3.04 01 87 insulating and finishing coatings

INSULATING AND FINISHING COATINGS

Introduction date 1988-07-01

1. GENERAL PROVISIONS

DEVELOPED BY TsNIIOMTP Gosstroy of the USSR (candidates of technical sciences N.N. Zavrazhin - leader of the topic, V.A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the Gosstroy of the USSR (candidate of technical sciences I.P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences) D.K. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences Prof. E.D. Belousov, Candidate of Technical Sciences G.S. Agadzhanov), Design Bureau of Glavtonnelmetrostroy of the Ministry of Transport and Construction of the USSR (Ph.D. V.V. Krylova , V.G. Golubov), Department of Soyuzmetrospetsstroy of the Ministry of Transport Construction of the USSR (A.P. Levina, P.F. Litvina), NIIZhB Gosstroy of the USSR (Doctor of Technical Sciences, Prof. F.M. Ivanova).

INTRODUCED by TsNIIOMTP Gosstroy of the USSR.

PREPARED FOR APPROVAL by the Office of Standards and technical standards in the construction of the Gosstroy of the USSR (D. I. Prokofiev).

APPROVED by the Decree of the State building committee USSR dated December 4, 1987 No. 280.

With the entry into force of SNiP 3.04.01-87 "Insulating and finishing coatings» become invalid SNiP III-20-74*, SNiP III-21-73*, SNiP III-B.14-72; GOST 22753-77, GOST 22844-77, GOST 23305-78.

When using normative document should take into account the approved changes in building codes and state standards published in the Bulletin construction equipment”, “Collection of changes to building codes and rules” of the USSR State Construction Committee and an information index “ State standards USSR" Gosstandart of the USSR.

1. GENERAL PROVISIONS

1.1. Real building codes and the rules apply to the production and acceptance of work on the installation of insulating, finishing, protective coatings and floors of buildings and structures, with the exception of work due to special operating conditions of buildings and structures.

1.2. insulating, finishing, protective coatings and floor structures must be carried out in accordance with the project (finishing coatings in the absence of project requirements - according to the standard). Replacement of materials, products and compositions provided for by the project is allowed only upon agreement with the design organization and the customer.

1.3. Work on the production of thermal insulation works can only begin after the execution of an act (permit) signed by the customer, representatives of the installation organization and the organization performing thermal insulation work.

2. INSULATION COATINGS AND ROOFING

GENERAL REQUIREMENTS

2.1. Insulating and roofing it is allowed to perform from 60 to minus 30 °С environment(performance of work using hot mastics - at an ambient temperature of at least minus 20 ° C, using compositions on water based without antifreeze additives not lower than 5 °С).
2.2. In the bases for roofing and insulation in accordance with the project, it is necessary to perform the following work:

Seal the seams between prefabricated slabs;
arrange temperature-shrinkage seams;
mount embedded elements;
plaster sections of vertical surfaces of stone structures to the height of the junction of a rolled or emulsion-mastic roofing carpet and insulation.

2.3. Insulating compositions and materials must be applied in continuous and uniform layers or in one layer without gaps and sagging. Each layer must be arranged on the hardened surface of the previous one with leveling of the applied compositions, with the exception of paints. In the preparation and preparation of insulating compositions, the requirements of Table. one.

PREPARATION OF THE BASES AND SUBJECTS

INSULATION ELEMENTS
2.4. Substrates must be dedusted before applying primers and sealers, including bonding adhesives and mastics.
2.6. The priming of the surface before applying the adhesive and insulating compositions must be made continuous without gaps and gaps. Priming of screeds made of cement-sand mortars, should be carried out no later than 4 hours after their laying, using primers on slowly evaporating solvents (with the exception of screeds with a surface slope of more than 5%, when priming should be done after they have hardened). When preparing the surface of the base, it is necessary to comply with the requirements of Table. 2.

The primer should have a strong adhesion to the base, no traces of binder should remain on the tampon applied to it.

INSULATION AND ROOFING
FROM ROLL MATERIALS

2.13. Roofing and waterproofing carpets made of rolled materials with a mastic layer pre-melted at the factory must be glued onto a pre-primed base by melting or liquefying (plasticizing) the mastic layer of the material without using adhesive mastics. The adhesive strength must be at least 0.5 MPa.

Liquefaction of the mastic layer should be carried out at an air temperature of at least 5 ° C with the simultaneous laying of the rolled carpet or before it is laid (depending on the ambient temperature).

The melting of the mastic layer should be carried out simultaneously with the layout of the panels (the temperature of the melted mastic is 140-160 ° C). Each laid layer of the roof must be rolled with a roller to the next one.

2.16. cloths roll materials when installing roofs, the following should be glued:

In the direction from low to high sections with the arrangement of panels along the length perpendicular to the flow of water with roof slopes up to 15%;

In the direction of flow - with roof slopes of more than 15%.

Cross-sticking of insulation panels and roofing is not allowed. The type of sticker of the rolled carpet (solid, strip or spot) must correspond to the project.

