Preparing the device for work

-"- 3 0,20 8

Inspection and testing of secondary switching and current transformers

- "- 3 0.33 9 3.1.2.3. Maximum directional protection

Time limits for 1 set

External inspection of the device and all its elements

Electrician for the repair of relay protection and automation equipment 5 1.10 1

Internal inspection and verification of the mechanical part of the apparatus

The same 5 2.11 2

Insulation test:


Insulation resistance measurement

-"- 5 0,80 3

Checking the dielectric strength of the insulation

-"- 5 0,55 4

Checking and adjusting the electrical characteristics of the relay:


Power consumption of voltage and current windings

-"- 5 4,40 5

Elimination of self-propelled relay

-"- 5 2,23 6

Determining the coverage area and actuation power of the relay

-"- 5 2,10 7

Checking equipment, control and signaling circuits

-"- 5 2,60 8

Checking elements of circuit breaker drives and other switching devices

-"- 5 2,40 9

Checking current and voltage transformers and their circuits

-"- 5 1,90 10

Checking the device with operating current (load current)

Electrician for the repair of relay protection and automation equipment 5 1.70 11

Checking the interaction of all elements of the device circuit and the action of the device on switches and other switching devices

The same 5 4.30 12

Preparing the device for use

-"- 5 1,34 13

Removing vector diagrams

-"- 5 1.20 14 3.1.2.4. Gas protection kit

Time limits for 1 set

External inspection of the device and all its elements

Electrician for the repair of relay protection and automation equipment 4 0.56 1

Checking the slopes of the oil lines and the transformer cover and the correct installation of the gas relay

The same 3 0.52 2

Checking the correctness of cutting the control cable and protecting it from oil ingress and mechanical damage

-"- 3 1,12 3

Checking the gas protection by forcing air into the relay

-"- 3 2,00 4

Checking the adjustment of the oil surge protection when starting and stopping the pumps forced circulation oil and cooling fans

-"- 4 2,38 5

Checking the operation of the disconnecting float when the relay is smoothly filled with air

-"- 3 1,00 6

Checking the operation of the protection circuit for the reliability of the contact connections of the operation and return voltage of the intermediate and signal relays (circuit operation at an operating current voltage of 0.8)

-"- 4 0,50 7

Preparing the device for switching on

-"- 4 1.32 8 3.1.2.5. Power transformer differential protection

Time limits for 1 set

Electrician for the repair of relay protection and automation equipment 5 0.50 1

Dismantling of relay equipment

The same 5 0.48 2

-"- 5 2,30 3

Identification and replacement of worn and broken parts

-"- 5 2,10 4

Checking the equipment of control circuits in the alarm system with flushing of contacts and replacement of parts

-"- 5 2,95 5

-"- 5 2,24 6

Checking elements of circuit breaker drives and other switching devices with replacement of parts

-"- 5 3,50 7

Checking and adjusting the electrical characteristics of the relay

-"- 5 1,84 8

Removal of characteristics of magnetization

-"- 5 1,00 9

Determination of safety factors

-"- 5 0,80 10

Checking and selecting taps of a short-circuited winding

-"- 5 2,22 11

Checking and adjusting the parameters of the relay type RNT

-"- 5 2,60 12

Checking the reliability of the contact system

-"- 5 0,64 13

Adjustment of preset settings on relay equipment Relay relay

-"- 5 2,40 14

Relay panel color update

(See collection E 8-1)

Installation of relay equipment on the panel

Electrician for the repair of relay protection and automation equipment 5 0.12 15

Checking the correct inclusion of current circuits

The same 5 0.70 16

Checking the device with the primary load current and removing vector diagrams

-"- 5 1,82 17

Insulation test: insulation resistance measurement; dielectric strength test

Electrician for the repair of relay protection and automation equipment 5 1.82 18

Checking the interaction of all elements of the device circuit and the action on switches and other switching devices

The same 5 2.80 19 3.1.2.6. Alarm and warning panel

Time limits for 1 panel

External inspection of the device and all elements

Electrician for the repair of relay protection and automation equipment 5 0.20 1

Dismantling of relay and signal equipment

The same 5 0.50 2

Internal inspection and testing of mechanical equipment according to the full program

-"- 5 2,10 3

Identification and replacement of worn and broken parts and burnt out lamps in lighting signal equipment

-"- 5 1,00 4

Testing of equipment, control and signaling circuits with flushing of contacts and replacement of parts

-"- 5 1,50 5

Bench check and adjustment of electrical characteristics

-"- 5 7,20 6

Checking and adjusting the sensitivity of the relay type RIS-32

-"- 5 0,90 7

Checking additional resistances

-"- 5 0,30 8

Checking the polarity of the outputs of the relay type RIS

-"- 5 0,30 9

Checking and adjusting the polarized relay

-"- 5 0,90 10

Relay panel color update

(See collection E 8-1)

Installation of relay and signal equipment on the panel

Electrician for the repair of relay protection and automation equipment 5 0.30 11

The same 5 0.50 12

Testing the signal pickup with the button

-"- 5 0,20 13

Testing the circuit at reduced (0.8 V nom) and increased (1.10 V nom) voltage of the control current network

Electrician for the repair of relay protection and automation equipment 5 0.33 14

Checking the interaction of all elements of the device circuit and the action of the device on the siren, bell and light alarm

The same 5 0.50 15

Preparing the device for use

- "- 5 0.30 16 3.1.2.7. Earth fault signaling device in networks 6 - 35 kV

Time limits for 1 device

External inspection of the device

Electrician for the repair of relay protection and automation equipment 5 0.31 1

Removing the relay equipment from the panels and carrying it to the laboratory

The same 5 0.50 2

Internal inspection and verification of the mechanical part of the apparatus

-"- 5 2,50 3

Identification and replacement of worn and broken parts

-"- 5 1,32 4

Checking equipment, control and signaling circuits with flushing of contacts and replacement of worn parts

-"- 5 2,60 5

Checking current transformers and their circuits

-"- 5 2,10 6

Checking and replacing fuses and checking circuit breakers in the secondary circuits of voltage transformers

-"- 5 0,44 7

Checking the electrical characteristics of the relay equipment of auxiliary devices

-"- 5 1,50 8

Adjustment of preset settings on relay equipment

-"- 5 1,40 9

Relay panel color update

(See collection E 8-1)

Installation of relay equipment on the panel

Electrician for the repair of relay protection and automation equipment 5 0.41 10

Insulation test: insulation resistance measurement; dielectric strength test

The same 5 1.83 11

Checking the interaction of all elements of the device circuit and the action of the device on signaling equipment

Electrician for the repair of relay protection and automation equipment 5 0.73 12 3.1.2.8. Automatic switch A-3100, VA

Time limits for 1 switch

Visual inspection

Electrician for the repair of relay protection and automation equipment 4 0.10 1

Removing the switch from the panel

The same 4 0.22 2

Complete disassembly of the switch

-"- 4 0,70 3

Check the wear of the circuit breaker parts and, if necessary, replace them

-"- 4 0,47 4

Checking the main and spark-extinguishing contacts with cleaning and replacement of unusable ones

-"- 4 0,95 5

Checking springs, flexible connections and spark chambers

-"- 4 0,13 6

Assembly of the switch and adjustment of contacts for solution, failure and pressing

-"- 4 1,66 7

Checking each thermal and electromagnetic element for operation with a pole load with a test current

-"- 4 0,45 8

Insulation test: Insulation resistance measurement: Insulation dielectric strength test