2.17. When sticking the panels of insulation and roofing, they must overlap by 100 mm (70 mm across the width of the panels of the lower layers of the roofing of roofs with a slope of more than 1.5%).

2.19. Temperature-shrinkage joints in screeds and joints between coating slabs must be covered with strips of rolled material up to 150 mm wide and glued on one side of the joint (joint).

2.20. At junctions with protruding roof surfaces (parapets, pipelines, etc.) roofing carpet must be raised to the top of the screed edge, glued on the mastic with putty on the upper horizontal seams. Bonding of additional roof layers should be carried out after the installation of the top layer of the roof, immediately after applying the adhesive mastic in a continuous layer.

2.21. When sticking panels of roofing carpet along the roof slope top part the panels of the lower layer should overlap the opposite slope by at least 1000 mm. The mastic should be applied directly under the roll being rolled out in three strips 80-100 mm wide. Subsequent layers must be glued on a continuous layer of mastic.

When sticking panels across the roof slope, the upper part of the panel of each layer laid on the ridge should overlap the opposite roof slope by 250 mm and be glued on a continuous layer of mastic.

THERMAL INSULATION DEVICE FROM PLATES AND
BULK MATERIALS

2.36. Insulators when installing thermal insulation from slabs should be laid on the base tightly to each other and have the same thickness in each layer.

When installing thermal insulation in several layers, the seams of the plates must be arranged apart.

2.38. When installing thermal insulation from plate and bulk materials, the requirements of Table. 5 and 6.

DEVICE OF ROOFING FROM PIECE MATERIALS

2.39. On device wooden bases(lattices) under roofs made of piece materials, the following requirements must be observed:

The joints of the crate should be placed apart;

The distances between the elements of the crate must correspond to the design ones;

In places of coverage eaves overhangs, grooves and valleys, as well as under roofs from small-piece base elements, it is necessary to arrange from boards (solid).

2.40. piece roofing materials should be laid on the crate in rows from the eaves to the ridge according to preliminary markings. Each overlying row should overlap the underlying one.

REQUIREMENTS FOR FINISHED INSULATION (ROOF)

COATINGS AND STRUCTURAL ELEMENTS 2.46. The requirements for finished insulating (roofing) coatings and structures are given in Table.

Technical requirements

Limit deviations

Complete drainage of water over the entire surface of the roofs should be carried out through external and internal drains without stagnant water

The strength of adhesion to the base and between each other of the roofing and waterproofing carpet made of rolled materials on a continuous mastic adhesive layer of emulsion compositions with the base is not less than 0.5 MPa

Measuring, 5 measurements per 120-150 sq.m of the surface of the coating (when tapping, the nature of the sound should not change); when the glued materials break, no delamination along the mastic should be observed (the gap should occur inside the rolled panel), acceptance certificate

The heat resistance and compositions of mastics for gluing roll and plate materials, as well as the strength and composition of the solutions of the adhesive layer, must comply with the design ones. Deviations from the project - 5%.

Technical inspection, act of acceptance

The location of panels and metal paintings (depending on the slope of the coating), their connection and protection in the ordinary coating, at the junctions and interfaces in different planes must comply with the project

Bubbles, swellings, air pockets, tears, dents, punctures, spongy structure, dripping and sagging on the surface of roofing and insulation are not allowed.

Increased moisture content of substrates, intermediate elements, coating and the entire structure compared to the standard

Not more than 0.5%

Measuring, 5 measurements on an area of ​​50-70 sq.m of the surface of the coating or in separate areas of a smaller area in the places identified visual inspection, act of acceptance

When accepting finished insulation and roofing, it is necessary to check:

compliance of the number of reinforcing (additional) layers in mates (junctions) with the project;

for waterproofing:

the quality of filling joints and openings in structures made of prefabricated elements with sealing materials;

the quality of the coinage;

the correctness of the waterproofing of bolt holes, as well as holes for injection of mortar for finishing structures;

absence of leaks and discontinuity of seam lines in metal waterproofing;

for roofs made of rolled materials, emulsion, mastic compositions:

funnel bowls internal drains should not protrude above the surface of the base;

the corners of the junction structures (screeds and concrete) must be smoothed and even, without sharp corners;

for roofs made of piece materials and roofing parts made of metal sheets:

the absence of visible gaps in the coating when examining the roof from the attic;

absence of spalls and cracks (in asbestos-cement and sealed flat and wavy sheets);

strong connection links downpipes between themselves;

the presence of smearing of double lying folds in the joints of metal paintings on a coating with a slope of less than 30 °;

for thermal insulation:

the continuity of the layers, the quality of the lining of the places where the fastenings of pipelines, equipment, structural details, etc. pass through. through thermal insulation;

absence of mechanical damage, sagging layers and looseness of adhesion to the base

Deviations from the project are not allowed

Technical inspection, acceptance certificate

3. FINISHING WORKS AND PROTECTION OF BUILDING STRUCTURES AND TECHNOLOGICAL EQUIPMENT FROM CORROSION
(ANTI-CORROSION WORKS)

GENERAL PROVISIONS

3.1. Finishing work, with the exception of facade finishing, must be carried out at a positive ambient temperature and surfaces to be finished at least 10 ° C and air humidity not more than 60%. Such a temperature in the room must be maintained around the clock, at least 2 days before the start and 12 days after the end of work, and for wallpaper work - until the facility is put into operation.