-"- 4 0,15 9

Mounting the switch on the panel

- "- 4 0.28 10 3.1.2.9. Rectifier stabilizing devices

Time limits for 1 device

External inspection of the device and its elements

Electrician for the repair of relay protection and automation equipment 4 0.30 1

Dismantling the device

The same 4 0.84 2

Partial disassembly of the device

-"- 4 1,00 3

Checking the insulation of transformer windings

-"- 4 0,54 4

DC winding resistance measurement

Electrician for the repair of relay protection and automation equipment 4 0.12 5

Pin Polarity Determination

The same 4 0.11 6

Turn ratio measurement

-"- 4 0,13 7

Thermal testing

-"- 4 8,37 8

Removal of magnetization curves of a stabilizing transformer

-"- 4 3,12 9

Checking the insulation between washers and steel rod

-"- 4 1,58 10

Forming of rectifiers by voltage and current

-"- 4 4,16 11

Identification and replacement of bad washers

-"- 4 1,34 12

Barrier layer breakdown test of rectifiers

-"- 4 4,70 13

Checking the stress distribution across the washers

-"- 4 3,50 14

Characterization of forward and reverse current

-"- 4 5,40 15

Assembly of the rectifier stabilizing device

-"- 4 1,29 16

Mounting the device on a panel

-"- 4 1,86 17

Insulation test: checking the dielectric strength of the insulation

- "- 4 1.10 18 3.1.2.10. Voltage regulators for power transformers of the OLTC type

Time limits for 1 device

External inspection of the device and all its elements

Electrician for repair and maintenance of electrical equipment 3 1.00 1

Draining the oil from the contactor housing

The same 2 0.17 2

Removing the contactor housing cover

-"- 2 0,05 3

Dismantling the contactor and switching mechanism

-"- 4 0,76 4

Inspection of the condition of contactor parts, camshafts, Maltese gears and flexible current-carrying links and replacement of worn parts

Electrician for repair and maintenance of electrical equipment 4 5.40 5

Assembling the contactor and switching mechanism

The same 4 0.69 6

Adjustment of the pressure of movable contactors to fixed ones and adjustment of the switching mechanism

-"- 4 4,60 7

Fitting the cover and filling the contactor housing with fresh oil

-"- 2 0,18 8

Revision of the electric motor of the switching mechanism

-"- 4 14,12 9

Checking the sequence of operation of the switch contactors (removing a pie chart)

Electrician for the repair of relay protection and automation equipment 4 1.82 10

Bench testing and adjustment of voltage, time, intermediate relays and speed control relays

The same 4 8.20 11

Checking and adjusting the electrical characteristics of the unit automatic control voltage regulator type BAURPN-1

-"- 4 12,40 12

Checking and adjusting the drive mechanism for the clarity of the start, the correct direction of the rotating device and the braking system

Electrician for repair and maintenance of electrical equipment 3 6.50 13

Remote pointer adjustment

The same 3 2.96 14

Checking the selsino sensors and the receiver

Electrician for the repair of relay protection and automation equipment 4 2.20 15

Insulation test: insulation resistance measurement, insulation dielectric strength test

The same 4 1.00 16

Checking the interaction of all elements of the device diagram

- "- 4 1.17 17 3.1.2.11. Telemetering and telesignaling installations for urban electrical networks (TI-TS)

Time limits for 1 set

Checking the correctness of the passage of the TS signals and the call of the TI (for three to four objects)

Electrician for the repair of relay protection and automation equipment 3 0.24 1

Measurement of current (voltage) in linear devices on the transmitting and receiving sides

The same 3 0.64 2

Testing the operation of the automatic power supply of the device on the DP

-"- 3 2,29 3

Measurement on the DP side of the main time parameters of the TS network (impulse, pause, selective pause)

-"- 3 4,71 4

Identification of contact devices with increased sparking in semi-sets

-"- 3 0,57 5

Recording Device Meter Readings

-"- 3 0,18 6

Processing of measurement results and analysis of entries in operational logs

-"- 3 0,18 7

Production of a complete shutdown of TI-TS devices at DP and KP

-"- 3 0,01 8

Cleaning equipment from dust using brushes and a vacuum cleaner

-"- 3 0,57 9

Checking the serviceability of the mechanical part of the equipment and installation with updating the marking, checking the fusible links and the presence of protective earths