3.3. Finishing work must be carried out in accordance with the project for the production of works (PPR) for the construction of buildings and structures. Before the beginning finishing works the following work must be done:

The finished premises were protected from atmospheric precipitation;
waterproofing, heat and sound insulation and floor screeds were installed;

Seams between blocks and panels are sealed;
sealed and isolated junctions of window, door and balcony blocks;
glazed light openings;
embedded products were installed, heating and water supply and heating systems were tested.

Plastering and cladding (according to the project) of surfaces at the installation sites of embedded products of sanitary systems must be completed before their installation.

SURFACE PREPARATION

3.7. Performing finishing and protective coatings on bases with rust, efflorescence, grease and bituminous stains is not allowed. Wallpapering is also not allowed on surfaces that have not been cleaned of whitewash.

3.12. When painting and wallpapering, the quality of the prepared bases must meet the following requirements:

Surfaces when painted with oil, adhesive, water-based compositions and pasted with wallpaper should be smoothed, without roughness;

Surface cracks are opened, primed, filled with putty to a depth of at least 2 mm and sanded;

Sinks and irregularities primed, puttied and smoothed;

Delaminations, streaks of mortar, traces of processing by trowels have been removed;

Seams between sheets dry gypsum plaster and the areas adjacent to them are primed, puttied, sanded flush with the surface or treated with rustication (in accordance with the project), and when pasting with wallpaper, they are additionally pasted over with strips of paper, gauze, etc.;

When pasting the surfaces with wallpaper, the painting of the ceilings was completed and other painting work was done.

Bases prepared for painting, pasting with synthetic wallpaper on a paper and fabric basis, as well as with an adhesive applied at the factory, must meet the requirements of Table. 9. The surfaces of all fasteners located under cardboard, paper or directly under the wallpaper must be pre-coated with an anti-corrosion compound.

PRODUCTION OF PLASTER AND MODELING WORKS
3.15. When plastering brick walls at an ambient temperature of 23 ° C and above, the surface must be moistened before applying the mortar.

3.16. improved and high quality plaster should be carried out on beacons, the thickness of which should be equal to the thickness of the plaster coating without the covering layer.

3.21. In production plastering works table requirements must be met.

Technical requirements

Control (method, scope,

type of registration)

Permissible thickness of single-layer plaster, mm:

Measuring, at least 5 measurements per 70-100 sq.m of the coating surface or in one room of a smaller area

when using all types of solutions, except for gypsum, - up to 20, from gypsum solutions- up to 15

in places identified by continuous visual inspection, work log

Permissible thickness of each layer when installing multi-layer plasters without polymer additives, mm:

Measuring, at least 5 measurements per 70-100 sq.m of the coating surface or in one room of a smaller area in places identified by a continuous

spraying on stone, brick, concrete surfaces- up to 5

visual inspection, work log

spray on wooden surfaces(including the thickness of the wound) - up to 9

soil from cement mortars- up to 5

soil from lime, lime-gypsum mortars - up to 7

covering layer of plaster coating - up to 2

covering layer decorative finishes- up to 7

PRODUCTION OF PAINTING WORKS

3.22. Production painting works on facades should be carried out with the protection of the applied compositions (up to their complete drying) from direct exposure to sunlight.

3.23. In the production of painting work, continuous surface puttying should be performed only with high-quality painting, and improved - for metal and wood.

3.27. When painting wooden floors, each layer, with the exception of the last, must be sanded to remove the gloss.

WALLPAPER PRODUCTION

3.37. Gluing panels paper wallpaper should be performed after they are swollen and impregnated with adhesive.

3.38. Wallpaper surface density up to 100 g/sq.m must be glued overlapping, 100-120 g/sq.m and more - back to back.

3.39. When joining overlapped panels, pasting surfaces with wallpaper must be carried out in the direction from the light openings without arranging joints of vertical rows of panels at the intersections of the planes.

3.41. When sticking pile wallpapers, the panels should be smoothed in one direction when gluing.

PRODUCTION OF FACING WORKS
3.51. Surface cladding must be carried out in accordance with the PPR in accordance with the project. The connection of the cladding field with the base must be carried out:

When using facing slabs and blocks with a size of more than 400 sq. cm and a thickness of more than 10 mm - fastening to the base and filling the space between the cladding and the wall surface (sinuses) with mortar or without filling the sinuses with mortar when the cladding is taken away from the wall;

When using plates and blocks with a size of 400 sq. cm or less, with a thickness of not more than 10 mm, as well as when facing with plates of any size horizontal and inclined (no more than 45%) surfaces - on mortar or mastic (in accordance with the project) without additional fastening to the base;

When facing with embedded slabs and facing bricks simultaneously with laying walls - on masonry mortar.

3.52. Cladding of walls, columns, pilasters of the interiors of the premises should be carried out before the installation of floor covering.

3.53. The cladding elements along the adhesive layer of mortar and mastic must be installed horizontally `ou.e. , (from bottom to top from the corner of the cladding field.

3.54. The mastic and adhesive layer mortar should be applied in an even, sag-free layer before the tiles are installed. Small-sized tiles on mastics or mortars with retarders should be installed after applying the latter over the entire area to be lined in one plane when mastics and mortars with retarders thicken.

3.55. Finishing the site and the entire surface of the interior and facade facing products different color, textures, textures and sizes should be made with the selection of the entire pattern of the cladding field in accordance with the project.

3.56. Lining elements when using natural and artificial stone polished and polished textures must be dry matched, adjusting the edges of adjacent slabs selected according to the pattern with fastening according to the project. The seams of the plates must be filled with mastic after filling the sinuses with mortar and its hardening.

3.57. Plates with a polished, dotted, bumpy and grooved structure, as well as with a "rock" type relief, must be installed on the mortar; vertical joints should be filled with mortar to a depth of 15 - 20 mm or with sealant after the adhesive layer mortar has hardened.

3.58. The seams of the cladding must be even, of the same width. When cladding walls erected by freezing, filling the joints of the cladding from embedded ceramic plates must be done after thawing and hardening. masonry mortar with loads on the walls of at least 80% of the design.

3.59. Filling the sinuses with a solution must be done after installing a permanent or temporary fastening of the cladding field. The mortar should be poured in horizontal layers, leaving a space of 5 cm to the top of the cladding after pouring the last layer of the mortar.

The solution, poured into the sinuses, during technological breaks exceeding 18 hours, should be protected from moisture loss. Before continuing work, the unfilled part of the sinus must be cleaned of dust with compressed air.

3.60. After cladding, the surfaces of slabs and products must be cleaned of mortar and mastic influx immediately, while: the surfaces of glazed, polished and polished slabs and products are washed hot water, and polished, point, bumpy, grooved and "rock" type are treated with a 10% solution of hydrochloric acid and steam with a sandblaster.

3.61. Surfaces cut from soft rock slabs (limestone, tuff, etc.), as well as edges of slabs protruding by more than 1.5 mm with polished, ground, grooved and dotted surfaces, must be respectively ground, polished or hewn to obtain a clear contour of the edges of the plates.

3.62. In the production of facing works, the requirements of Table.

Technical requirements

Limit deviations, mm

Control (method, scope, type of registration)

Adhesive layer thickness, mm:

Measuring, at least 5 measurements per 70-100 sq.m of surface

from solution - 7

or on a separate

from mastic - 1

a plot of a smaller area in places identified by a continuous visual inspection, a work log

Lined surface

deviations from the vertical (mm per 1 m of length), mm:

The same, at least 5 measurements per 50-70 sq.m of surface

mirrored, polished - no more than 2

No more than 4 per floor

polished, dotted, bumpy, furrowed - no more than 3

ceramic, glass-ceramic and other products in cladding

No more than 8 per floor

outdoor - 2

No more than 5 per floor

internal - 1.5

No more than 4 per floor

deviations of the location of the seams from the vertical and horizontal (mm per 1 m of length) in the cladding, mm:

mirrored, polished - up to 1.5

polished, dotted, bumpy, furrowed - up to 3

“rock” textures - up to 3

ceramic, glass-ceramic, other products in cladding:

outdoor - up to 2

internal - up to 1.5

Permissible mismatches of the profile at the joints of architectural details and seams, mm:

mirror, polished - up to 0.5

polished, point, bumpy, furrowed - up to 1

textures of the “rock” type - up to 2

ceramic, glass-ceramic and other products in cladding:

outdoor - up to 4

internal - up to 3

Measuring, at least 5 measurements per 70-100 sq.m of surface or on separate area smaller area in places identified by continuous visual inspection, work log

Roughnesses of the plane (when controlled by a two-meter rail), mm:

mirrored, polished - up to 2

polished, point, bumpy, furrowed - up to 4

ceramic, glass-ceramic and other products in cladding:

outdoor - up to 3

internal - up to 2

Deviations in the width of the cladding seam:

mirrored, polished

granite and artificial stone

marbles

polished, pitted, bumpy, furrowed

rock textures


INSTALLATION OF SUSPENDED CEILINGS, PANELS AND PLATES

WITH FACE FINISHING IN THE INTERIORS OF BUILDINGS

3.63. Device suspended ceilings it is necessary to carry out after installation and fastening of all elements of the frame (in accordance with the project), checking the horizontalness of its plane and compliance with the marks.

3.64. Installation of slabs, wall panels and suspended ceiling elements should be carried out after marking the surface and start from the corner of the surface to be lined. Horizontal joints of sheets (panels) not provided for by the project are not allowed.