-"- 3 5,75 10

Contact cleaning

-"- 3 1,71 11

Adjustment of relays and seekers

-"- 4 4,65 12

Checking the functionality of keys, buttons and rotary symbols

-"- 3 4,53 13

Checking the insulation of the installation for all circuits (the circuits of the TM device are checked with a 500 V megger, a-circuits connected with the operating current of the object, with a 1,000 V megger)

-"- 5 1,83 14

Separate check of DP and KP under voltage of serviceability and operation of those units and elements of the device, the normal operation of which is ensured when the communication channel is turned off:

Electrician for the repair of relay protection and automation equipment 5 10.85 15

power supplies for equipment and automatic power backup

The same 5 1.84 a

seekers

- "- 5 0.72 b

thermal relay

- "- 5 0.71 in

all common control and calling systems

- "- 5 0.67 g

ready lamps, horn, bypass counters

- "- 5 0.14 d

mismatch latching relay and flashing light relay

- "- 5 0.62 e

time relay

- "- 5 0.68 f

blocks of contactless devices

- "- 5 4.64 s

circuits of all individual signal lamps

- "- 5 0.83 and

Joint verification of the entire complex of DP and CP equipment, including communication channels

-"- 5 8,13 16

Acceptance of channels after their full check

-"- 5 1,12 17

Enabling half sets to work together via a communication channel

-"- 3 0,13 18

Testing device operation

-"- 5 4,00 19

Measurement of the main time parameters of devices

-"- 3 0,35 20

Timing adjustment

-"- 3 0,62 21

Checking the operation of pulsating slow relays

-"- 3 0,78 22

Checking the operation of the device in artificially created emergency modes with a repetition of 2 - 3 times

-"- 5 0,27 23

Checking the protective nodes of devices with imitation of all types of damage to which this or that protection should respond

-"- 5 0,18 24

Electrician for the repair of relay protection and automation equipment 5 0.52 25

Final verification with testing of individual input and output circuits of the device by transmitting the entire used volume of signaling and calling measurements in conditions as close as possible to operation

The same 5 2.25 26

Putting the device into operation with the restoration of all disconnected circuits

-"- 5 1,76 27

3.1.3. Overhead power lines

Name of operations and content of work Profession Category of work Norm of time N pos. Pole type without crossbar with crossbar to power transmission line strut with voltage, kV up to 1 1 - 20 up to 1 1 - 20 up to 1 1 - 20 3.1.3.1. Installation of wooden attachments to the supports (manually)

Time limits for 1 prefix

Prefix blank

Electrician for the repair of overhead power lines 2 0.20 0.22 0.20 0.21 0.22 0.22 1

Crossbar blank

2 - - 0,20 0,21 0,21 0,21 2

Strut blank

2 - - - - 0,20 0,20 3

Digging a hole

(See collection E 2-1)

Electrician for the repair of overhead power lines 3 - - 0.30 0.30 - - 4

The same 3 0.30 0.30 0.29 0.29 0.32 0.29 5

Installing the attachment with attachment to the support

-"- 3 0,38 0,42 0,42 0,42 0,38 0,43 6

Antiseptic junctions

-"- 2 0,23 0,22 0,24 0,22 0,23 0,21 7

-"- 3 0,35 0,38 0,35 0,38 0,35 0,36 8

Pit filling and compaction

(See collection E 2-1)

Cutting out the end of the support

Electrician for the repair of overhead power lines 3 0.26 0.27 0.26 0.27 0.26 0.27 9

Removal of stretch marks or hooks

The same 3 0.17 0.27 0.17 0.26 0.17 0.25 10

Coloring bandages

(See collection E 8-1)

Electrician for the repair of overhead power lines 2 0.07 0.07 0.07 0.07 0.07 0.07 11 3.1.3.2. Installation of reinforced concrete prefixes to supports