4. DEVICE OF FLOORS
GENERAL REQUIREMENTS

4.3. The device of floors is allowed at the air temperature in the room, measured in the cold season near the door and window openings at a height of 0.5 m from the floor level, and the laid floor elements and materials to be laid - not lower, ° С:

15 - at the device of coverings from polymeric materials; this temperature should be maintained within 24 hours after completion of work;

5 - when installing floor elements using bituminous mastics and their mixtures, which include cement; this temperature must be maintained until the material acquires a strength of at least 50% of the design;

STRAP DEVICE

4.15. Monolithic screeds made of concrete, asphalt concrete, cement-sand mortar and prefabricated screeds made of fibreboard must be made in compliance with the rules for the installation of coatings of the same name.

4.16. Gypsum self-leveling and porous cement screeds must be laid immediately to the calculated thickness specified in the project.

4.17. When installing screeds, the requirements of Table.

Technical requirements

Control (method, scope, type of registration)

Screeds laid on soundproof pads or backfills, at the junction with walls and partitions and other structures, must be laid with a gap of 20 - 25 mm wide for the entire thickness of the screed and filled with a similar soundproofing material:

monolithic screeds must be isolated from walls and partitions with strips of waterproofing materials

Technical, all junctions, work log

The end surfaces of the laid section of monolithic screeds after removing the beacon or restrictive rails before laying the mixture in the adjacent section of the screed must be primed (see clause 4.11) or moistened (see clause 4.12), and the working seam is smoothed so that it is invisible

Visual, at least four times per shift, work log

Smoothing the surface of monolithic screeds should be performed under coatings on mastics and adhesive layers and under continuous (seamless) polymer coatings before setting mixtures

The same, the entire surface of the screeds, the work log

Gluing the joints of the prefabricated fiberboard screed should be carried out along the entire length of the joints with strips of thick paper or adhesive tape 40 - 60 mm wide

Technical, all joints, work log

Laying additional elements between prefabricated screeds on cement and gypsum binders should be carried out with a gap of 10-15 mm wide, filled with a mixture similar to the screed material. If the width of the gaps between the prefabricated screed slabs and walls or partitions is less than 0.4 m, the mixture must be laid on a continuous soundproof layer

Technical, all clearances, work log

WATERPROOFING DEVICE

4.21. Pasting waterproofing using bitumen, tar and mastics based on them should be carried out in accordance with Sec. 2, a polymer waterproofing- according to SNiP 3.04.03-85.

4.22. Waterproofing from crushed stone impregnated with bitumen should be carried out in accordance with SNiP 3.06.03-85.

4.23. Surface bituminous waterproofing before laying on it coatings, layers or screeds, which include cement or liquid glass, should be covered with hot bituminous mastic with dry coarse-grained sand embedded in it in compliance with the parameters of Table.

Technical requirements

Limit deviations

Control (method, scope, type of registration)

Temperature bituminous mastic during application - 160 °С

Measuring, each batch prepared for applying mastic, work log

Sand temperature - 50 °C

The same, each portion of sand before its application, the journal of work

The thickness of the layer of bituminous mastic - 1.0 mm

The same, at least three measurements for every 50-70 sq.m of waterproofing surface, certificate of inspection hidden works

WOOD COATING DEVICE
AND PRODUCTS BASED ON ITS

4.34. All plank floor boards must be fastened to each joist with nails 2-2.5 times the thickness of the floor, and parquet boards - with nails 50-60 mm long. Nails should be hammered obliquely into the face of plank boards /. *`kb (o) and into the base of the lower cheek of the groove on the edges of parquet boards and parquet boards with caps embedded. Driving nails into the front surface of parquet boards and parquet boards is prohibited.

4.35. The joints of the ends of boards of plank coverings, the joints of the ends and side edges with the ends of adjacent parquet boards, as well as the joints of the edges parallel to the logs of adjacent parquet boards should be located on the logs.

4.37. Superhard fibreboards, type-setting and block parquet should be glued to the base with quick-hardening mastics on waterproof binders, applied in a cold or heated state. Adhesive mastic on the base for superhard fiberboards should be applied in strips 100-200 mm wide along the perimeter of the boards and in the middle zone with an interval of 300-400 mm. When laying out and cutting fiberboards, joining the four corners of the boards at one point is not allowed. 4.38. When installing coatings made of wood and products based on them, it is necessary to comply with the requirements of Table.

Technical requirements

Limit deviations, mm

Control (method, scope, type of registration)

All logs, boards (except front side), wooden spacers laid on posts under logs, as well as wood under the base of fibreboard, must be antiseptic

Visual, all materials, certificate of examination of hidden works

The moisture content of materials should not exceed for:

Measuring, at least three measurements

lag and gaskets

for every 50-70 sq.m

cover and base boards

floor surfaces,

when laying typesetting and block parquet, parquet boards and parquet boards

work log

fibreboard coating

The length of the joined logs must be at least 2 m, the thickness of the log, resting on the floor slabs or the soundproof layer with the entire lower surface, is 40 mm, and the width is 80-100 mm. The thickness of the logs laid on separate supports (columns in floors on the ground, floor beams, etc.) should be 40 - 50 mm, width - 100-120 mm

Wooden laying under the logs in the floors on the ground:

width - 100-150 mm, length - 200-250 mm, thickness - at least 25 mm

The distance between the axes of the logs laid on floor slabs and for floor beams (when laying the coating directly on the beams) should be 0.4-0.5 m. When laying the log on separate supports (columns in floors on the ground, floor beams, etc. ) this distance should be:

with a lag thickness of 40 mm 0.8 - 0.9 m

with a lag thickness of 50 mm 1.0 - 1.1 m

For high operational loads on the floor (more than 500 kg / sq.m), the distance between the supports for the log, between the logs and their thickness should be taken according to the project

Measuring, at least three measurements for every 50-70 sq.m of floor surface, work log

The length of the boards joined by the ends of the coating must be at least 2 m, and parquet boards - at least 1.2 m

The thickness of the adhesive layer for type-setting and block parquet and super-hard fiberboards should be no more than 1 mm

Measuring, at least five measurements for every 50-70 sq.m of floor surface or in one room of a smaller area, work log

Glue area:

parquet plank - not less than 80%

fibreboard - not less than 40%

Technical, with trial lifting of products in at least three places per 500 sq.m of floor surface, work log

DEVICE OF COATINGS FROM POLYMER
MATERIALS

4.39. Linoleum, carpets, rolled materials made of synthetic fibers and PVC tiles before gluing must be aged until the waves disappear and completely adhere to the base, they must be glued to the underlying layer over the entire area, except as specified in the project.

4.40. Cutting of joined panels of rolled materials must be done no earlier than 3 days after the main gluing of the panels. The edges of the joined linoleum panels must be welded or glued after cutting.

4.41. In areas of heavy pedestrian traffic, the installation of transverse (perpendicular to the direction of movement) seams in linoleum coatings, carpets and rolled materials from synthetic fibers not allowed.

REQUIREMENTS FOR THE FINISHED FLOOR COVERING

4.43. The main requirements for finished floor coverings are given in Table.

Technical requirements

Control (method, scope, type of registration)

Deviations of the coating surface from the plane when checking with a two-meter control rail should not exceed, mm, for:

earthen, gravel, slag, crushed stone, adobe coatings and pavement coatings - 10

asphalt concrete coatings, on a layer of sand, end, from cast iron plates and brick - 6

cement-concrete, mosaic-concrete, cement-sand, polyvinyl acetate-cement concrete, metal-cement, xylolite coatings and coatings made of acid-resistant and heat-resistant concrete - 4

coatings on a layer of mastics, end, cast iron and steel plates, bricks of all types - 4

coatings from cement-concrete, cement-sand, mosaic-concrete, asphalt-concrete, ceramic, stone, slag-ceramic slabs - 4

polyvinyl acetate, plank, parquet flooring and coverings from linoleum, rolls based on synthetic fibers, from polyvinyl chloride and superhard fiberboards - 2

Ledges between adjacent products of coatings made of piece materials should not exceed for coatings, mm:

from paving stones - 3

brick, end, concrete, asphalt concrete, cast iron and steel slabs - 2

from ceramic, stone, cement-sand, mosaic-concrete, slag-ceramic slabs - 1

plank, parquet, linoleum, polyvinyl chloride and superhard fiberboards, polyvinyl chloride plastic - not allowed

Ledges between coatings and floor edging elements - 2 mm

Measuring, at least nine measurements for every 50-70 sq.m of the coating surface or in one room of a smaller area, acceptance certificate

Deviations from the specified coating slope - 0.2% of the corresponding room size, but not more than 50 mm

Deviations in coating thickness - no more than 10% of the design

The same, at least five measurements, acceptance certificate

When testing the adhesion of monolithic coatings and coatings made of rigid tile materials with the underlying elements of the floor by tapping, there should be no change in the nature of the sound

Technical, by tapping the entire floor surface in the center of the squares along a conditional grid with a cell size of at least 50 x 50 cm, acceptance certificate

Gaps should not exceed, mm:

between plank boards - 1

between parquet boards and parquet boards - 0.5

between adjacent plans of piece parquet - 0.3

Measuring, at least five measurements for every 50-70 sq.m of the coating surface or in one room of a smaller area, acceptance certificate

Gaps and gaps between skirting boards and floor coverings or walls (partitions), between adjacent edges of linoleum panels, carpets, rolled materials and tiles are not allowed

Visual, the entire surface of the floor and junctions, the act of acceptance

The surface of the coating should not have potholes, cracks, waves, swellings, raised edges. The color of the coating must match the design

The same, the entire surface of the floor, the act of acceptance

BUILDING REGULATIONS

INSULATING AND FINISHING COATINGS

SNiP 3.04.01-87

STATE CONSTRUCTION

USSR COMMITTEE

Moscow 1988

DEVELOPED BY TsNIIOMTP Gosstroy of the USSR (candidates of technical sciences N. N. Zavrazhin - leader of the topic, V. A. Anzigitov) with the participation of the Central Research Institute of Industrial Buildings of the Gosstroy of the USSR (candidate of technical sciences I. P. Kim), TsNIIEP housing of the State Committee for Architecture (candidate of technical sciences) D. B. Baulin), NIIMosstroy of the Moscow City Executive Committee (Doctor of Technical Sciences Prof. E. D. Belousov, Candidate of Technical Sciences G. S. Agadzhanov), Design Bureau of Glavtonnelmetrostroy of the Ministry of Transport and Construction of the USSR (Ph.D. V. V. Krylova , V. G. Golubova), Department of Soyuzmetrospetsstroy of the Ministry of Transport of the USSR (A. P. Levina, P. F. Litvina), NIIZhB Gosstroy of the USSR (Doctor of Technical Sciences, Prof. F. M. Ivanova).