Time limits for 1 prefix

Strengthening the support with stretch marks or hooks

Electrician for the repair of overhead power lines 3 0.33 0.34 0.31 0.34 0.34 0.31 1

The same 3 - - 0.34 0.42 - - 2

Digging a hole

(See collection E 2-1)

Electrician for the repair of overhead power lines 2 0.17 0.21 0.17 0.20 0.20 0.21 3

Set-top box installation

The same 3 0.29 0.25 0.29 0.30 0.28 0.30 4

Fitting to a support

-"- 3 0,18 0,32 0,16 0,25 0,19 0,27 5

Antiseptic junctions

-"- 3 0,18 0,14 0,19 0,15 0,21 0,13 6

Wire rod blank

-"- 2 0,18 0,10 0,14 0,15 0,16 0,11 7

-"- 2 0,30 0,33 0,33 0,38 0,33 0,32 8

Pit filling and compaction

(See collection E 2-1)

Cutting out the end of the support

Electrician for the repair of overhead power lines 3 0.36 0.36 0.34 0.36 0.30 0.36 9

Removal of stretch marks or hooks

The same 3 0.25 0.26 0.21 0.26 0.23 0.25 10

Coloring bandages

(See collection E 8-1)

Numbering of supports, attaching posters

Electrician for the repair of overhead power lines 2 0.07 0.07 0.07 0.07 0.07 0.07 11 3.1.3.3. Replacing wooden consoles with wooden ones (manually)

Time limits for 1 prefix

Prefix blank

Electrician for the repair of overhead power lines 2 0.32 0.32 0.33 0.29 0.32 0.32 1

Crossbar blank

The same 2 - - 0.21 0.27 - - 2

Attaching the crossbar to the attachment using a bandage

-"- 3 - - 0,31 0,35 - - 3

Strengthening the support with stretch marks or hooks

-"- 3 0,42 0,38 0,40 0,40 0,42 0,38 4

-"- 3 0,29 0,30 0,35 0,35 0,29 0,30 5

Installation of a new prefix with fitting to the rack with antiseptization of interface points

-"- 3 0,77 0,74 0,72 0,72 0,71 0,71 6

Adjustment, twisting and installation of bandages made of strip iron, wire rod

-"- 3 0,34 0,50 0,36 0,52 0,35 0,48 7

Pit filling and compaction

(See collection E 2-1)

Removal of stretch marks or gaffs and old prefix

Electrician for the repair of overhead power lines 3 0.29 0.31 0.27 0.26 0.24 0.27 8

Coloring bandages

(See collection E 8-1)

Numbering of supports, attaching posters

Electrician for the repair of overhead power lines 2 0.07 0.07 0.07 0.07 0.07 0.07 9 3.1.3.4. Replacing wooden prefixes with reinforced concrete ones

Time limits for 1 prefix

Strengthening the support with stretch marks or hooks

Electrician for the repair of overhead power lines 3 0.42 0.41 0.41 0.47 0.42 0.42 1

Attaching the stand base with an attachment

The same 3 0.40 0.41 0.41 0.41 0.40 0.41 2

Attaching the crossbar to the attachment

-"- 3 - - 0,37 0,37 0,30 0,30 3

Covering the underground part of the console with bituminous mastic

-"- 3 0,20 0,23 0,21 0,21 0,21 0,21 4

Removing old bandages

-"- 3 0,15 0,16 0,16 0,18 0,16 0,16 5

Removing the old prefix

-"- 3 0,45 0,66 0,42 0,61 0,43 0,62 6

Installing a new console

-"- 3 0,50 0,57 0,61 0,61 0,46 0,70 7

Fitting to a support with antiseptic junctions

-"- 3 0,49 0,45 0,57 0,45 0,50 0,39 8

Adjustment, twisting and installation of strip iron bandages

-"- 3 0,54 0,55 0,56 0,56 0,53 0,56