INTRODUCED by TsNIIOMTP Gosstroy of the USSR.

PREPARED FOR APPROVAL by the Office of Standardization and Technical Standards in Construction of the USSR State Construction Committee (D. I. Prokofiev).

With the entry into force of SNiP 3.04.01-87 "Insulating and finishing coatings", SNiP III-20-74*, SNiP III-21-73*, SNiP III-B.14-72 become invalid; GOST 22753-77, GOST 22844-77, GOST 23305-78.

When using a regulatory document, one should take into account the approved changes in building codes and rules and state standards published in the Bulletin of Construction Equipment magazine, the Collection of Changes to Building Norms and Rules of the Gosstroy of the USSR and the information index "State Standards of the USSR" of the State Standard of the USSR.

1. GENERAL PROVISIONS

l.l. These building codes and regulations apply to the production and acceptance of work on the installation of insulating, finishing, protective coatings and floors of buildings and structures, with the exception of work due to the special operating conditions of buildings and structures.

1.2. Insulating, finishing, protective coatings and floor structures must be carried out in accordance with the project (finishing coatings in the absence of project requirements - according to the standard). Replacement of the materials, products and compositions provided for by the project is allowed only upon agreement with the design organization and the customer.

1.3. Work on the production of thermal insulation works can begin only after the execution of an act (permit) signed by the customer, representatives installation organization and organization that performs thermal insulation works.

1.4. The device of each element of insulation (roof), floor, protective and finishing coatings should be carried out after checking the correctness of the implementation of the corresponding underlying element with the preparation of an inspection certificate for hidden work.

1.5. With appropriate justification, in agreement with the customer and the design organization, it is allowed to assign methods of work performance and organizational and technological solutions, as well as establish methods, volumes and types of registration of quality control of work that differ from those provided for by these rules.

2. INSULATION COATINGS AND ROOFING

GENERAL REQUIREMENTS

2.1. It is allowed to carry out insulation and roofing work from 60 to minus 30 ° C of the environment (works using hot mastics - at an ambient temperature of at least minus 20 ° C, using water-based compositions without antifreeze additives not lower than 5 ° C).

2.2. In the bases for roofing and insulation in accordance with the project, it is necessary to perform the following work:

seal the seams between prefabricated slabs;

arrange temperature-shrinkage seams;

mount embedded elements;

plaster sections of vertical surfaces of stone structures to the height of the junction of a rolled or emulsion-mastic roofing carpet and insulation.

2.3. Insulating compositions and materials must be applied in continuous and uniform layers or in one layer without gaps and sagging. Each layer must be arranged on the hardened surface of the previous one with leveling of the applied compositions, with the exception of paints. In the preparation and preparation of insulating compositions, the requirements of Table. one.

Table 1

Technical requirements

Limit deviations

Bitumen and tar (pitch) must be used cleaned of impurities and dehydrated. Heating should not exceed, ° С:

bitumen - 180

tar (pitch) - 140

Measuring, periodic but not less than 4 times per shift, work log

Fillers (aggregates) must be sifted through a sieve with mesh sizes, mm:

for sand - 1.5

for pulverized - 2

for fibrous - 4

Permissible humidity of fillers (aggregates):

for sand

for compositions with sealing additives

for other formulations

Measuring, periodic, at least 4 times per shift, work log

Temperature of emulsions and their components, ° С:

bitumen - 110

emulsifier solution - 90

latex (when introduced into the emulsion) - 70

Minus 10 ° C

The same, at least 5-6 times per shift, work log

Uniform distribution of bitumen in bitumen-perlite and bitumen-ceramsite - 90%

Compaction coefficient of bitumen perlite and bitumen expanded clay under pressure 0.67-0.7 MPa - not less than 1.6

Temperature when applying mastics, ° С:

hot bituminous - 160

hot tar - 130

cold (in winter time) - 65

Installation of insulations, dispersed-reinforced with glass fiber (fiber glass):

fiber dimensions - 20 mm

weight ratio of aluminous cement to Portland cement - 90: 10

Measuring, periodic at least 16 measurements per shift (every 0.5 hours of work), work log

heavy concrete for the installation of roofs without an insulating coating (roofing) must contain:

plasticizing and air-entraining additives, aggregates from graded sand and coarsely graded crushed stone;

portland cement - hydrophobic, containing no more than 6% calcium aluminate;

crushed stone of igneous rocks or gravel with a temporary resistance of at least 100 MPa in a water-saturated state; granulometric composition of crushed stone, mm:

sand of the protective layer of fineness modulus - 2.1 - 3.15

Measuring, periodic, at least 4 times per shift, work log

Gravel and other frost-resistant mineral materials must be sorted and washed

PREPARATION OF THE BASES AND SUBJECTS

INSULATION ELEMENTS

2.4. Substrates must be dedusted before applying primers and sealers, including bonding adhesives and mastics.

2.5. Leveling screeds (from cement-sand, gypsum, gypsum-sand mortars and asphalt mixes) should be arranged with grips 2-3 m wide along guides with leveling and compaction of the surface.

2.6. The priming of the surface before applying the adhesive and insulating compositions must be made continuous without gaps and gaps. Priming of screeds made from cement-sand mortars should be carried out no later than 4 hours after their laying, using primers on slowly evaporating solvents (with the exception of screeds with a surface slope of more than 5%, when priming should be performed after they have hardened). When preparing the surface of the base, it is necessary to comply with the requirements of Table. 2.

The primer should have a strong adhesion to the base, no traces of binder should remain on the tampon applied to it.

table 2

Technical requirements

Limit deviations

Control (method, scope, type of registration)

Permissible deviations in the surface of the base for rolled and non-rolled emulsion and mastic insulation and roofing:

along the slope and on the horizontal surface

across the slope and on the vertical surface

from piece materials:

along and across the slope

Measuring, technical inspection, at least 5 measurements for every 70-100 m 2 of surface or on a smaller area in places determined by visual inspection

Deviations of the plane of the element from the specified slope (over the entire area)

Structural element thickness (from design)

The number of irregularities (smooth outlines with a length of not more than 150 mm) on a surface area of ​​4 m 2

No more than 2

Primer thickness, mm:

for roofs made of built-up materials - 0.7

when priming a hardened screed - 0.3

when priming screeds within 4 hours after applying the solution - 0.6

2.7. Humidity of the base before applying the primer should not exceed the values ​​indicated in Table. 3. On wet substrates, only water-based primers or insulating compounds may be applied, if the moisture acting on the surface of the substrate does not violate the integrity of the coating film.

2.8. metal surfaces pipelines, equipment and fasteners to be insulated must be cleaned of rust, and those subject to anti-corrosion protection must be processed in accordance with the project.

2.9. Insulation of the installed equipment and pipelines should be carried out after their permanent fixing in the design position. Thermal insulation of equipment and pipelines in places that are difficult to reach for insulation must be carried out completely before installation, including the installation of cover shells.

Insulation of pipelines located in impassable channels and trays must be performed before they are installed in channels.

2.10. Equipment and pipelines filled with substances must be freed from them before the commencement of insulation work.

2.11. Rolled insulating materials when performing work in negative temperatures, it is necessary to warm up to a temperature of at least 15 ° C within 20 hours, rewind and deliver to the place of installation in an insulated container.

THERMAL INSULATION DEVICE FROM PLATES AND LOOSE MATERIALS

Before sending an electronic application to the Ministry of Construction of Russia, please read the rules of operation of this interactive service set out below.

1. Electronic applications in the field of competence of the Ministry of Construction of Russia, filled in in accordance with the attached form, are accepted for consideration.

2. An electronic appeal may contain a statement, complaint, proposal or request.

3. Electronic appeals sent through the official Internet portal of the Ministry of Construction of Russia are submitted for consideration to the department for working with citizens' appeals. The Ministry provides an objective, comprehensive and timely consideration of applications. Consideration of electronic appeals is free of charge.

4. In accordance with the Federal Law of May 2, 2006 N 59-FZ "On the Procedure for Considering Citizens' Appeals Russian Federation"electronic appeals are registered within three days and are sent depending on the content to the structural subdivisions of the Ministry. The appeal is considered within 30 days from the date of registration. An electronic appeal containing issues, the solution of which is not within the competence of the Ministry of Construction of Russia, is sent within seven days from the date of registration to the appropriate body or the appropriate official, whose competence includes resolving the issues raised in the appeal, with notification of this to the citizen who sent the appeal.

5. An electronic appeal is not considered when:
- the absence of the name and surname of the applicant;
- indication of an incomplete or inaccurate postal address;
- the presence of obscene or offensive expressions in the text;
- the presence in the text of a threat to life, health and property official as well as members of his family;
- using a non-Cyrillic keyboard layout or only capital letters when typing;
- the absence of punctuation marks in the text, the presence of incomprehensible abbreviations;
- the presence in the text of a question to which the applicant has already received a written answer on the merits in connection with previously sent appeals.

6. The response to the applicant of the appeal is sent to the postal address specified when filling out the form.

7. When considering an appeal, it is not allowed to disclose the information contained in the appeal, as well as information relating to privacy citizen without his consent. Information about the personal data of applicants is stored and processed in compliance with the requirements of Russian legislation on personal data.

8. Appeals received through the site are summarized and submitted to the leadership of the Ministry for information. The answers to the most frequently asked questions are periodically published in the sections "for residents" and "for specialists"